[deanwoodcitizens] Re: Project Update For Your Area-Small Diameter Water Main Replacement Project in the Deanwood Neighborhood

  • From: David Smith <deanwoodcdc@xxxxxxxxx>
  • To: deanwoodcitizens@xxxxxxxxxxxxx
  • Date: Mon, 15 Mar 2021 12:50:45 -0400

Me. Briggs,

Is there a consistent testing of lead and metal levels due pipe replacement.  
We have seen brown and cloudy water in Deanwood.  Can we get regular updates of 
the results of water quality during these replacements?

Also, does DC water provide water filters for kitchen sinks and drinking water?

David Smith
Deanwood CDC



On Mar 15, 2021, at 10:23 AM, Emanuel D. Briggs <Emanuel.Briggs@xxxxxxxxxxx> 
wrote:


<image002.jpg>
 
 
PROJECT UPDATE
Monday, March 15, 2021
Manager, Community Outreach: Emanuel D. Briggs               
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx

Greetings DC Water Community Stakeholders:   
Please see our revised list of ongoing and upcoming construction activities-
Active Work Location: Jay Street NE
 
Week of March 15
 
We have successfully completed the installation of 300 linear feet of new 
8-inch water mains on Jay Street, between 48th Street and 48th Place.
 
We have nearly completed the installation of 300 linear feet of new 8-inch 
water mains on Jay Street, between 48th Place and 49th Street, and are now 
scheduled to complete this portion of work during this week.  
 
Testing and disinfection of newly installed water mains at Jay Street work 
locations is still on schedule to take place throughout this week.
 
Week of March 29
 
We are now scheduling to install new water services at some Jay Street work 
locations from Thursday, April 1 through Monday, April 19.
 
-----------------------------------------------------------------------------------------------------------------------------------
 
Active Work Location: Hunt Place NE
 
Week of March 15
 
We are still scheduled to work on installation of 350 linear feet of new 
8-inch water mains on 44th Street, between Jay Street and Hunt Place from 
Monday, March 15 – Tuesday, March 23.  
 
Week of March 22
 
We are still scheduled to work on installation of new 8-inch water mains on 
Hunt Place, between 44th Street and 46th Street from Wednesday, March 24 – 
Friday, April 16.
 
 
Please keep in mind that all construction activities are highly dependent 
upon favorable weather conditions.
 
Thanks much, please stay tuned for more updates, and make it a wonderful 
week…..ON PURPOSE!!
 
 
From: Emanuel D. Briggs 
Sent: Monday, March 8, 2021 6:05 PM
To: Emanuel D. Briggs <Emanuel.Briggs@xxxxxxxxxxx>
Cc: Emanuel D. Briggs <Emanuel.Briggs@xxxxxxxxxxx>
Subject: RE: Project Update For Your Area-Small Diameter Water Main 
Replacement Project in the Deanwood Neighborhood
 
<image002.jpg>
 
 
PROJECT UPDATE
Monday, March 8, 2021
Manager, Community Outreach: Emanuel D. Briggs               
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx

Greetings DC Water Community Stakeholders:   
Please see our revised list of ongoing and upcoming construction activities-
 
Active Work Location: Jay Street NE
 
Week of March 8
 
We have nearly completed the installation of 300 linear feet of new 8-inch 
water mains on Jay Street, between 48th Street and 48th Place, and are now 
scheduled to complete this portion of work today.
 
We are now scheduled to begin installation of 300 linear feet of new 8-inch 
water mains on Jay Street, between 48th Place and 49th Street on Tuesday, 
March 9; we are now scheduled to complete this portion of work by Friday, 
March 12.
 
Week of March 15
 
Testing and disinfection of newly installed water mains at Jay Street work 
locations is now scheduled to take place from Monday, March 15 through 
Friday, March 19.
 
Week of March 29
 
We are now scheduling to install new water services at some Jay Street work 
locations from Monday, March 29 through Wednesday, April 14.
 
-----------------------------------------------------------------------------------------------------------------------------------
 
Active Work Location: Hunt Place NE
 
Week of March 15
 
We are now scheduled to begin installation of 350 linear feet of new 8-inch 
water mains on 44th Street, between Jay Street and Hunt Place on Monday, 
March 15; we are now scheduled to complete this portion of work by Tuesday, 
March 23.
 
Week of March 22
 
We are scheduled to begin installation of new 8-inch water mains on Hunt 
Place between 44th Street and 46th Street on Wednesday, March 24; we are 
scheduled to complete this portion of work by Friday, April 16.
 
--------------------------------------------------------------------------------------------------------------------------------------
 
As a final piece of information for this week’s update, we want to inform you 
of a separate notification that many of you have already begun receiving from 
DC Water. As some of you may be aware, prior to any scheduled water shut-offs 
we will have for water main tie-ins as part of this project, we will need to 
conduct what we call “test-shuts”. During test-shuts, we will essentially 
need to visit the area and check valves along the existing mains in order to 
identify operational valves that will be needed to turn off water inside the 
mains when we need to conduct this phase of work. In testing the valves, we 
will essentially be turning them on and off for brief intervals, so some 
residents will experience brief interruptions in their water service during 
these test-shuts. We will be conducting a series test-shuts in your area on 
the following dates:
 
Tuesday, March 9 – Test-shuts will be conducted in the 44th Street and Nannie 
Helen Burroughs Avenue area  
Wednesday, March 10 – Test shuts will be conducted in the 48th and Hayes 
Streets area
Thursday, March 11 – Test shuts will be conducted in the 47th Place and Jay 
Street area
 
All test-shuts are scheduled to start at 9:30am and last for approximately 
2-4 hours.
 
Now, for the notification information – besides this update from me, all 
customers whom will be affected by these test-shuts are also receiving 
notifications via our ‘Everbridge’ automated notification system. Affected 
customers will be receiving this separate notification to both their email 
and telephone accounts that we have on file for them. Should any of you 
receive these notifications, we just want you to be aware of them, and not be 
alarmed. This is all being done as step toward improving our outreach and 
notification efforts to inform our valued customers of scheduled water 
shut-offs.
----------------------------------------------------------------------------------------------------------------------------------------
 
Please keep in mind that all construction activities are highly dependent 
upon favorable weather conditions.
 
Thanks much, please stay tuned for more updates, and make it a wonderful 
week…..ON PURPOSE!!
 
 
From: Emanuel D. Briggs 
Sent: Monday, March 1, 2021 8:23 AM
To: Emanuel D. Briggs <Emanuel.Briggs@xxxxxxxxxxx>
Cc: Emanuel D. Briggs <Emanuel.Briggs@xxxxxxxxxxx>
Subject: RE: Project Update For Your Area-Small Diameter Water Main 
Replacement Project in the Deanwood Neighborhood
 
<image003.jpg>
 
 
PROJECT UPDATE
Monday, March 1, 2021
Manager, Community Outreach: Emanuel D. Briggs               
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx

Greetings DC Water Community Stakeholders:   
Please see our revised list of ongoing and upcoming construction activities-
 
Active Work Location: Jay Street NE
 
Week of March 1
 
We have more than halfway completed the installation of 300 linear feet of 
new 8-inch water mains on Jay Street, between 48th Street and 48th Place, and 
are now scheduled to complete this portion of work by Wednesday, March 3.
 
Week of March 8
 
We are now scheduled to begin installation of 300 linear feet of new 8-inch 
water mains on Jay Street, between 48th Place and 49th Street on Thursday, 
March 4; we are now scheduled to complete this portion of work by Tuesday, 
March 9.
 
Week of March 15
 
Testing and disinfection of newly installed water mains at Jay Street work 
locations is now scheduled to take place from Wednesday, March 10 through 
Tuesday, March 16.
 
We are still scheduled to install new water services at some Jay Street work 
locations from Monday, March 1 through Tuesday, March 16.
As mentioned in a previous update, during this portion of work we will be 
connecting the new water service lines to homes in these blocks to the newly 
installed water mains. As a reminder, please see below specific details on 
what residents can expect to see during installation of new water services.
 
Typically, during installation of new water services, you will see the 
following:
We will begin to paint the areas where we will be working, so you may begin 
to see paint markings on the sidewalk, portions of the roadway, and even on 
portions of yard spaces.
Essentially, we will be replacing the portions of water service lines feeding 
homes in the block on the city (public space) side. This could include 
replacing portions of lead service lines with copper service lines in public 
space (in cases where the public portion of the service line is lead), and/or 
upgrading the diameter of the service line in public space from ¾ inch up to 
1 inch.
Where property owners may have lead for the portion of their service line 
inside their private property, DC Water will replace this portion of lead 
line with copper if the property owner has signed a Lead Service Replacement 
Agreement with DC Water and a service order for this private side lead line 
replacement has been issued.
We will provide our standard 48-hour advance notification door hanger before 
starting the work.
As property lines vary widely across the District, we understand that for 
many of the properties, portions of the front yard spaces are located in 
public space (property owned by the District). Despite this fact, we 
understand customers’ sensitivity when it comes to disturbances inside yards, 
so we will do our very best to work around plantings and pavers in the public 
space portion of yards; we do strongly suggest that property owners 
temporarily remove these items prior to the work, however, because DC Water 
is not responsible for replacement of these items, if damaged.
Similarly, for portions of yard spaces located inside customers’ private 
property, DC Water is not responsible for replacement of any plantings or 
pavers that are damaged during private side service line replacements. For 
this reason, we ask that customers temporarily remove these items inside 
their private property as well.
We may, on a case-by-case basis, need to perform a test pit in some of the 
yards. This would include a small excavation (dig) in some of the yards in 
order to access the pipe and/or move the water meter from the private 
property over into the public space for future access, if needed. We just 
want to make sure you have this information.  
 
 
 
Active Work Location: Hunt Place NE
 
Week of March 8
 
We are now scheduled to begin installation of 350 linear feet of new 8-inch 
water mains on 44th Street, between Jay Street and Hunt Place on Wednesday, 
March 10; we are now scheduled to complete this portion of work by Thursday, 
March 18.
 
 
 
Please keep in mind that these construction activities are highly dependent 
upon favorable weather conditions.
 
Thanks much, please stay tuned for more updates, and make it a wonderful 
week…..ON PURPOSE!!
 
 
From: Emanuel D. Briggs 
Sent: Monday, February 22, 2021 1:28 PM
To: Emanuel D. Briggs <Emanuel.Briggs@xxxxxxxxxxx>
Cc: Emanuel D. Briggs <Emanuel.Briggs@xxxxxxxxxxx>
Subject: RE: Project Update For Your Area-Small Diameter Water Main 
Replacement Project in the Deanwood Neighborhood
 
<image004.jpg>
 
 
PROJECT UPDATE
Monday, February 22, 2021
Manager, Community Outreach: Emanuel D. Briggs               
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx

Greetings DC Water Community Stakeholders:  
In addition to the weekly update you’ve just received this morning, we also 
wanted to inform you that our Contractor will be working at Jay Street NE and 
43rd Place NE this coming Wednesday (February 24) beginning at 9:30am to tie 
newly installed 8-inch water mains into the existing drinking water 
distribution system.
This portion of work will take approximately 8 hours to complete, and will 
result in scheduled water service outage to the following addresses during 
the tie-in:
4300 block of Jay Street NE
4302-4308 Nannie Helen Burroughs Avenue NE
900 block of 43rd Place NE
4235 Sheriff Road NE
All affected customers listed above have received our standard 48-hour 
notification prior to the work and water outage.
 
We apologize for any inconvenience, and thank you for your patience and 
cooperation as we complete this critical portion of work.
 
Please let us know if you have any questions.
 
From: Emanuel D. Briggs 
Sent: Monday, February 22, 2021 11:10 AM
To: Emanuel D. Briggs <Emanuel.Briggs@xxxxxxxxxxx>
Cc: Emanuel D. Briggs <Emanuel.Briggs@xxxxxxxxxxx>
Subject: RE: Project Update For Your Area-Small Diameter Water Main 
Replacement Project in the Deanwood Neighborhood
 
 
<image004.jpg>
 
 
PROJECT UPDATE
Monday, February 22, 2021
Manager, Community Outreach: Emanuel D. Briggs               
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx

Greetings DC Water Community Stakeholders:   
Please see our revised list of ongoing and upcoming construction activities-
 
Active Work Location: Jay Street NE
 
Week of February 15
 
As of last week, we have successfully completed the installation of 250 
linear feet of new 8-inch water mains on Jay Street, between 47th Place and 
48th Street.
 
Week of February 22
 
We have begun the installation of 300 linear feet of new 8-inch water mains 
on Jay Street, between 48th Street and 48th Place, and are still scheduled to 
complete this portion of work by Friday, February 26.
 
Week of March 1
 
We are still scheduled to begin installation of 300 linear feet of new 8-inch 
water mains on Jay Street, between 48th Place and 49th Street on Monday, 
March 1; we are also still scheduled to complete this portion of work by 
Thursday, March 4.
 
We will be performing testing and disinfection of newly installed water mains 
at all above listed Jay Street locations from Friday, March 5 through 
Thursday, March 11.
 
We will be installing new water services at all above listed Jay Street 
locations from Monday, March 1 through Tuesday, March 16.
 
 
Active Work Location: Hunt Place NE
 
Week of March 1
 
We are scheduled to begin installation of new 8-inch water mains on 44th 
Street, between Jay Street and Hunt Place on Friday, March 5; we are 
scheduled to complete this portion of work by Monday, March 15.
 
 
Please keep in mind that these construction activities are highly dependent 
upon favorable weather conditions.
 
Thanks much, please stay tuned for more updates, and make it a wonderful 
week…..ON PURPOSE!!
 
 
From: Emanuel D. Briggs 
Sent: Tuesday, February 16, 2021 10:17 AM
To: Emanuel D. Briggs <Emanuel.Briggs@xxxxxxxxxxx>
Cc: Emanuel D. Briggs <Emanuel.Briggs@xxxxxxxxxxx>
Subject: RE: Project Update For Your Area-Small Diameter Water Main 
Replacement Project in the Deanwood Neighborhood
 
<image004.jpg>
 
 
PROJECT UPDATE
Tuesday, February 16, 2021
Manager, Community Outreach: Emanuel D. Briggs               
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx

Greetings DC Water Community Stakeholders:   
Please see our revised list of ongoing and upcoming construction activities-
Active Work Location: Jay Street NE
 
Week of February 15
 
Testing and disinfection of newly installed water mains on Jay Street are 
still ongoing.
 
We have begun the installation of 250 linear feet of new 8-inch water mains 
on Jay Street, between 47th Place and 48th Street, and we are now scheduled 
to complete this portion of work by tomorrow, February 17.
For this location, we are now scheduled to install new water services from 
Wednesday, February 24 through Thursday, March 11.
 
Week of February 22
 
We are now planning to begin the installation of 300 linear feet of new 
8-inch water mains on Jay Street, between 48th Street and 48th Place on 
Thursday, February 18; we are now scheduled to complete this portion of work 
on Friday, February 26.
 
Week of March 1
 
We are scheduled to begin installation of 300 linear feet of new 8-inch water 
mains on Jay Street, between 48th Place and 49th Street on Monday, March 1; 
we are scheduled to complete this portion of work on Thursday, March 4.
 
 
Please keep in mind that these construction activities are highly dependent 
upon favorable weather conditions.
 
Thanks much, please stay tuned for more updates, and make it a wonderful 
week…..ON PURPOSE!!
 
 
From: Emanuel D. Briggs 
Sent: Tuesday, February 9, 2021 7:08 AM
To: Emanuel D. Briggs <Emanuel.Briggs@xxxxxxxxxxx>
Cc: Emanuel D. Briggs <Emanuel.Briggs@xxxxxxxxxxx>
Subject: RE: Project Update For Your Area-Small Diameter Water Main 
Replacement Project in the Deanwood Neighborhood
 
<image004.jpg>
 
 
PROJECT UPDATE
Tuesday, February 9, 2021
Manager, Community Outreach: Emanuel D. Briggs               
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx

Greetings DC Water Community Stakeholders:   
Please see our revised list of ongoing and upcoming construction activities-
Active Work Location: Jay Street NE
 
Weeks of February 8 and February 15
 
We have successfully completed the installation of 250 linear feet of new 
8-inch water mains on Jay Street, between 47th Street and 47th Place.
 
We have begun testing and disinfection of the newly installed water mains on 
Jay Street, and these procedures are still ongoing.
 
We have begun the installation of 250 linear feet of new 8-inch water mains 
on Jay Street, between 47th Place and 48th Street, and we are now scheduled 
to complete this portion of work by Tuesday, February 16.
For this location, we are tentatively scheduled to install new water services 
from Wednesday, February 10 through Friday, February 26. During this phase of 
work, we will be connecting the water service lines to homes in these blocks 
to the newly installed water mains. Please see below specific details on what 
residents can expect to see during installation of new water services.
 
Week of February 22
 
We are now planning to begin the installation of 300 linear feet of new 
8-inch water mains on Jay Street, between 48th Street and 48th Place on 
Wednesday, February 17; we are now scheduled to complete this portion of work 
on Thursday, February 25.
 
Typically, during installation of new water services, you will see the 
following:
We will begin to paint the areas where we will be working, so you may begin 
to see paint markings on the sidewalk, portions of the roadway, and even on 
portions of yard spaces.
Essentially, we will be replacing the portions of water service lines feeding 
homes in the block on the city (public space) side. This could include 
replacing portions of lead service lines with copper service lines in public 
space (in cases where the public portion of the service line is lead), and/or 
upgrading the diameter of the service line in public space from ¾ inch up to 
1 inch.
Where property owners may have lead for the portion of their service line 
inside their private property, DC Water will replace this portion of lead 
line with copper if the property owner has signed a Lead Service Replacement 
Agreement with DC Water and a service order for this private side lead line 
replacement has been issued.
We will provide our standard 48-hour advance notification door hanger before 
starting the work.
As property lines vary widely across the District, we understand that for 
many of the properties, portions of the front yard spaces are located in 
public space (property owned by the District). Despite this fact, we 
understand customers’ sensitivity when it comes to disturbances inside yards, 
so we will do our very best to work around plantings and pavers in the public 
space portion of yards; we do strongly suggest that property owners 
temporarily remove these items prior to the work, however, because DC Water 
is not responsible for replacement of these items, if damaged.
Similarly, for portions of yard spaces located inside customers’ private 
property, DC Water is not responsible for replacement of any plantings or 
pavers that are damaged during private side service line replacements. For 
this reason, we ask that customers temporarily remove these items inside 
their private property as well.
We may, on a case-by-case basis, need to perform a test pit in some of the 
yards. This would include a small excavation (dig) in some of the yards in 
order to access the pipe and/or move the water meter from the private 
property over into the public space for future access, if needed. We just 
want to make sure you have this information.  
 
 
 
Please note that in observation of the “Presidents’ Day” Holiday, we will not 
be performing any construction activities on Monday, February 15.  
 
Please also keep in mind that these construction activities are highly 
dependent upon favorable weather conditions.
 
Thanks much, please stay tuned for more updates, and make it a wonderful 
week…..ON PURPOSE!!
 
 
From: Emanuel D. Briggs 
Sent: Tuesday, February 2, 2021 10:35 AM
To: Emanuel D. Briggs <Emanuel.Briggs@xxxxxxxxxxx>
Cc: Emanuel D. Briggs <Emanuel.Briggs@xxxxxxxxxxx>
Subject: RE: Project Update For Your Area-Small Diameter Water Main 
Replacement Project in the Deanwood Neighborhood
 
<image005.jpg>
 
 
PROJECT UPDATE
Tuesday, February 2, 2021
Manager, Community Outreach: Emanuel D. Briggs               
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx

Greetings DC Water Community Stakeholders:   
Please see our list of ongoing and upcoming construction activities-
Active Work Location: Jay Street NE
 
Weeks of January 25, February 1 and February 8
 
We have successfully completed the new water main installations on Jay 
Street, between 46th Street and 47th Street.
 
We have begun installation of 250 linear feet of new 8-inch water mains on 
Jay Street, between 47th Street and 47th Place. We were originally scheduled 
to complete this portion of work by Wednesday, February 3, but this week’s 
inclement weather has caused a slight delay. Currently, we are tentatively 
slated to complete this portion of work by Friday, February 5.
 
We have begun testing and disinfection of the newly installed water mains on 
Jay Street, and these procedures are ongoing.
 
We are still scheduled to begin installation of 250 linear feet of new 8-inch 
water mains on Jay Street, between 47th Place and 48th Street on Thursday, 
February 4, and complete this portion of work by Friday, February 12.
For this location, we are tentatively scheduled to perform water service 
reconnections from Wednesday, February 10 through Friday, February 26. During 
this phase of work, we will be connecting the water service lines to homes in 
these blocks to the newly installed water mains. In the next update, we will 
provide more specific details on what residents can expect to see during 
water service reconnections.
 
Weeks of February 15 and February 22
 
We are planning to begin installation of 300 linear feet of new 8-inch water 
mains on Jay Street, between 48th Street and 48th Place on Tuesday, February 
16. We are scheduled to complete this portion of work on Wednesday, February 
24.
 
 
As noted above, this week’s activities are slightly delayed in light of our 
inclement weather event.
 
Thanks much, please stay tuned for more updates, and enjoy your snowy 
Tuesday…..BURR!!!!!
 
 
From: Emanuel D. Briggs 
Sent: Monday, January 25, 2021 8:58 AM
To: Emanuel D. Briggs <Emanuel.Briggs@xxxxxxxxxxx>
Cc: Emanuel D. Briggs <Emanuel.Briggs@xxxxxxxxxxx>
Subject: RE: Project Update For Your Area-Small Diameter Water Main 
Replacement Project in the Deanwood Neighborhood
 
 
<image005.jpg>
 
 
PROJECT UPDATE
Monday, January 25, 2021
Manager, Community Outreach: Emanuel D. Briggs               
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx

Greetings DC Water Community Stakeholders:   
Please see our revised list of upcoming construction activities for the next 
three weeks-
Active Work Location: Jay Street NE
 
Week of January 25
 
We have nearly completed the new water main installation on Jay Street, 
between 46th Street and 47th Street. We are now scheduled to complete this 
portion of work by tomorrow- Tuesday, January 26.
 
We are now scheduled to begin installation of 250 linear feet of new 8-inch 
water mains on Jay Street, between 47th Street and 47th Place on this coming 
Wednesday, January 27. We should complete this portion of work by the 
following Wednesday, February 3.
 
 
Weeks of February 1 and February 8
 
We are now scheduled to begin testing and disinfection of the newly installed 
water mains on Jay Street on Thursday, February 4. We are scheduled to 
complete these activities on the following Monday, February 8.
 
Concurrently with testing and disinfection of newly installed water mains, we 
will also begin installation of new 8-inch water mains on Jay Street, between 
47th Place and 48th Street on Thursday, February 4. We are scheduled to 
complete this portion of work on Friday, February 12.
 
 
Please keep in mind that the completion dates for these activities are all 
highly dependent upon favorable weather conditions.
 
Thanks much, please stay tuned for more updates, and make it a wonderful 
week…ON PURPOSE!
 
 
From: Emanuel D. Briggs 
Sent: Monday, January 18, 2021 11:16 AM
To: Emanuel D. Briggs <Emanuel.Briggs@xxxxxxxxxxx>
Cc: Emanuel D. Briggs <Emanuel.Briggs@xxxxxxxxxxx>
Subject: RE: Project Update For Your Area-Small Diameter Water Main 
Replacement Project in the Deanwood Neighborhood
 
<image005.jpg>
 
 
PROJECT UPDATE
Monday, January 18, 2021
Manager, Community Outreach: Emanuel D. Briggs               
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx

Greetings DC Water Community Stakeholders:   
Please see our revised list of upcoming construction activities for the next 
three weeks-
Active Work Location: Jay Street NE
 
Week of January 18
 
Per last week’s update, we have successfully completed installation of 300 
linear feet of new 8-inch water mains on Jay Street, between 45th Place and 
46th Street.
 
We have completed about 60 percent of the new water main installation on Jay 
Street, between 46th Street and 47th Street. We are now scheduled to complete 
this portion of work on this coming Friday, January 22.
 
Week of January 25
 
We are now scheduled to begin installation of 250 linear feet of new 8-inch 
water mains on Jay Street, between 47th Street and 47th Place on next Monday, 
January 25. We should complete this portion of work by the following Monday, 
February 1.
 
Week of February 1
 
We are now scheduled to begin testing and disinfection of the newly installed 
water mains at all above listed work locations on Tuesday, February 2. We are 
scheduled to complete these activities on the following Monday, February 8.
 
Concurrently with testing and disinfection of newly installed water mains, we 
will also begin installation of new 8-inch water mains on Jay Street, between 
47th Place and 48th Street on Tuesday, February 2. We are scheduled to 
complete this portion of work on the following Wednesday, February 10.
 
 
In observance of the Rev. Dr. Martin Luther King, Jr. Day Holiday, there will 
be no construction activities taking place on Monday, January 18.
 
Also, in observance of the 59th Presidential Inauguration Event, there will 
be no construction activities taking place on Wednesday, January 20.
 
 
Please keep in mind that the completion dates for these activities are all 
highly dependent upon favorable weather conditions.
 
Thanks much, please stay tuned for more updates, and make it a wonderful 
week…ON PURPOSE!
 
 
From: Emanuel D. Briggs 
Sent: Tuesday, January 12, 2021 7:48 AM
To: Emanuel D. Briggs <Emanuel.Briggs@xxxxxxxxxxx>
Cc: Emanuel D. Briggs <Emanuel.Briggs@xxxxxxxxxxx>
Subject: RE: Project Update For Your Area-Small Diameter Water Main 
Replacement Project in the Deanwood Neighborhood
 
 
<image005.jpg>
 
 
PROJECT UPDATE
Tuesday, January 12, 2021
Manager, Community Outreach: Emanuel D. Briggs               
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx

Greetings DC Water Community Stakeholders:   
In keeping with our last update sent to you regarding our Small Diameter 
Water Main Replacement Project in your area, our Contractor is still working 
on Jay Street NE. Please see our list of current and upcoming construction 
activities for this location-
Active Work Location: Jay Street NE
 
Week of January 11
 
We have nearly completed installation of 300 linear feet of new 8-inch water 
mains on Jay Street, between 45th Place and 46th Street. We are scheduled to 
complete this portion of work this week.
 
Today, we are scheduled to begin installation of 250 linear feet of new 
8-inch water mains on Jay Street, between 46th Street and 47th Street. We are 
scheduled to complete this portion of work on Wednesday, January 20.
 
Week of January 18
 
On Thursday, January 21, we are scheduled to begin installation of 250 linear 
feet of new 8-inch water mains on Jay Street, between 47th Street and 47th 
Place. We are scheduled to complete this portion of work on Thursday, January 
28.
 
Week of January 25
 
On Friday, January 29, we will begin testing and disinfection of the newly 
installed water mains at these locations. We are scheduled to complete these 
activities on Thursday, February 4.
 
In observance of the Rev. Dr. Martin Luther King, Jr. Day Holiday, there will 
be no construction activities taking place on Monday, January 18.
 
Also, in observance of the 59th Presidential Inauguration Event, there will 
be no construction activities taking place on Wednesday, January 20.
 
 
Please keep in mind that the completion dates for these activities are all 
highly dependent upon favorable weather conditions.
 
Thanks much, please stay tuned for more updates, and have a great and 
productive week!!!!!
 
From: Emanuel D. Briggs 
Sent: Thursday, December 10, 2020 10:57 PM
To: Emanuel D. Briggs <Emanuel.Briggs@xxxxxxxxxxx>
Cc: Emanuel D. Briggs <Emanuel.Briggs@xxxxxxxxxxx>
Subject: RE: Project Update For Your Area-Small Diameter Water Main 
Replacement Project in the Deanwood Neighborhood
 
<image005.jpg>
PROJECT UPDATE
Thursday, December 10, 2020
Manager, Community Outreach: Emanuel D. Briggs               
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx

Greetings DC Water Community Stakeholders:   
As you may recall from the notification that we’d emailed to you on 10/16 
(below), our upcoming Small Diameter Water Main Replacement Project in the 
Deanwood Neighborhood was set to start in early November. I have re-attached 
our project information sheet to this update to re-familiarize you with the 
project. The primary purpose for this new update is to inform you that we did 
officially start our construction activities on some of the project area 
streets last month.
 
To date, our Contractor has surveyed and mobilized on the following streets: 
Hayes Street NE and Jay Street NE. Mobilization activities include 
installation of tree protection fencing, project signs, equipment staging 
site, and other related activities. Please see below a list of completed and 
current construction activities and applicable dates for the work:
 
Active Work Location: Jay Street NE
Monday, November 9 – Monday, November 16
During that week, we successfully completed installation of 300 linear feet 
of new 8-inch water mains on Jay Street NE, from 43rd Place NE to 44th Street 
NE
 
Tuesday, November 17 – Friday, November 27
During that week, we successfully completed installation of 500 linear feet 
of new 8-inch water mains on Jay Street NE, from 44th Street NE to 45th Place 
NE
 
Friday, November 27 – Friday, December 4
During that week, we successfully completed installation of 300 linear feet 
of new 8-inch water mains on Jay Street NE, from 45th Place NE to 46th Street 
NE
 
Friday, December 4 – Thursday, December 10
Currently, we are installing 250 linear feet of new 8-inch water mains on Jay 
Street NE, from 46th Street NE to 47th Street NE
Moving forward, we will be sending you regular weekly updates to keep you 
informed of our ongoing activities.
 
Please have a great weekend, stay tuned for future updates, and let us know 
if you have any questions.
 
From: Emanuel D. Briggs 
Sent: Friday, October 16, 2020 8:39 AM
To: Emanuel D. Briggs <Emanuel.Briggs@xxxxxxxxxxx>
Cc: Emanuel D. Briggs <Emanuel.Briggs@xxxxxxxxxxx>
Subject: RE: New DC Water Project In Your Area-Small Diameter Water Main 
Replacement Project in the Deanwood Neighborhood
 
 
<image005.jpg>
NEW DC WATER PROJECT IN YOUR AREA
Friday, October 16, 2020
Manager, Community Outreach: Emanuel D. Briggs               
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx

Greetings DC Water Community Stakeholders:   
This message is intended to inform you of a new DC Water construction project 
that will soon begin in your area. As part of its Capital Improvement 
Program, DC Water is replacing existing 12-inch and smaller cast iron water 
mains in various locations throughout the city.  Overall benefits of these 
projects include improved water quality and system reliability. Construction 
activities for this project will take place in the Deanwood neighborhood. The 
scope of work will include installation of approximately 9,700 linear feet of 
4-inch up to 12-inch water mains; replacement of service lines (lead and/or 
other), as needed; replacement of fire hydrants and valves; and restoration 
of all surfaces disturbed by the project construction upon completion of the 
work.
 
The project is scheduled to start early next month, and be completed by 
August 2021. The normal work hours will be from 7:00am to 5:00pm, Monday 
through Friday. However, as construction moves forward there may be portions 
of work that need to be completed at night and/or on weekends due to 
inclement weather or other unforeseen circumstances-every attempt will be 
made to keep these occurrences to a minimum. This and other important 
information may be found on the attached project information sheet.
 
As part of our regular construction outreach program, we will provide the 
following:
This e-mail message and attached project information sheet are being shared 
with some local area residents, businesses and community organizations that 
will be directly impacted by the project construction; all ANC 7C and 7D 
Commissioners; Ward 7 representatives in the Mayor’s Office of Community 
Relations and Services; and Ward 7 Councilmember Vincent Gray and members of 
his staff.
This project information will be posted to our website at www.dcwater.com and 
updated regularly.
Our Contractor will be going out beginning next week to hand deliver printed 
copies of the attached project information sheet to all customers that will 
be directly impacted by the project construction.
As our project gets underway, we will be providing you regular weekly email 
updates to keep you informed about our work activities.
We are available to provide you with a presentation to discuss the project’s 
short-term construction impacts and long-term benefits, as well as address 
any concerns you may have. If interested in a presentation, please contact me 
and we will be happy to accommodate you.
 
Thanks much for allowing us to share this important information with you, and 
please let us know if you have any questions.


IMPORTANT NOTICE: 
The security of electronic mail sent through the Internet is not guaranteed. 
DC WATER therefore recommends that you do not send confidential information 
to us via electronic mail, including social security numbers, account 
numbers, and personal identification numbers unless instructed to do so 
through a secured site. Delivery, and timely delivery, of electronic mail is 
also not guaranteed. DC WATER also recommends that you do not send 
time-sensitive or action-oriented messages to us via electronic mail unless 
instructed to do so.

Other related posts: