[TCUG] Re: Power Supply Installation / Connection

  • From: Dick Andrews <dick.andrews@xxxxxxxxxxxx>
  • To: "'tcug@xxxxxxxxxxxxx'" <tcug@xxxxxxxxxxxxx>
  • Date: Thu, 21 Apr 2005 14:58:48 +0100

The supply company has refused to provide a supply until its completion
certifcate is submitted for many years now. In practice they provide a
supply but don't fit a fuse until the certificate is submitted. The
controller is without power only very briefly.

Dick

http://www.devon.gov.uk/email.shtml


-----Original Message-----
From: Chris Mulholland [mailto:sotonutc@xxxxxxxxxxxxxxxxxxx] 
Sent: 21 April 2005 11:35
To: TCUG
Subject: [TCUG] Power Supply Installation / Connection


Has anybody had trouble getting power installed to a site before your
equipment has been installed, i.e. in to a feeder pillar?
We have been told the regulations have now changed and the equipment to be
powered up (signal controller, vms sign, real-time signs etc) has to be
installed and electrical safety checks carried out before the board will
service the site.

If this is the case how long will sensitive equipment have to sit on site
cold and damp before being powered up!!!

Regards,

Chris Mulholland
Southampton City Council
-----------------------------------------------------------
A message from the TCUG mailing list. For information about
the list visit //www.freelists.org/webpage/tcug
-----------------------------------------------------------
A message from the TCUG mailing list. For information about
the list visit //www.freelists.org/webpage/tcug

Other related posts: