[highland-discuss] Re: IMPORTANT: Road Work Next Week - Temporary Road Closure

  • From: "Alex Agle" <dmarc-noreply@xxxxxxxxxxxxx> (Redacted sender "alex" for DMARC)
  • To: highland-discuss@xxxxxxxxxxxxx
  • Date: Wed, 29 Apr 2020 09:51:16 -0400

Next week. 4th, 5th, or 6th of May.  Most likely the 4th based on weather 
outlook. 

Alex Agle
alex@xxxxxxxxx
C 404-229-3325
W 404-894-6165

On Apr 29, 2020, at 9:37 AM, NITA STEWART <nitaastewart@xxxxxxx> wrote:


Hi Alex, can you give us the date of the projects, Monday or Tuesday or 
Wednesday? Thank you 

Get Outlook for Android

From: highland-discuss-bounce@xxxxxxxxxxxxx 
<highland-discuss-bounce@xxxxxxxxxxxxx> on behalf of Joseph Curtis 
<josephcurtis07@xxxxxxxxxxx>
Sent: Tuesday, April 28, 2020 4:59:32 PM
To: highland-discuss@xxxxxxxxxxxxx <highland-discuss@xxxxxxxxxxxxx>
Subject: [highland-discuss] Re: IMPORTANT: Road Work Next Week - Temporary 
Road Closure
 
So are we printing up a letter for each household and placing them on the 
door. I don’t think everyone is going to get the message in the list serve. 
Also are we going to put up some sort of road block at the gate so we don’t 
have a repeat of the last time? The way it is now, we have no control over 
delivery of ups or anything else.
Thanks 
Sent from my iPhone

On Apr 28, 2020, at 4:22 PM, Alex Agle (Redacted sender alex for DMARC) 
<dmarc-noreply@xxxxxxxxxxxxx> wrote:


Hi everyone,

This email is being sent so that you can begin planning now.  More 
information on the exact dates and times will follow.

The HOA is currently in the final stages of planning the sealcoat project.  
This is where cracks in the road are filled, and a tar spray paint is 
applied to the road's surface.  The coating takes approximately 24 hours to 
cure.  This maintenance is typically performed every 9-10 years, and it 
extends the life of the road.

This project is of a large magnitude and will directly affect each resident. 
 We ask for your understanding and cooperation during the project.  We 
apologize in advance for the inconvenience that you will experience.

The neighborhood road (pavement) will be closed to all vehicles and 
pedestrians for a 24 hour period next week.  You will not be able to drive 
or walk on the pavement.  You may walk on the cement strips that border the 
pavement, and it is possible to reach each unit on foot without stepping on 
the pavement.

The exact day is still to be determined, but we are aiming for Monday with 
Tuesday and Wednesday as backup days, depending on weather.  If there is 
more than a 30-40% chance of rain, then the project will be postponed to the 
next day.  Most likely it will be an 8AM-8AM period.  We will provide more 
details before the end of the week. 

Preparation steps for residents:

1. Avoid scheduling deliveries or pickups between Monday - Wednesday.  In 
the event that a delivery or pickup cannot be made, they will make another 
attempt the next day.

2. Avoid scheduling contractors or moving trucks.

3. Vehicles that are parked in driveways cannot cover the cement strip on 
the day of the project, or they will be towed.  Typically these are larger 
trucks that occupy the full length of the driveway.  The logic here is that 
these cement strips will serve as temporary sidewalks to allow people to 
access their units on foot.  We will place notices on these vehicles ahead 
of time to increase awareness.  We will also attempt to make contact with 
affected units before calling for a tow.

4. Guest parking spaces must be vacated by 8AM on the day of the project, or 
vehicles will be towed.

5. Remove your car from your driveway or garage by 8AM on the day of the 
project if you plan to drive that day.  If you don't plan to drive, then it 
is fine to leave your vehicle in your garage or driveway. 

Vehicles in driveways have little risk of the spray being blown but 
residents are encouraged to put their vehicle(s) in the garage, off the 
property, or cover the vehicle during the day of repair.

BluePrint Painting and Renovations, the Highland Unit Owners Association, 
and Community Management Associates will not be held responsible should this 
occur, so please take appropriate precautions.

6. If you plan to drive on the day of the project, you will need to park 
your vehicle outside of the neighborhood for one night.  Possible parking 
options are Hilliard St, the grassy lot across the street from Hilliard, 
Cain St (near Jackson St bridge), and the Atlanta Medical Center (AMC) 
parking lot (across from Highland).  The AMC option is the most secure, and 
there is a $6 charge.

7. Make mental notes on how you can access your unit on foot without walking 
on the pavement.  Note that the 400 and 500 buildings can only be accessed 
via the rear pedestrian gate.

Residents who walk or drive on uncured sealcoat will be fined a minimum of 
$500, plus the cost to repair or replace the damaged areas!  During the last 
project, a UPS truck drove onto uncured sealcoat, and you can still see tire 
marks near the 900 building.

Thanks,
Alex

-- 
Alex Agle
alex@xxxxxxxxx
C 404-229-3325
W 404-894-6165