To all,
Drillers have completed collecting core samples on Taxiway A. I was informed 
this morning that surveyors now need to collect data on both Taxiway A and 
Runway 4/22 beginning next week. At this time, I don't have an accurate 
schedule, but at times, Taxiway A will need to be closed to traffic in stages. 
Runway 4/22 will also need to be closed to traffic for one day, but Runway 
13/31 will be available via Taxiway A and B. We will try to minimize the 
inconvenience and I will send out more information as the scheduling is set.

Thank you,
John Thompson
Public Works Department
Airport Division
575-758-4995
_____
@_I_@
\_____(_o_)_____/
II     I     II

Town of Taos

Under the New Mexico Inspection of Public Records Act (IPRA), all messages sent 
by or to me on this Town-owned email account may be subject to public 
disclosure.

taosgov.com <http://www.taosgov.com>

Other related posts:

  • » [flytaos] Surveying on Taxiway A - John Thompson