Feel free to step in and provide ignitors with 100% fail proof reliability
and electrical engineering to prevent future failures.

This is a International VOLUNTEER team effort, if you're not part of the
solution, you're part of the problem.

It's REAL easy to throw stones, it's a whole lot harder to step up instead
of making derogatory comments that help no one.

Jeff Moore
SS2S
Bend, Oregon

On Tue, Dec 24, 2013 at 6:02 PM, Eric Christy <sliderulelover@xxxxxxxxxxx>wrote:

> You guys are EMBARASSING! Either you're lousy chemists, not able to get
> your mixture correct, or you're lousy electronics engineers, not able to
> make decent continuity between control board and igniter, or you're both.
> Which is it??? Suffice it to say, you bozos are very UNimpressive! When you
> grow some decent science, then get back to me. I bet you can't even balance
> the chemical reaction between Potassium Nitrate and Sorbital (sugar). You
> need to get that part right first before you try connecting to the igniter.
>
> Eric
>
>
>
> > Date: Mon, 23 Dec 2013 22:25:28 -0600
>
> > Subject: [SS2S-Main] Sugar Shot Weekly Activity Report - Dec.16-20, 2013
> > From: richard.rocketry@xxxxxxxxx
> > To: sugarshot@xxxxxxxxxxxxx
>
> >
> > Highlights of recent developments on the DoubleSShot project
> >
> ---------------------------------------------------------------------------------------
> > -As planned, Rick Maschek test fired the 89mm (3.5”) 2-grain rocket
> > motor with DD-slot grains on Saturday Dec.21st. The test firing was
> > conducted at the FAR site, with the motor mounted nozzle down on one
> > of the vertical test stands. The base of the stand was fitted with a
> > blast deflector to help prevent smoke from obscuring the pressure
> > gauge used to record chamber pressure. This worked well, and good
> > pressure readings were recorded over the full duration of the burn,
> > which was nominal. Maximum chamber pressure was about 260 psi
> > (1.9Mpa), which compares well with the predicted pressure of 248 psi.
> > Due to problems with the igniter, the planned firings of the 4-grain
> > and 6-grain motor had to be postponed. Rick will be modifying the
> > forward bulkhead with an igniter fitting to prevent a similar igniter
> > issue from re-occurring.
> > Rick and Richard Dierking setting up the motor:
> > http://sugarshot.org/downloads/setup.jpg
> > Richard Dierking connecting the pressure gauge:
> > http://sugarshot.org/downloads/setup1.jpg
> > Motor at full thrust:
> > http://sugarshot.org/downloads/thrusting.jpg
> > Gauge reading at full thrust:
> > http://sugarshot.org/downloads/gaugereading.jpg
> > DD-slot grain details:
> > http://sugarshot.org/downloads/dd_grain.pdf
> > Video:
> > http://www.youtube.com/watch?v=h1mYHtsD7a8&feature=youtu.be
> > (video courtesy Rick Maschek)
> >
> > -Richard has made further progress on fabricating the carbon composite
> > nozzle exhaust cone for the VIC-2 motor. All 10 plies of carbon
> > prepreg were wrapped around the mandrel. After each ply was laid,
> > heat-shrink tape was wrapped around the prepreg, then shrunk using a
> > heat gun to consolidate the layers. The product was then vacuum bagged
> > in preparation for curing. Curing will be done in an autoclave at
> > elevated temperature (300F/150C) and pressure (4 bar).
> > --------------------------
> > -Sugar Shot to Space is on facebook. Check us out.
> > http://tinyurl.com/2exr92k
> >
>