Re: 10204 RAC upgrade

  • From: Harel Safra <harel.safra@xxxxxxxxx>
  • To: smishra_97@xxxxxxxxx
  • Date: Mon, 15 Feb 2010 07:40:13 +0200

About 2, Since the installation and copy of the CRS is done with the CRS up an all the nodes, I believe you can do that before the down time window and then run root102.sh in the window.


Harel Safra

On 14/02/2010 23:07, Sanjay Mishra wrote:
Hi
I had to upgrade one of the 8 Node RAC environment and it is running 5 Database with ASM and RDBMS with it own Home in 10.2.0.3 on AIX. We have only 2-3 hrs window and so want to have expert opinion on the following

   1. If I will upgrade CRS and it suggest at the end of successfull
      install to run *_root102.sh_ on all NODES* Can I run on all node
      in parallel. It takes 10-15 minutes and so want to save some
      time. Not clear if it affect each other as anyway CRS is down at
      that time on that node
   2. Can I run the CRS upgrade indiviual on all node at the same time
      from few new putty session instead of initiating from one window
      and selecting all nodes. The reason is that it will take 15
      Minutes to upgrade on Node 1 and then 15 minutes to copy to
      other nodes. If there are 7 more nodes, then it will take
      15*7=100+ min. to copy to other nodes. So I f will run
      seperately from each nodes, it will be total of 15-20 minutes
      for Software and then 15 minutes for root102.sh.
   3. If CRS is upgraded and is down, Can I start the ASM and RDBMS
      upgrade at the same time or it will conflict due to
      /tmp/installer Lock files or any other issue can come.

TIA
Sanjay