Just a real brief update email, more to come soon. I've been doing a lot of scheduling :-) *Mk V: *Design has been frozen (nothing more added) and is reaching maturity. Tank is in production at the SIF, soon to be followed by several other components. Badass level: 10.5. Also, it's huge. We need to seriously start working on the logistics of moving it around. Targeting hydrotest Sept 27 cold flow Nov 11 *Mk IIb:* Design looks great, Material on hand. Have you guys started machining stuff? Targeting hydrotest by Sept 6, hot fire by Sept 27 (goal is to both hydrotest Mk V tank and hot fire mk IIb on the same day in Sudbury). *Electronics:* Kronos and Hyperion out for fabrication, Kronos Lite will follow soon. Dean and company are kicking ass. *Software: *GSE software is really awesome and is reaching basic functionality level. Drew's got some insane plans for this thing. *Astro: *Pete, where are we at? Targeting flight by Oct 30.