Thank you for the replies, its appreciated.

There are currently 2.4 of us, and we also look after middleware for a
couple of applications.  Its mostly vendor supplied, but we have a couple
of in-house developed systems too.  We provide some day to day support for
developers too, and are struggling to keep everything patched up to date.


On Mon, Jan 22, 2018 at 7:15 AM, Hemant K Chitale <hemantkchitale@xxxxxxxxx>
wrote:

Within the same organisation you may have some databases (yes Production
databases) that need no attention for months and years while other
databases may be raising alerts / requests more than once a day.

Some test databases may be critical and undergo selective-data  or full
data refreshes once or more a week, others may not require refreshes for
months.  Some Test and Development databases need daily backups and ability
do PITR, others can do with weekly backups.


I dislike a "N databases per DBA" rule.  Managers one level above,
unfortunately, in many cases look at "$ spend" as the immediate DBA manager
doesn't provide them enough metrics to justify the DBA headcount.  Number
of service tickets may be a proxy (but some service tickets are serviced in
a minute, others take days to execute).


Hemant K Chitale


Hemant K Chitale



On Wed, Jan 17, 2018 at 7:29 PM, Steve Bradshaw <sjb1970@xxxxxxxxx> wrote:

Hi,

I hope nobody minds me asking a non-technical question.

If you had approximately 50 databases, mix of live, test, development, no
dataguard or RAC, what sort of staffing level would you expect to have in
order to keep them patched to the latest PSU?