To all,
A closure of Runway 4/22 has been planned for 3 days beginning July 24 to
complete the approach end of Runway 4 to its finished length. This date could
change due to weather or contractors scheduling. If wind direction allows,
departures should be able to take place on Runway 4 at A2 on the 24th up to the
time work begins around 7AM, and possibly at times while work is being done if
construction equipment is far enough back from A2. No departures will be
allowed from Runway 22 toward the construction equipment, and no landings will
be allowed until the runway is reopened due to the possibility of landing short
or overrunning long into the construction equipment.
If dates or times change, I will send out a notification when I confirm the new
information.
Thank you,
John Thompson
Public Works Department
Airport Division
575-758-4995