Re: Upgrade and Execution Plans

  • From: Steve Harville <steve.harville@xxxxxxxxx>
  • To: dba.tyagisumit@xxxxxxxxx, Oracle L <oracle-l@xxxxxxxxxxxxx>
  • Date: Thu, 07 Apr 2016 15:57:37 +0000

Correction - that was for 11.1 to 11.2 upgrades.

On Thu, Apr 7, 2016 at 11:55 AM Steve Harville <steve.harville@xxxxxxxxx>
wrote:

I have used export/import in the past to maintain the version 10 plans -
see:
https://docs.oracle.com/cd/B28359_01/server.111/b28274/optplanmgmt.htm#CHDGDICI


On Thu, Apr 7, 2016 at 11:46 AM sumit Tyagi <dba.tyagisumit@xxxxxxxxx>
wrote:

Hi Guys ,

One of our client want to upgrade it's legacy 10g database to 11.2.0.4 .
But one concern is how it will impact the
query execution plans ?

How can we make sure the execution plans remain same . What are the
different options we have here


--

*--*
*BR*
*Sumit Tyagi*
*+91-7829543355*


Other related posts: