What's the length requirement for the run? The max cable length for cat5e is 
100m, or about 328ft. If it's longer than that you'll need to put a switch in 
the middle to act as a repeater.
Tony

> Date: Fri, 22 Jul 2011 10:04:59 -0400
> From: tbrown@xxxxxxxxxxxx
> To: frgeek-michiana@xxxxxxxxxxxxx
> Subject: [frgeek-michiana] Projects moving forward
> 
> INTERNET --
> The warehouse manager unlocked the second floor for Mike and I last 
> night. Mike, Dan, Dan's son Dale and myself studied the requirements for 
> installing the wireless access point.
> 
> I will order 500 ft of cable; what we have is probably not enough. The 
> WAP will be mounted outside the building on a metal panel in a window so 
> we need materials for that. The CAT5e cable will anchor above the window 
> then thread through hooks used to hang light fixtures, then down a large 
> pipe and through the floor. I'll ask the warehouse manager if we can use 
> a scissor lift. If he doesn't have a scissor lift, I'll see if I can 
> borrow a scissor lift from my employer. If that is not possible, Mike 
> says we can do the job with a tall ladder, a piece of conduit and vise 
> grips. Mike and I visited Lowe's last night. Mike thinks he has most of 
> the materials needed and will buy the rest at Lowes after he takes 
> measurements.
> 
> RACK SHELVING --
> I bought rack shelving per Mike's estimate two weeks ago. The vendor's 
> crews delivered the parts this morning, and I helped them unload. The 
> parts are on the floor in front of our overhead door. There wasn't room 
> inside the workshop so the parts are exposed. We'll want to either 
> assemble the shelves next Thursday or make room for the parts inside the 
> workshop.
> 
> We'll need to measure the shelves for lumber: cross pieces and plywood 
> and buy the lumber cut to order. If we had a lift truck, we wouldn't 
> need the plywood.
> 
> THE PLAN --
> Mike, Dan, Dan's son and I will be at the workshop next week. We'll move 
> as many pallets as needed out of the way, assemble the shelving then 
> move the pallets back. If there is time, we'll begin the Internet 
> install. There won't be time to finish both projects unless we can 
> effectively divide into two crews working independently on both projects.
> 
> Tom --
> ** This list is PUBLICLY archived. **
> PLEASE don't post personal or sensitive information unless you wish for it to 
> be in the public domain. Email addresses are removed from the archive but 
> other items included in the body of the email will be shown.
> 
> To visit the main website for Free Geek Michiana go to 
> http://www.freegeekmichiana.org
> 
> To post to the list send email to frgeek-michiana@xxxxxxxxxxxxxx
> The archive is available at //www.freelists.org/archives/frgeek-michiana/
> 
> You may unsubscribe or change your list settings by going to the list website 
> at //www.freelists.org/webpage/frgeek-michiana
> 
                                          

Other related posts: