Dear SI expert, I have two loads that I need to support with one clock. I route the clock from the generator to half way between the loads and T off to stubs each going to its target load. I know that the stub needs to be minimize but I can only make so short. Transmission line theory suggest there is a relationship between the stub length and signal rise time? does any know this relation or can point me to an article. Thanks Hura arag abu deeb --------------------------------- Do you Yahoo!? Yahoo! Mail Plus - Powerful. Affordable. Sign up now ------------------------------------------------------------------ To unsubscribe from si-list: si-list-request@xxxxxxxxxxxxx with 'unsubscribe' in the Subject field or to administer your membership from a web page, go to: //www.freelists.org/webpage/si-list For help: si-list-request@xxxxxxxxxxxxx with 'help' in the Subject field List archives are viewable at: //www.freelists.org/archives/si-list or at our remote archives: http://groups.yahoo.com/group/si-list/messages Old (prior to June 6, 2001) list archives are viewable at: http://www.qsl.net/wb6tpu