Good morning Taos pilots,
   Here is your periodic construction update:
- The PAPIs on rwy 22 and Rwy 04 are fixed. It helps us if you let us know of 
any problems on the airfield.
- Taxiway A construction is progressing but unfortunately the northeast 
hangars are still blocked. As soon as I see an opportunity to get access to 
the runway for the northeast hangar pilots I will. The contractor and I talk 
regularly and he is going to improve the access as soon as he is able.
- All of the paint has been removed from runway 13/31. They have begun to lay 
down the sealcoat. 
- Taxiway B is just beginning to have the paint removed.
- After the sealcoat is down on taxiway A and runway 13/31 there is a cure 
period and then the base coat of paint goes on. After a short cure period the 
reflective glass beads go down and the project is finished. 

Thanks


Kino Chavez
TAOSAviation