I stop by and spoke to the construction manager whose crew is working on
the new Sewer pump construction, along Park Forrest.

1.  They are replacing all of the old plumbing and also upgrading to 6
inch piping from 4 inches.

2.  They expect the entire work to continue for an additional 3 to 4 weeks.

3.  Once completed, they will erect an 8 feet, chain linked, enclosed
fence around everything.

4.  I will continue to watch their progress, also ensuring they correct
any damages that might occur by their parking on the grassy areas.