We need to Clarify that Phrase and its correct Definition.

Dennis

On Thu, Jan 6, 2022, 7:50 AM Clarrage, Katherine C. <
Katherine.C.Clarrage@xxxxxxxxx> wrote:

I believe the term “shortening pedestrian time” means less time
pedestrians are in the road…which can be a good thing. Kathy



Kathy Clarrage, COMS

State of Maine, Division for the Blind & Visually Impaired

151 Jetport Blvd

Portland, ME 04102

207-423-5448

Katherine.c.clarrage@xxxxxxxxx

Facebook page: https://www.facebook.com/MEDBVI
<https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fwww.facebook.com%2FMEDBVI&data=04%7C01%7CKatherine.C.Clarrage%40maine.gov%7Cbe848c8aa2c4455e8b9a08d8e595d144%7C413fa8ab207d4b629bcdea1a8f2f864e%7C0%7C0%7C637511778914485573%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C1000&sdata=JIVmipGTEi9U%2BmwN446knoFzgLalypibGdvTUREpx0M%3D&reserved=0>



“The day you plant the seed Is Not the day you eat the fruit”







*From:* wsmac-bounce@xxxxxxxxxxxxx <wsmac-bounce@xxxxxxxxxxxxx> *On
Behalf Of *Carson Wood
*Sent:* Thursday, January 06, 2022 6:54 AM
*To:* wsmac@xxxxxxxxxxxxx
*Subject:* [wsmac] Re: Westbrook Intersection Improvement



*EXTERNAL: This email originated from outside of the State of Maine Mail
System. Do not click links or open attachments unless you recognize the
sender and know the content is safe.*

The crossing times at other intersections are so quick that an elderly
person would not be able to cross in the time given.

   If this is what is meant by shortened times it is an issue



*From:* wsmac-bounce@xxxxxxxxxxxxx <wsmac-bounce@xxxxxxxxxxxxx> *On
Behalf Of *John Brooking
*Sent:* Wednesday, January 05, 2022 8:00 PM
*To:* wsmac@xxxxxxxxxxxxx
*Subject:* [wsmac] Re: Westbrook Intersection Improvement



We have not discussed the project formally from a WSMAC perspective. The
history is that this was originally part of the 2010 William Clarke
redesign, but they ran out money.



My personal feeling is that if this project will create “a tighter
intersection, shortening pedestrian crossing times”, per the DOT project
engineer, that should be an improvement for non-motorized users as well as
motorists. But I’m not speaking for the committee.



On Wed, Jan 5, 2022 at 6:24 PM Dennis Marrotte <
dennis.marrotte1111@xxxxxxxxx> wrote:

Hi Angela,



Are you referring to the $ 3.2 M Multi Intersection Project at the Western
side of Westbrook  ?



I will have to check with Kim, Lee, John and a couple others.



I am a bit concerned with the comments of the new WPD Chief.  The Traffic
Back-up goes back to The Spring Street - WCD - Main Street Intersection -
not just to Mechanic Street.  I would like to see the Proposed New Multi
Story- Multi Use Building on the Municipal Parking Lot off Mechanic Street
delayed until the Western Intersection Project is completed.  But I'm just
1 Voice squeeking !



Do You have any Thoughts or Suggestions on the Multi - Intersection
Construction Project for the Western side of the City ?



Thanks Angela



Dennis Marrotte



On Wed, Jan 5, 2022, 5:39 PM Angela King <angela@xxxxxxxxxxxxx> wrote:

Was this group involved with or did you give any input on this
intersection project?




https://www.pressherald.com/2021/12/28/3-2-million-in-improvements-slated-for-major-westbrook-intersection/
<https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fwww.pressherald.com%2F2021%2F12%2F28%2F3-2-million-in-improvements-slated-for-major-westbrook-intersection%2F&data=04%7C01%7Ckatherine.c.clarrage%40maine.gov%7C639d36b78f2548f442bd08d9d10b2a3a%7C413fa8ab207d4b629bcdea1a8f2f864e%7C0%7C0%7C637770668164190635%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000&sdata=UGmzB37nLZZrs0Pgivf37uVru7o78xnGrTf%2BeQqDgbc%3D&reserved=0>

















--

John Brooking

Cyclist, Cycling Educator, Technologist

http://cyclingsavvy.org
<https://gcc02.safelinks.protection.outlook.com/?url=http%3A%2F%2Fcyclingsavvy.org%2F&data=04%7C01%7Ckatherine.c.clarrage%40maine.gov%7C639d36b78f2548f442bd08d9d10b2a3a%7C413fa8ab207d4b629bcdea1a8f2f864e%7C0%7C0%7C637770668164190635%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000&sdata=f9RmpJR1kwSTjGcQodSdr9wNycQ0MiKzZCsPEMQvH7k%3D&reserved=0>

Other related posts: