Instead of a crew of four, we had six Morton guys on the job today. Turned out 
another Morton job was cancelled for rest of the week so we got two of their 
crew. Framing of three walls is up, including first truss (south side). Plan is 
to have at least one or two more trusses up tomorrow before they leave for the 
Holiday. 
Foreman Ralph knows all about our Snowbird ( he could barely see the runway and 
laughed ‘really!!’) and before they leave tomorrow they will clear building 
materials from the taxiway so we can get gliders out of the hanger.  

Karin