[SI-LIST] Re: IBIS for PDN

  • From: "Han, Guobing" <han.guobing@xxxxxxxxx>
  • To: "Lynne D. Green" <lgreen22@xxxxxxxxxxxxxx>
  • Date: Wed, 4 Nov 2009 10:13:32 +0800

Hi Lynne,

    Thanks a lot for your reply.
    As we know, SPICE model for PDN analysis is very time-consuming
and so-called methodology of Icct is not accurate enough. So I want to
imrpove it by generating IBIS for PDN or by other ways.
   Any suggestions?

Thanks,
Guobing



2009/11/4, Lynne D. Green <lgreen22@xxxxxxxxxxxxxx>:
> Hello, Guobing,
>
> The major vendors have PDN analysis software.  Each has different
> algorithms and user interfaces.  Of the common issues below, the first
> two are probably most important.
>
> Common issues:
> * What functionality do you need?  This could include analyzing Z(PDN),
> simulating for current and voltage at each Vcc and GND pin on every IC,
> showing constraint violations for delta_Vcc, running signal integrity
> simulations with PDN effects included, and so forth.
> * Geometric resolution should be small enough to capture such things as
> via fields and microvias.
> * IBIS models should associate I(driver) with a specific POWER and GND
> pin pair, to improve PDN model accuracy in near the IC.  This data is
> usually available from the IBIS model maker; unfortunately this data is
> not included in many IBIS models.
> * For modeling of curved areas on the plane, flexible gridding is
> preferred for speed/accuracy tradeoff compared to a fixed grid size.
> With flexible gridding, a coarser grid is used in large plane areas,
> while a finer grid is used near vias and curved edges.
> * PDN analysis should include traces to capacitors and Vcc/GND pins.
> * First order IBIS models that do not describe delta_/delta_Vcc) limit
> accuracy of I(t).
> * Run time tradeoff (fine grids give more accuracy, but take longer).
> One can run a coarse grid for early analysis, and a finer grid for final
> layout.  Of course, actual run time also depends on the algorithm and
> implementation.
>
> Regards.
> Lynne Green
>
> "IBIS training when you need it, where you need it."
>
> Dr. Lynne Green
> Green Streak Programs
> http://www.greenstreakprograms.com
> 425-788-0412
> lgreen22@xxxxxxxxxxxxxx
>
>
>
>
> Han, Guobing wrote:
>> Hi all,
>>
>>     Have someone tried to study the IBIS for PDN?
>>     What's biggest problem and challenge?
>>
>> Thanks,
>> Guobing
>>
>>
>
>


-- 
Guobing HAN,
Senior Signal Integrity Engineer,
Marvell Shanghai Ltd.
4F,Building4,399 Keyuan RD,Shanghai 201203, China
Email: gbhan@xxxxxxxxxxx
Office:   86-21-61094805
Mobile:  86-13818903075
MSN:    han_guobing@xxxxxxxxxxx
Web site:  http://www.marvell.com
------------------------------------------------------------------
To unsubscribe from si-list:
si-list-request@xxxxxxxxxxxxx with 'unsubscribe' in the Subject field

or to administer your membership from a web page, go to:
//www.freelists.org/webpage/si-list

For help:
si-list-request@xxxxxxxxxxxxx with 'help' in the Subject field


List technical documents are available at:
                http://www.si-list.net

List archives are viewable at:     
                //www.freelists.org/archives/si-list
or at our remote archives:
                http://groups.yahoo.com/group/si-list/messages
Old (prior to June 6, 2001) list archives are viewable at:
                http://www.qsl.net/wb6tpu
  

Other related posts: