[makion] Fw: 液体窒素タンクの更新について

  • From: "Makio Takeda" <mtakeda@xxxxxxxxxxxx>
  • To: <makion@xxxxxxxxxxxxx>
  • Date: Thu, 8 Feb 2001 10:52:50 +0900


----- Original Message -----
From: 鵜川 和子 <ukawa@xxxxxxxxxxxx>
To: <ebisu@xxxxxxxxxxxxxxxxxxxxx>; <ukawa@xxxxxxxxxxxxxxxxxxxxx>;
<himaish@xxxxxxxxxxxx>; <kksato@xxxxxxxxxxxx>; <ukikkawa@xxxxxxxxxxxx>;
<naosaito@xxxxxxxxxxxx>; <yonodayo@xxxxxxxxxxxx>; <kawai@xxxxxxxxxxxx>;
<tsurumis@xxxxxxxxxxxxxxxxxxx>; <tainosho@xxxxxxxxxxxx>;
<enomotr@xxxxxxxxxxxxxxxxxxxx>; <sanukida@xxxxxxxxxxxx>;
<terakado@xxxxxxxxxxxx>; <naoshika@xxxxxxxxxxxxxxxxxxx>;
<kunitomo@xxxxxxxxxxxx>; <wada@xxxxxxxxxxxxxxxxxxxxx>;
<ohta@xxxxxxxxxxxxxxxxxxxxx>; <okubo@xxxxxxxxxxxxxxxxxxxxx>;
<sakurai@xxxxxxxxxxxxxxxxxxxxx>; <h-kato@xxxxxxxxxxxx>;
<sotani@xxxxxxxxxxxx>; <fuke@xxxxxxxxxxxx>; <mhashi@xxxxxxxxxxxx>;
<nyosida@xxxxxxxxxxxx>; <kawamoto@xxxxxxxxxxxx>; <kanno@xxxxxxxxxxxx>;
<setsunej@xxxxxxxxxxxx>; <tominaga@xxxxxxxxxxxx>; <kuitoh@xxxxxxxxxxxx>;
<oishi@xxxxxxxxxxxxxxxxx>; <matsuday@xxxxxxxxxxxx>; <shichijo@b
Sent: Thursday, February 08, 2001 9:37 AM
Subject: 液体窒素タンクの更新について


> >
> > 液体窒素利用者 各位
> >
> > 現在設置している3トンのタンクを10トンに更新します。
> > 本日工程表がメーカーから示されました。
> > 高圧ガス保安法によって規制されていることも有り、
> > 更新手続き(変更願い、完成検査)、工事(撤去、基礎、養生、据え付け)に約
1ケ
> > 月を要します。
> >
> > 2月28日(水)に旧の3トンのタンクを撤去します。
> > 新の10トンのタンクの共用は3月30日(金)を予定しております。
> >
> > この間の液体窒素の供給は低温センター前の駐車場に
> > 置く予定の1トンのタンクで行います。
> > 実際にどのように操作して使用するかにつきましては、
> > 当日までに掲示を出しますので、それに従って液体窒素の
> > 汲み出しを行って下さい。
> >
> > タンクが空になれば、充填されたタンクと入れ替える
> > やり方になりますが、注文してから充填されたタンクが
> > 運搬されてくるまでに最低1日は必要で、何かと不都合が生じると
> > 予想されますが御協力をお願いします。
> >
> > 平成13年2月8日
> > 低温センター
> >
>
>
>
>