[ashram-shala] Re: Fw: Re: Plan and Project Tracker_Eklavya (mail from Ishra)

  • From: madhav kelkar <madhavkel@xxxxxxxxx>
  • To: Uma Sudhir <uma.eklavya@xxxxxxxxx>
  • Date: Sun, 21 Jan 2018 22:22:33 +0530

प्रिय उमा, अनिश,  राजेश व आकांक्षा,
फरवरी के प्लान में
1 केआरटी वर्कशॉप
2 लैब अटेंडेंट व असिस्टेंट के साथ वर्कशॉप
3 तीन पीओ में टीचर्स के साथ मंधली मिटिंग करना।

मुझे लगता है हम अगले एक दो दिन में इन तीनों के लिए प्लानिंग नोट तैयार कर
ले। आप इन तीनों के बारे में क्या सोचते है। थोड़ा बताएंगे तो नोट तैयार हो
सकता है।
माधव
On 19-Jan-2018 10:53 am, "Uma Sudhir" <uma.eklavya@xxxxxxxxx> wrote:

Dear All,
I think you should have a summer workshop for the the Amravati teachers
also since we are planning to cover the topics to be covered in the first
four-five months. A couple of reasons - 1) you should bring Amravati in
line with the other regions; no point in planning separately for them 2)
resource group availability and teachers availability - summer mein dono
possible hai - October mein Dushera / Diwali holidays mat kharab karo!!
Regards, Uma

On Fri, Jan 19, 2018 at 10:40 AM, madhav kelkar <madhavkel@xxxxxxxxx>
wrote:

प्रिय उमा,
हमारे सालाना प्लान में अमरावती टीचर्स का अगला रिफ्रेशर शायद अक्टूबर में
है।
लैब अटेंडेंट व असिस्टेंट के साथ वर्कशॉप आपकी व अनिश और रिसोर्स टीचर्स की
मदद से किया जाना है।
पहला वर्कशॉप धारणी के अटेंडेंट व असिस्टेंट के साथ कर रहे हैं। इसमें
टीचर्स किट, स्टुडेंट किट से परिचय, कुछ हैंडेस आन, बच्चों से प्रयोग करवाने
में शिक्षकों की मदद, बच्चों को प्रयोग करने में मार्गदर्शन और लैब को अपटूडेट
रखना आदि बातों को शामिल करना ठीक रहेगा।
आपके कुछ सुझाव हो तो बताए।
पीपीएस - हाई स्कूल टीचर्स वाले एक सवाल का जवाब दोपहर तक देता हूं।
माधव
On 19-Jan-2018 9:58 am, "Uma Sudhir" <uma.eklavya@xxxxxxxxx> wrote:

Dear Madhav,
Like I had said earlier, we need to confirm dates of workshops asap
since we need to book our resource persons well in advance.****!!!!
Nothing else specific that I noted. Sorry for the delay in getting back
to you.
Regards, Uma

**** Why no workshop (in summer) with Amravati teachers?

PS What is being planned for the workshop for the KRT's and lab
attendants in the first half of Feb? Who is doing it? And monthly meetings
with teachers?

PPS What is planned in the workshops with the high & higher sec teachers?

On Thu, Jan 18, 2018 at 4:53 PM, madhav kelkar <madhavkel@xxxxxxxxx>
wrote:

प्रिय सभी,
मैं जनवरी-फरवरी-मार्च 2018 में एटीसी अमरावती, धारणी में किए जाने वाले
प्रमुख टास्क भेज रहा हूं।
इसमें अप्रैल और जून की नागपुर व नासिक की टीचर्स वर्कशॉप भी शामिल है।
आपके जो भी सुझाव हो वो कल दोपहर 12 बजे तक भेज दीजिए।
इसके बाद सुझावों पर काम करके मैं इसे सुश्री इशरत, व एटीसी अमरावती को
भेज दूंगा।
माधव


On 17 January 2018 at 13:56, Rajesh Khindri <
dmarc-noreply@xxxxxxxxxxxxx> wrote:

Anish - Comments embedded in your mail below. - Rajesh
------------------------------------------------------------
---------------------

On Wednesday 17 January 2018, 1:25:13 PM IST, Anish Mokashi <
anish.dot@xxxxxxxxx> wrote:

Dear all,

Nitika, you had sent the document which you were working on. Can you
please put the updated one on the Ashram Shala google drive and share it
with us? We will all go through it line by line.

e.g. I was not sure about line 38 (study on status of high school
science labs) - I thought it was part of the baseline.
*[While we can cover some of these aspects in the baseline, we can
undertake a separate focused study of couple of schools during first six
months to review the status and provide suggestions/guidelines for 
future].*

I am reminded of a point that Satyajit Rath had pointed out - we need
to make sure there is congruence between what the TDD expects and how we
understand it :)
*[**Keeping in touch with the TDD team will help both understand each
other better].*

Shall we go through the tracker file line by line? We can make sure at
least all of us are on the same page.
*[Yes, it will be good if Madhav, you, Uma, Akanksha and Nitika can go
through it in a comprehensive fashion. Others can pitch-in for specific
components and overall review].*

Best, Anish

On 17 January 2018 at 13:05, Rajesh Khindri <
dmarc-noreply@xxxxxxxxxxxxx> wrote:

Missed to share this earlier.
We need to share filled-in tracker with TDD within next two days.
Nitika, Madhav and Anish will need to coordinate, assuming that Uma is
traveling at the moment.
Thanks
Rajesh

----- Forwarded message -----
*From:* Ishrat Jahan <ishratjahaan10@xxxxxxxxx>
*To:* khindriraj <khindriraj@xxxxxxxxx>; madhav kelkar <
madhavkel@xxxxxxxxx>; Anish Mokashi <anish.dot@xxxxxxxxx>; Tultul
Biswas <tultulbiswas@xxxxxxxxx>
*Cc:* Manisha Verma <maniverma100@xxxxxxxxx>; Sunil Patil <
patilsuni@xxxxxxxxx>; Subarao Shinde <subrao.shinde@xxxxxx>; "
dhokelg@xxxxxxxxx" <dhokelg@xxxxxxxxx>
*Sent:* Monday 15 January 2018, 1:17:15 PM IST
*Subject:* Re: Plan and Project Tracker_Eklavya

Dear Rajesh Ji and Team

As discussed earlier, I would request you to please use the tracker
and update the activities as per the plan and implementation. We would 
need
the updated tracker and 6 month plan in the given format by the end of 
this
week.

Thanks
Warm Regards
Ishrat

On Wed, Nov 15, 2017 at 12:15 PM, Ishrat Jahan <
ishratjahaan10@xxxxxxxxx> wrote:

Dear Rajesh Ji

Please see my comments and to streamline the process and keep everyone
on board we have devised a project tracker for our projects. We would
request you to please fill the details in that.

I have marked our CM Fellows also in this mail.

Thanks
Warm Regards
Ishrat






--
MADHAV
EKLAVYA, Malakhedi, Hoshangabad
Mob - 9300683199




Other related posts: