Following up on what Joe said, I'd recommend coming to the meeting Monday if
you're interested in getting some hands on building done that week. We're going
to put out a schedule of what we need done by each day. There's going to be a
lot to do so the more help the merrier.
Jeremy Pedro
On Apr 7, 2016, at 1:38 PM, Joseph Beaupre <joebeau@xxxxxx> wrote:
Hey Everyone,
We have come to the decision that it is best to hold off testing this
weekend. The GOD Box wont be done in time to allow full testing of the
totally-rewritten ground software, with both the rewritten software and fully
upgraded GOD Box a necessity for continued testing. Holding off on the test
also opens up a significant amount of time for upgrading feed lines to 1",
assembling the quad ox tank, and building the new valve panel that is going
on the test stand. These upgrades should be able to happen in under a week,
and will mean the GSE system is fully optimized and complete; we will be able
to complete the test campaign (hopefully) without any changes or upgrades.
With that in mind, be on the lookout for updates on work that needs to be
completed for the GSE system.
--
Joseph M. Beaupre
Boston University
Director, Rocket Propulsion Group
Electrical Engineering 2017