[deanwoodcitizens] Re: Project Update For Your Area-Small Diameter Water Main Replacement Project in the Deanwood Neighborhood

  • From: "Emanuel D. Briggs" <Emanuel.Briggs@xxxxxxxxxxx>
  • To: "Emanuel D. Briggs" <Emanuel.Briggs@xxxxxxxxxxx>
  • Date: Wed, 24 Nov 2021 08:45:53 +0000

[cid:image001.jpg@01D7E0D6.8E215010]

PROJECT UPDATE
Wednesday, November 24, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>
Greetings DC Water Community Stakeholders:
Please see our revised list of ongoing and upcoming construction activities-
Active Work Location: Sheriff Road NE

Weeks of November 22 – December 13


  *   We have successfully completed installation of 450 linear feet of new 
8-inch water mains between 45th Street NE and Sheriff Road NE.

  *   We have begun installation of new water services at this location, but 
these activities have been delayed, and are now scheduled for completion by 
Monday, December 6.
  *   Between Tuesday, December 7 and Thursday, December 9, we will be 
performing some restoration activities to portions of the roadway where we have 
successfully completed water main installation, disinfection, tie-in and new 
water service installations.
  *   We are scheduled to perform some final restoration activities at this 
location from Monday, December 13 – Friday, December 17.


  *   Following successful installation of new 8-inch water mains along Sheriff 
Road, we are now scheduled to abandon (take out of service) an existing 12-inch 
water main on Sheriff Road this week.

  *   We have nearly completed final restoration activities at this location, 
and this final portion of work should be completed very soon.


Active Work Location: Hayes Street NE

Weeks of November 22- December 13


  *   We have just begun installation of new 8-inch water mains beginning on 
46th Street NE, running down to Hayes Street NE, then moving along Hayes Street 
over to 48th Street NE. We anticipate this portion of work will be completed by 
Tuesday, December 14.

  *   Concurrent with this portion of work, we will begin testing and 
disinfection of these newly installed water mains on Tuesday, November 30, and 
these activities are now scheduled to continue through Thursday, December 2.
  *   We are scheduled to begin installation of new water services at this 
location on Friday, December 3, and these activities should be completed by 
Monday, December 6.
  *   Between Tuesday, December 7 and Thursday, December 9, we will be 
performing some restoration activities to portions of the roadway where we have 
successfully completed water main installation, disinfection, tie-in and new 
water service installations.
  *   We are scheduled to perform some final restoration activities at this 
location from Monday, December 13 – Friday, December 17.


In observation of the Thanksgiving Day Holiday, there will be no construction 
activities scheduled for Thursday, November 25.

Please keep in mind that these construction activities are highly dependent 
upon favorable weather conditions.


Thanks much, and make it a wonderful week…..ON PURPOSE!!

From: Emanuel D. Briggs
Sent: Monday, November 8, 2021 6:33 AM
To: Emanuel D. Briggs <Emanuel.Briggs@xxxxxxxxxxx>
Cc: Emanuel D. Briggs <Emanuel.Briggs@xxxxxxxxxxx>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image001.jpg@01D7E0D6.8E215010]

PROJECT UPDATE
Monday, November 8, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>
Greetings DC Water Community Stakeholders:
Please see our revised list of ongoing and upcoming construction activities-
Active Work Location: Sheriff Road NE

Weeks of November 8 – December 6


  *   We have successfully completed installation of 450 linear feet of new 
8-inch water mains between 45th Street NE and Sheriff Road NE.

  *   We have begun installation of new water services at this location, but 
these activities have been delayed, and are now scheduled for completion by 
Friday, December 10.


  *   We have successfully completed installation of 450 linear feet of new 
8-inch water mains between 46th Street NE and Sheriff Road

  *   Between Tuesday, November 9 and Friday, November 12, we will be 
performing some restoration activities to portions of the roadway where we have 
successfully completed water main installation, disinfection, tie-in and new 
water service installations.

  *   We will be performing some final restoration activities at this location 
between Monday, November 15 – Friday, November 19.



Active Work Location: Hayes Street NE

Weeks of November 15- December 6


  *   On  Monday, November 15, we will begin installation of new 8-inch water 
mains beginning on 46th Street NE, running down to Hayes Street NE, then moving 
along Hayes Street over to 48th Street NE. We anticipate this portion of work 
will be completed by Monday, December 6.
  *   Concurrent with this portion of work, we will begin testing and 
disinfection of these newly installed water mains on Thursday, November 18, and 
these activities are now scheduled to continue through Monday, November 22.
  *   We are scheduled to begin installation of new water services at this 
location on Tuesday, November 23, and these activities should be completed by 
Wednesday, November 24.
  *   Between Monday, November 29 and Wednesday, December 1, we will be 
performing some restoration activities to portions of the roadway where we have 
successfully completed water main installation, disinfection, tie-in and new 
water service installations.



Active Work Location: 46th Street NE

Weeks of November 8 – November 15


  *   This week, we are finalizing construction activities related to the 
installation of 350 linear feet of new 8-inch water mains on 46th Street NE 
between Jay Street NE and Hunt Place NE.
  *   We will be performing some final restoration activities at this location 
between Monday, November 15 – Friday, November 19.


In observation of the Veterans’ Day Holiday, there will be no construction 
activities scheduled for Thursday, November 11.

Please keep in mind that these construction activities are highly dependent 
upon favorable weather conditions.


Thanks much, and make it a wonderful week…..ON PURPOSE!!

From: Emanuel D. Briggs
Sent: Monday, November 1, 2021 1:48 PM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image001.jpg@01D7E0D6.8E215010]

PROJECT UPDATE
Monday, November 1, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>
Greetings DC Water Community Stakeholders:
Please see our revised list of ongoing and upcoming construction activities-
Active Work Location: Sheriff Road NE

Weeks of November 1 – December 6


  *   We have successfully completed installation of 450 linear feet of new 
8-inch water mains between 45th Street NE and Sheriff Road NE.

  *   We have completed testing and disinfection of these newly installed water 
mains.
  *   We have begun installation of new water services at this location, but 
these activities have been delayed, and are now scheduled for completion by 
Friday, December 10.


  *   Following successful installation of new 8-inch water mains along Sheriff 
Road, we are now scheduled to abandon (take out of service) an existing 12-inch 
water main on Sheriff Road between Friday, November 5 – Monday, November 8.

  *   On Monday, November 8, we are tentatively scheduled to perform a tie-in 
of a newly installed 12-inch water main at Sheriff Road.


  *   We have successfully completed installation of 450 linear feet of new 
8-inch water mains between 46th Street NE and Sheriff Road

  *   Between Tuesday, November 9 and Friday, November 12, we will be 
performing some restoration activities to portions of the roadway where we have 
successfully completed water main installation, disinfection, tie-in and new 
water service installations.


  *   We will be performing some final restoration activities at this location 
between Monday, November 15 – Friday, November 19.



Active Work Location: Hayes Street NE

Weeks of November 15- December 6


  *   On  Monday, November 15, we will begin installation of new 8-inch water 
mains beginning on 46th Street NE, running down to Hayes Street NE, then moving 
along Hayes Street over to 48th Street NE. We anticipate this portion of work 
will be completed by Monday, December 6.
  *   Concurrent with this portion of work, we will begin testing and 
disinfection of these newly installed water mains on Thursday, November 18, and 
these activities will be ongoing.


Active Work Location: 46th Street NE

Weeks of November 1 – November 15


  *   This week, we are finalizing construction activities related to the 
installation of 350 linear feet of new 8-inch water mains on 46th Street NE 
between Jay Street NE and Hunt Place NE.

  *   Between Wednesday, November 3 and Friday, November 5, we will be 
performing some restoration activities to portions of the roadway where we have 
successfully completed water main installation, disinfection, tie-in and new 
water service installations.


  *   We will be performing some final restoration activities at this location 
between Monday, November 15 – Friday, November 19.


Please keep in mind that these construction activities are highly dependent 
upon favorable weather conditions.


Thanks much, and make it a wonderful week…..ON PURPOSE!!

From: Emanuel D. Briggs
Sent: Wednesday, October 27, 2021 2:42 PM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image001.jpg@01D7E0D6.8E215010]


PROJECT UPDATE
Wednesday, October 27, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>

Greetings DC Water Community Stakeholders:
By way of this update, we want to inform you that our Contractor will be 
working in your area this coming Saturday, October 30. Specifically, we will be 
performing the following activities:

  *   Installation of new water services in the 800 block of 46th Street NE.


We just wanted to ensure you had this information, in case there is any 
confusion as to why our Contractor is working on a Saturday😊

Thanks much, and please enjoy the remainder of your day!

From: Emanuel D. Briggs
Sent: Monday, October 25, 2021 9:05 PM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image001.jpg@01D7E0D6.8E215010]


PROJECT UPDATE
Monday, October 25, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>
Greetings DC Water Community Stakeholders:
Please see our revised list of ongoing and upcoming construction activities-
Active Work Location: Sheriff Road NE

Weeks of October 25 – December 6


  *   We have successfully completed installation of 450 linear feet of new 
8-inch water mains between 45th Street NE and Sheriff Road NE.

  *   We have completed testing and disinfection of these newly installed water 
mains.
  *   We have begun installation of new water services at this location, but 
these activities have been delayed, and are now scheduled for completion by 
Friday, December 10.


  *   Following successful installation of new 8-inch water mains along Sheriff 
Road, we are now scheduled to abandon (take out of service) an existing 12-inch 
water main on Sheriff Road between Thursday, November 4 – Friday, November 5.

  *   We have begun testing and disinfection of these newly installed water 
mains, and anticipate completion of these activities by Friday, October 29.
  *   On Friday, November 5, we are tentatively scheduled to perform a tie-in 
of a newly installed 12-inch water main at Sheriff Road.


  *   We have successfully completed installation of 450 linear feet of new 
8-inch water mains between 46th Street NE and Sheriff Road

  *   Following installation of these new mains, we have begun testing and 
disinfection of the new mains, and are scheduled to complete these activities 
by Friday, October 29.
  *   We will begin installation of new water services at this location on 
Monday, November 1, and these activities will continue through the following 
Monday, November 8.
  *   Between Tuesday, November 9 and Friday, November 12, we will be 
performing some restoration activities to portions of the roadway where we have 
successfully completed water main installation, disinfection, tie-in and new 
water service installations.



Active Work Location: Hayes Street NE

Week of November 15


  *   On  Monday, November 15, we will begin installation of new 8-inch water 
mains beginning on 46th Street NE, running down to Hayes Street NE, then moving 
along Hayes Street over to 48th Street NE. We anticipate this portion of work 
will be completed by Wednesday, November 17.


Active Work Location: 46th Street NE

Weeks of October 25 – November 8


  *   We have successfully completed installation of 350 linear feet of new 
8-inch water mains on 46th Street NE between Jay Street NE and Hunt Place NE.

  *   Testing and disinfection of the new mains is currently underway.
  *   We will begin installation of new water services at this location on 
Monday, November 1, and these activities will continue through Thursday, 
November 4.
  *   Between Friday, November 5 and Tuesday, November 9, we will be performing 
some restoration activities to portions of the roadway where we have 
successfully completed water main installation, disinfection, tie-in and new 
water service installations.


Please keep in mind that these construction activities are highly dependent 
upon favorable weather conditions.


Thanks much, and make it a wonderful week…..ON PURPOSE!!

From: Emanuel D. Briggs
Sent: Monday, October 18, 2021 8:30 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image001.jpg@01D7E0D6.8E215010]


PROJECT UPDATE
Monday, October 18, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>
Greetings DC Water Community Stakeholders:
Please see our revised list of ongoing and upcoming construction activities-
Active Work Location: Sheriff Road NE

Weeks of October 18 – November 8


  *   We have successfully completed installation of 450 linear feet of new 
8-inch water mains between 45th Street NE and Sheriff Road NE.

  *   We have completed testing and disinfection of these newly installed water 
mains.
  *   We have begun installation of new water services at this location, but 
these activities have been delayed, and are now scheduled for completion by 
Tuesday, November 9.


  *   Following successful installation of new 8-inch water mains along Sheriff 
Road, we are now scheduled to abandon (take out of service) an existing 12-inch 
water main on Sheriff Road between Tuesday, October 26-Wednesday, October 27.

  *   We have completed testing and disinfection of these newly installed water 
mains.
  *   We have completed installation of new water services at this location.
  *   Between Monday, October 18 and Friday, October 22, we will be performing 
some concrete base restoration to portions of the roadway where we have 
successfully completed water main installation, disinfection, tie-in and new 
water service installations.
  *   On Wednesday, October 27, we are tentatively scheduled to perform a 
tie-in of a newly installed 12-inch water main at Sheriff Road.


  *   We have successfully completed installation of 450 linear feet of new 
8-inch water mains between 46th Street NE and Sheriff Road

  *   Following installation of these new mains, we have begun testing and 
disinfection of the new mains, and are scheduled to complete these activities 
early this week.
  *   We will begin installation of new water services at this location on 
Wednesday, October 20, and these activities will continue through Tuesday, 
October 26.
  *   Between Wednesday, October 27 and Friday, October 29, we will be 
performing some restoration activities to portions of the roadway where we have 
successfully completed water main installation, disinfection, tie-in and new 
water service installations.



Active Work Location: Hayes Street NE

Weeks of November 1 – November 15


  *   On  Monday, November 1, we will begin installation of new 8-inch water 
mains beginning on 46th Street NE, running down to Hayes Street NE, then moving 
along Hayes Street over to 48th Street NE. We anticipate this portion of work 
will be completed by Thursday, November 18.

  *   Concurrent with the installation of new mains, we will be performing 
testing and disinfection of the new mains from Thursday, November 4 – Monday, 
November 8.



Active Work Location: 46th Street NE

Weeks of October 18 – October 25


  *   We have successfully completed installation of 350 linear feet of new 
8-inch water mains on 46th Street NE between Jay Street NE and Hunt Place NE.

  *   We are now scheduled to begin testing and disinfection of the new mains 
on Monday, October 18, and these activities are scheduled for completion by 
Wednesday, October 20.
  *   We will begin installation of new water services at this location on 
Thursday, October 21, and these activities will continue through Tuesday, 
October 26.
  *   Between Wednesday, October 27 and Friday, October 29, we will be 
performing some restoration activities to portions of the roadway where we have 
successfully completed water main installation, disinfection, tie-in and new 
water service installations.


Please keep in mind that these construction activities are highly dependent 
upon favorable weather conditions.


Thanks much, and make it a wonderful week…..ON PURPOSE!!

From: Emanuel D. Briggs
Sent: Wednesday, October 13, 2021 8:08 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image001.jpg@01D7E0D6.8E215010]

PROJECT UPDATE
Wednesday, October 13, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>
Greetings DC Water Community Stakeholders:
Please see our revised list of ongoing and upcoming construction activities-
Active Work Location: Sheriff Road NE

Weeks of October 11 – October 25


  *   We have successfully completed installation of 450 linear feet of new 
8-inch water mains between 45th Street NE and Sheriff Road NE.

  *   We have completed testing and disinfection of these newly installed water 
mains.
  *   We have begun installation of new water services at this location, and 
these activities are scheduled for completion this week.
  *   This week, we are still scheduled to perform some concrete base 
restoration to portions of the roadway where we have successfully completed 
water main installation, disinfection, tie-in and new water service 
installations.


  *   Following successful installation of new 8-inch water mains along Sheriff 
Road, we are now scheduled to abandon (take out of service) an existing 12-inch 
water main on Sheriff Road between Tuesday, October 19-Wednesday, October 20.

  *   We have begun testing and disinfection of these newly installed water 
mains, and we anticipate that these activities will be completed this week.
  *   Between Monday, October 18 and Friday, October 22, we will be performing 
some concrete base restoration to portions of the roadway where we have 
successfully completed water main installation, disinfection, tie-in and new 
water service installations.


  *   We have successfully completed installation of 450 linear feet of new 
8-inch water mains between 46th Street NE and Sheriff Road

  *   Following installation of these new mains, we have begun testing and 
disinfection of the new mains, and are scheduled to complete these activities 
this week.
  *   We will begin installation of new water services at this location on 
Friday, October 15, and these activities will continue through Tuesday, October 
26.
  *   Between Wednesday, October 27 and Friday, October 29, we will be 
performing some concrete base restoration to portions of the roadway where we 
have successfully completed water main installation, disinfection, tie-in and 
new water service installations.



Active Work Location: Hayes Street NE

Weeks of October 11 – November 15


  *   This week, we will begin installation of new 8-inch water mains beginning 
on 46th Street NE, running down to Hayes Street NE, then moving along Hayes 
Street over to 48th Street NE. We anticipate this portion of work will be 
completed by Monday, November 15.

  *   Concurrent with the installation of these new mains, we will be 
performing testing and disinfection of the new mains from Friday, October 15 – 
Tuesday, October 19.
  *   Concurrent with the installation of new mains, we will begin installation 
of new water services at this location on Thursday, October 21, and these 
activities will continue through Tuesday, October 26.
  *   Between Wednesday, October 27 and Thursday, October 28, we will begin 
performing some concrete base restoration to portions of the roadway where we 
have successfully completed water main installation, disinfection, tie-in and 
new water service installations.



Active Work Location: 46th Street NE

Weeks of October 11 – October 18


  *   We have begun installation of 350 linear feet of new 8-inch water mains 
on 46th Street NE between Jay Street NE and Hunt Place NE, and we now 
anticipate completion of these activities by Friday, October 22.

  *   Concurrent with the installation of these new mains, we will be 
performing testing and disinfection of the new mains this week.
  *   We will begin installation of new water services at this location on 
Friday, October 15, and these activities will continue through Tuesday, October 
19.
  *   Between Wednesday, October 20 and Friday, October 22, we will be 
performing some concrete base restoration to portions of the roadway where we 
have successfully completed water main installation, disinfection, tie-in and 
new water service installations.


Please keep in mind that these construction activities are highly dependent 
upon favorable weather conditions.


Thanks much, and make it a wonderful week…..ON PURPOSE!!

From: Emanuel D. Briggs
Sent: Thursday, October 7, 2021 11:13 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image001.jpg@01D7E0D6.8E215010]


PROJECT UPDATE
Thursday, October 7, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>

Greetings DC Water Community Stakeholders:
By way of this update, we want to inform you that our Contractor will be 
working in your area this coming Saturday, October 9. Specifically, we will be 
performing the following activities:

  *   New pipe installation and installation of new water services in the 900 
block of 45th Street NE, and also in the 800 block of 46th Street NE.


We just wanted to ensure you had this information, in case there is any 
confusion as to why our Contractor is working on a Saturday😊

Thanks much, and please enjoy the remainder of your day!

From: Emanuel D. Briggs
Sent: Monday, October 4, 2021 6:02 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image001.jpg@01D7E0D6.8E215010]


PROJECT UPDATE
Monday, October 4, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>
Greetings DC Water Community Stakeholders:
Please see our revised list of ongoing and upcoming construction activities-
Active Work Location: Sheriff Road NE

Weeks of October 4 – October 18


  *   We have successfully completed installation of 450 linear feet of new 
8-inch water mains between 45th Street NE and Sheriff Road NE.

  *   We have completed testing and disinfection of these newly installed water 
mains.
  *   We have begun installation of new water services at this location, and 
these activities will continue through Thursday, October 7.
  *   Between Wednesday, October 13 and Friday, October 15, we will be 
performing some concrete base restoration to portions of the roadway where we 
have successfully completed water main installation, disinfection, tie-in and 
new water service installations.


  *   Following successful installation of new 8-inch water mains along Sheriff 
Road, we are now scheduled to abandon (take out of service) an existing 12-inch 
water main on Sheriff Road between Friday, October 8-Tuesday, October 12.

  *   We have begun testing and disinfection of these newly installed water 
mains, and we anticipate that these activities will be completed this week.
  *   Between Friday, October 8 and Thursday, October 14, we will be performing 
some concrete base restoration to portions of the roadway where we have 
successfully completed water main installation, disinfection, tie-in and new 
water service installations.




  *   We have begun installation of 450 linear feet of new 8-inch water mains 
between 46th Street NE and Sheriff Road, and we are still scheduled to complete 
this portion of work by Tuesday, October 5.

  *   Following installation of these new mains, we will be performing testing 
and disinfection of the new mains from Wednesday, October 6 – Friday, October 8.
  *   We will begin installation of new water services at this location on 
Monday, October 18, and these activities will continue through Thursday, 
October 21.



Active Work Location: Hayes Street NE

Weeks of October 11 – October 25


  *   From Tuesday, October 12 through Thursday, October 28, we will be 
installing new 8-inch water mains beginning on 46th Street NE, running down to 
Hayes Street NE, then moving along Hayes Street over to 48th Street NE.

  *   Concurrent with installation of these new mains, we will be performing 
testing and disinfection of the new mains, from Friday, October 15 – Tuesday, 
October 19.
  *   We will begin installation of new water services at this location on 
Wednesday, October 20, and these activities will continue through Tuesday, 
October 26.


Active Work Location: 46th Street NE

Weeks of October 4 – October 18


  *   We will be installing 350 linear feet of new 8-inch water mains on 46th 
Street NE between Jay Street NE and Hunt Place NE between Wednesday, October 6 
– Friday, October 8.

  *   Following installation of these new mains, we will be performing testing 
and disinfection of the new mains from Tuesday, October 12 – Thursday, October 
14.
  *   We will begin installation of new water services at this location on 
Friday, October 15, and these activities will continue through Tuesday, October 
19.
  *   Between Wednesday, October 20 and Friday, October 22, we will be 
performing some concrete base restoration to portions of the roadway where we 
have successfully completed water main installation, disinfection, tie-in and 
new water service installations.


In observation of the Columbus Day/Indigenous Peoples’ Day Holiday, there will 
be no construction activities scheduled on Monday, October 11.

Please keep in mind that these construction activities are highly dependent 
upon favorable weather conditions.


Thanks much, and make it a wonderful week…..ON PURPOSE!!

From: Emanuel D. Briggs
Sent: Wednesday, September 29, 2021 12:25 PM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image001.jpg@01D7E0D6.8E215010]


PROJECT UPDATE
Wednesday, September 29, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>

Greetings DC Water Community Stakeholders:
By way of this update, we want to inform you that our Contractor will be 
working in your area this coming Saturday, October 2. Specifically, we will be 
performing the following activities:

  *   New pipe installation in the 900 block of 46th Street NE

We just wanted to ensure you had this information, in case there is any 
confusion as to why our Contractor is working on a Saturday😊

Thanks much, and please enjoy the remainder of your day!

From: Emanuel D. Briggs
Sent: Monday, September 27, 2021 10:45 PM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image001.jpg@01D7E0D6.8E215010]

PROJECT UPDATE
Monday, September 27, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>
Greetings DC Water Community Stakeholders:
Please see our revised list of ongoing and upcoming construction activities-
Active Work Location: Hunt Place NE

Weeks of September 27 - October 4


  *   Final restoration activities at some Hunt Place work locations are 
underway, and we are planning to complete this portion of work by Tuesday, 
October 5.


Active Work Location: Sheriff Road NE

Weeks of September 27 – October 18


  *   We have successfully completed installation of 450 linear feet of new 
8-inch water mains between 45th Street NE and Sheriff Road NE.

  *   We are now performing testing and disinfection of these newly installed 
water mains, and are planning to complete these activities tomorrow.
  *   We will begin installation of new water services at this location on 
Wednesday, September 29, and these activities will continue through Tuesday, 
October 5.
  *   Between Friday, October 8 and Wednesday, October 13, we will be 
performing some concrete base restoration to portions of the roadway where we 
have successfully completed water main installation, disinfection, tie-in and 
new water service installations.


  *   Prior to abandoning (taking out of service) an existing 12-inch water 
main on Sheriff Road NE (scheduled to take place between Wednesday, October 
6-Thursday, October 7), we are installing new 8-inch water mains along Sheriff 
Road. We are scheduled to complete these new water main installations tomorrow.

  *   We will be performing testing and disinfection of these newly installed 
water mains from Wednesday, September 29 – Friday, October 1.
  *   Between Wednesday, October 6 and Tuesday, October 12, we will be 
performing some concrete base restoration to portions of the roadway where we 
have successfully completed water main installation, disinfection, tie-in and 
new water service installations.




  *   We are scheduled to begin installation of 450 linear feet of new 8-inch 
water mains between 46th Street NE and Sheriff Road on Wednesday, September 29. 
We are scheduled to complete this portion of work on Tuesday, October 5.

  *   Following installation of these new mains, we will be performing testing 
and disinfection of the new mains from Wednesday, October 6 – Friday, October 8.
  *   We will begin installation of new water services at this location on 
Thursday, October 14, and these activities will continue through Tuesday, 
October 19.



Active Work Location: Hayes Street NE

Weeks of October 11 – October 25


  *   From Tuesday, October 12 through Thursday, October 28, we will be 
installing new 8-inch water mains beginning on 46th Street NE, running down to 
Hayes Street NE, then moving along Hayes Street over to 48th Street NE.

  *   Concurrent with installation of these new mains, we will be performing 
testing and disinfection of the new mains, beginning Friday, October 15.


Active Work Location: 46th Street NE

Weeks of October 4 – October 18


  *   We will be installing 350 linear feet of new 8-inch water mains on 46th 
Street NE between Jay Street NE and Hunt Place NE between Wednesday, October 6 
– Friday, October 8.

  *   Following installation of these new mains, we will be performing testing 
and disinfection of the new mains from Tuesday, October 12 – Thursday, October 
14.
  *   We will begin installation of new water services at this location on 
Friday, October 15, and these activities will continue through Tuesday, October 
19.



Please keep in mind that these construction activities are highly dependent 
upon favorable weather conditions.


Thanks much, and make it a wonderful week…..ON PURPOSE!!

From: Emanuel D. Briggs
Sent: Thursday, September 23, 2021 5:20 PM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image001.jpg@01D7E0D6.8E215010]

PROJECT UPDATE
Thursday, September 23, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>

Hello, Again, DC Water Community Stakeholders:
In addition to the pipe installation work that our Contractor will be 
performing in the 4500 block of Sheriff Road NE this Saturday, they will also 
be saw-cutting the roadway in the 900 block of 46th Street NE in preparation 
for new water main installation at this location, as well.

Thanks much.

From: Emanuel D. Briggs
Sent: Thursday, September 23, 2021 5:08 PM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image001.jpg@01D7E0D6.8E215010]


PROJECT UPDATE
Thursday, September 23, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>

Greetings DC Water Community Stakeholders:
By way of this update, we want to inform you that our Contractor will be 
working in your area this coming Saturday, September 25. Specifically, we will 
be performing the following activities:

  *   New pipe installation in the 4500 block of Sheriff Road NE.

We just wanted to ensure you had this information, in case there is any 
confusion as to why our Contractor is working on a Saturday😊

Thanks much, and have a fantastic weekend!

From: Emanuel D. Briggs
Sent: Monday, September 20, 2021 2:37 PM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image001.jpg@01D7E0D6.8E215010]


PROJECT UPDATE
Monday, September 20, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>
Greetings DC Water Community Stakeholders:
Please see our revised list of ongoing and upcoming construction activities-
Active Work Location: Hunt Place NE

Week of September 20


  *   We are performing some final restoration activities at Hunt Place work 
locations beginning today through this coming Wednesday, September 22.

Active Work Location: Sheriff Road NE

Weeks of September 20 – October 11


  *   We have successfully completed installation of 450 linear feet of new 
8-inch water mains between 45th Street NE and Sheriff Road NE.

  *   We are now performing testing and disinfection of these newly installed 
water mains beginning today through this coming Thursday, September 23.
  *   We will begin installation of new water services at this location on 
Friday, September 24, and these activities will continue through the following 
Thursday, September 30.
  *   Between Tuesday, October 5 and Thursday, October 7, we will be performing 
some concrete base restoration to portions of the roadway where we have 
successfully completed water main installation, disinfection, tie-in and new 
water service installations.


  *   Prior to abandoning (taking out of service) an existing 12-inch water 
main on Sheriff Road NE (scheduled to take place between Friday, October 
1-Monday, October 4), we will be installing new 8-inch water mains along 
Sheriff Road throughout this week.

  *   Following installation of these new mains, we will be performing testing 
and disinfection of the new mains from Monday, September 27 – Wednesday, 
September 29.
  *   Between Friday, October 1 and Wednesday, October 6, we will be performing 
some concrete base restoration to portions of the roadway where we have 
successfully completed water main installation, disinfection, tie-in and new 
water service installations.


  *   We are scheduled to begin installation of 450 linear feet of new 8-inch 
water mains between 46th Street NE and Sheriff Road throughout next week.

  *   Following installation of these new mains, we will be performing testing 
and disinfection of the new mains from Monday, October 4 – Wednesday, October 6.
  *   We will begin installation of new water services at this location on 
Friday, October 8, and these activities will continue through the following 
Thursday, October 14.



Active Work Location: Hayes Street NE

Weeks of October 4 – October 11


  *   From Thursday, October 7 through Tuesday, October 12, we will be 
installing new 8-inch water mains beginning on 46th Street NE, running down to 
Hayes Street NE, then moving along Hayes Street over to 48th Street NE.


Active Work Location: 46th Street NE

Weeks of October 4 – October 11


  *   We will be installing 350 linear feet of new 8-inch water mains on 46th 
Street NE between Jay Street NE and Hunt Place NE between Monday, October 4 – 
Wednesday, October 6.

  *   Following installation of these new mains, we will be performing testing 
and disinfection of the new mains from Thursday, October 7 – Tuesday, October 
12.



Please keep in mind that these construction activities are highly dependent 
upon favorable weather conditions.


Thanks much, and make it a wonderful week…..ON PURPOSE!!


From: Emanuel D. Briggs
Sent: Wednesday, September 15, 2021 6:29 PM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image001.jpg@01D7E0D6.8E215010]

PROJECT UPDATE
Wednesday, September 15, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>

Greetings DC Water Community Stakeholders:
By way of this update, we want to inform you that our Contractor will be 
working in your area this coming Saturday, September 18. Specifically, we will 
be performing the following activities:

  *   New pipe installation and pressure testing of newly installed water mains 
at the intersection of 45th Place NE and Sheriff Road NE.

We just wanted to ensure you had this information, in case there is any 
confusion as to why our Contractor is working on a Saturday😊

Thanks much, and have a fantastic weekend!

From: Emanuel D. Briggs
Sent: Tuesday, September 14, 2021 9:59 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image001.jpg@01D7E0D6.8E215010]

PROJECT UPDATE
Tuesday, September 14, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>
Greetings DC Water Community Stakeholders:
Please see our revised list of ongoing and upcoming construction activities-
Active Work Location: Hunt Place NE

Week of September 13 – September 20


  *   We will be performing some final restoration activities at Hunt Place 
work locations from Friday, September 17 – Wednesday, September 22.


Active Work Location: Sheriff Road NE

Weeks of September 13 – October 4


  *   We are now scheduled to install 450 linear feet of new 8-inch water mains 
between 45th Street NE and Sheriff Road NE from Monday, September 13 – Monday, 
September 20.

  *   We will be performing testing and disinfection of these newly installed 
water mains from Tuesday, September 21 – Thursday, September 23.
  *   We will begin installation of new water services at this location on 
Friday, September 24, and these activities will continue through the following 
Friday, October 1.
  *   Between Monday, October 4 and Wednesday, October 6, we will be performing 
some concrete base restoration to portions of the roadway where we have 
successfully completed water main installation, disinfection, tie-in and new 
water service installations.



  *   We are now scheduled to begin installation of an additional 300 linear 
feet of new 8-inch water mains along Sheriff Road on Tuesday, September 21, and 
this portion of work will continue through Monday, September 27.

  *   We will perform testing and disinfection of these newly installed water 
mains from Tuesday, September 28 – Thursday, September 30.


  *   We will also begin installation of 450 linear feet of new 8-inch water 
mains between 46th Street NE and Sheriff Road NE on Tuesday, September 28, and 
this portion of work will continue through Tuesday, October 5.


Please keep in mind that these construction activities are highly dependent 
upon favorable weather conditions.


Thanks much, and make it a wonderful week…..ON PURPOSE!!


From: Emanuel D. Briggs
Sent: Thursday, September 9, 2021 4:55 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image001.jpg@01D7E0D6.8E215010]


PROJECT UPDATE
Thursday, September 9, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>

Greetings DC Water Community Stakeholders:
By way of this update, we want to inform you that our Contractor will be 
working in your area this coming Saturday, September 11. Specifically, we will 
be performing the following activities:

  *   Asphalt restoration to the roadway in the 4600 block of Hunt Place NE
  *   New water main installation in the 900 block of 45th Place NE

We just wanted to ensure you had this information, in case there is any 
confusion as to why our Contractor is working on a Saturday😊

Thanks much, and have a wonderful day!

From: Emanuel D. Briggs
Sent: Sunday, August 29, 2021 11:37 PM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image001.jpg@01D7E0D6.8E215010]


PROJECT UPDATE
Sunday, August 29, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>
Greetings DC Water Community Stakeholders:
Please see our revised list of ongoing and upcoming construction activities-
Active Work Location: Hunt Place NE

Week of August 30


  *   Installation of new water services is still underway, and we now expect 
to complete this portion of work by Tuesday, August 31.



  *   We are performing some restoration activities to Hunt Place work 
locations where we have successfully completed water main installation, 
disinfection, tie-in and new water service installations. We are now planning 
to complete these activities by Thursday, September 2.


Active Work Location: Sheriff Road NE

Weeks of September 6 – September 27


  *   We will be working to install 450 linear feet of new 8-inch water mains 
between 45th Street NE and Sheriff Road NE from Tuesday, September 7 – Tuesday, 
September 14.



  *   We will be performing testing and disinfection of these newly installed 
water mains from Wednesday, September 15 – Friday, September 17.



  *   We will begin installation of new water services at this location on 
Monday, September 20, and these activities will continue through the following 
Monday, September 27.



  *   We will begin installation of an additional 300 linear feet of new 8-inch 
water mains along Sheriff Road on Wednesday, September 15, and this portion of 
work will continue through Tuesday, September 21.



As a reminder, during installation of new water services, we will be connecting 
the new water service lines to some homes to the newly installed water mains. 
Please see below specific details:

Typically, during installation of new water services, you will see the 
following:

  *   We will begin to paint the areas where we will be working, so you may 
begin to see paint markings on the sidewalk, portions of the roadway, and even 
on portions of yard spaces.
  *   Essentially, we will be replacing the portions of water service lines 
feeding homes in the block on the city (public space) side. This could include 
replacing portions of lead service lines with copper service lines in public 
space (in cases where the public portion of the service line is lead), and/or 
upgrading the diameter of the service line in public space from ¾ inch up to 1 
inch.
  *   Where property owners may have lead for the portion of their service line 
inside their private property, DC Water will replace this portion of lead line 
with copper if the property owner has signed a Lead Service Replacement 
Agreement with DC Water and a service order for this private side lead line 
replacement has been issued.
  *   We will provide our standard 48-hour advance notification door hanger 
before starting the work.
  *   As property lines vary widely across the District, we understand that for 
many of the properties, portions of the front yard spaces are located in public 
space (property owned by the District). Despite this fact, we understand 
customers’ sensitivity when it comes to disturbances inside yards, so we will 
do our very best to work around plantings and pavers in the public space 
portion of yards; we do strongly suggest that property owners temporarily 
remove these items prior to the work, however, because DC Water is not 
responsible for replacement of these items, if damaged.
  *   Similarly, for portions of yard spaces located inside customers’ private 
property, DC Water is not responsible for replacement of any plantings or 
pavers that are damaged during private side service line replacements. For this 
reason, we ask that customers temporarily remove these items inside their 
private property as well.
  *   We may, on a case-by-case basis, need to perform a test pit in some of 
the yards. This would include a small excavation (dig) in some of the yards in 
order to access the pipe and/or move the water meter from the private property 
over into the public space for future access, if needed. We just want to make 
sure you have this information.


In observation of the Labor Day Holiday, there will be no construction 
activities scheduled for Monday, September 6.

Please keep in mind that these construction activities are highly dependent 
upon favorable weather conditions.


Thanks much, and make it a wonderful week…..ON PURPOSE!!


From: Emanuel D. Briggs
Sent: Thursday, August 26, 2021 2:10 PM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood


[cid:image001.jpg@01D7E0D6.8E215010]


PROJECT UPDATE
Thursday, August 26, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>

Greetings DC Water Community Stakeholders:
By way of this update, we want to inform you that our Contractor will be 
working in your area this coming Saturday, August 28. Specifically, we will be 
performing the following activities:

  *   We will be performing asphalt restoration to the roadway in the 4600 
block of Hunt Place NE.

We just wanted to ensure you had this information, in case there is any 
confusion as to why our Contractor is working on a Saturday😊

Thanks much, and have a fantastic weekend!

From: Emanuel D. Briggs
Sent: Thursday, August 19, 2021 7:49 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image001.jpg@01D7E0D6.8E215010]

PROJECT UPDATE
Thursday, August 19, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>

Greetings DC Water Community Stakeholders:
By way of this update, we want to inform you that our Contractor will be 
working in your area this coming Saturday, August 21. Specifically, we will be 
performing the following activities:

  *   Road repaving operations in the 4400 block of Hunt Place NE
  *   Abandonment of an existing area water main located at 44th Street NE & 
Hunt Place NE
We just wanted to ensure you had this information, in case there is any 
confusion as to why our Contractor is working on a Saturday😊
Thanks much, and have a terrific remainder of your week, and a fantastic 
weekend!


From: Emanuel D. Briggs
Sent: Monday, August 16, 2021 7:33 PM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image001.jpg@01D7E0D6.8E215010]

PROJECT UPDATE
Monday, August 16, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>
Greetings DC Water Community Stakeholders:
Please see our revised list of ongoing and upcoming construction activities-
Active Work Location: Hunt Place NE

Weeks of August 16 – August 30


  *   Installation of new water services is still underway, and we now expect 
to complete this portion of work by Monday, August 30.



  *   We are performing some restoration to portions of project area streets 
where we have successfully completed water main installation, disinfection, 
tie-in and new water service installations. We are now planning to complete 
this portion of work by Thursday, August 26.



  *   We will be performing restoration activities at some Hunt Place work 
locations from Monday, August 23 – Wednesday, August 25.


Active Work Location: Sheriff Road NE

Weeks of August 30 – September 6


  *   We will be working to install new 8-inch water mains at 45th Street NE 
and Sheriff Road NE from Monday, August 30 – Wednesday, September 8.


Please keep in mind that these construction activities are highly dependent 
upon favorable weather conditions.


Thanks much, and make it a wonderful week…..ON PURPOSE!!


From: Emanuel D. Briggs
Sent: Saturday, August 7, 2021 5:08 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood


[cid:image001.jpg@01D7E0D6.8E215010]
PROJECT UPDATE
Saturday, August 7, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>

Greetings DC Water Community Stakeholders:
By way of this update, we want to inform you that our Contractor will be 
working in your area today. Specifically, we will be performing installation of 
new water services in the 4400 block of Hunt Place NE.

We just wanted to ensure you had this information, in case there is any 
confusion as to why our Contractor is working on a Saturday😊
Thanks much, and have a terrific weekend!


From: Emanuel D. Briggs
Sent: Monday, July 19, 2021 5:27 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image001.jpg@01D7E0D6.8E215010]

PROJECT UPDATE
Monday, July 19, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>
Greetings DC Water Community Stakeholders:
Please see our revised list of ongoing and upcoming construction activities-
Active Work Location: Hunt Place NE

Weeks of July 19 – August 9


  *   Installation of new water services is still underway, and we now expect 
to complete this portion of work by Friday, August 6.



  *   Between Friday, July 23 and Wednesday, August 11, we will be performing 
some concrete base restoration to portions of the roadway where we have 
successfully completed water main installation, disinfection, tie-in and new 
water service installations.


  *   We have begun the installation of new 8-inch water mains at Hunt Place 
and 46th Street, and we are planning to complete this portion of work by 
Monday, July 26.



  *   Testing and disinfection of newly installed water mains at some Hunt 
Place work locations is still underway, and we now expect to complete this 
portion of work by Monday, July 26.



Please keep in mind that these construction activities are highly dependent 
upon favorable weather conditions.


Thanks much, and make it a wonderful week…..ON PURPOSE!!


From: Emanuel D. Briggs
Sent: Monday, July 12, 2021 5:53 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image001.jpg@01D7E0D6.8E215010]


PROJECT UPDATE
Monday, July 12, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>
Greetings DC Water Community Stakeholders:
Please see our revised list of ongoing and upcoming construction activities-
Active Work Location: Hunt Place NE

Weeks of July 12 – August 2


  *   Installation of new water services is still underway, and we now expect 
to complete this portion of work by Tuesday, August 3.



  *   Between Friday, July 16 and Monday, August 2, we will be performing some 
concrete base restoration to portions of the roadway where we have successfully 
completed water main installation, disinfection, tie-in and new water service 
installations.


  *   We are now scheduled to install new 8-inch water mains at Hunt Place and 
46th Street between Tuesday, July 13 – Friday, July 16.



  *   Testing and disinfection of newly installed water mains at some Hunt 
Place work locations is still underway, and we now expect to complete this 
portion of work by Wednesday, July 21.



Please keep in mind that these construction activities are highly dependent 
upon favorable weather conditions.


Thanks much, and make it a wonderful week…..ON PURPOSE!!


From: Emanuel D. Briggs
Sent: Tuesday, July 6, 2021 7:00 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image001.jpg@01D7E0D6.8E215010]

PROJECT UPDATE
Tuesday, July 6, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>
Greetings DC Water Community Stakeholders:
Please see our revised list of ongoing and upcoming construction activities-
Active Work Location: Hunt Place NE

Weeks of July 5 – July 26


  *   Installation of new water services is still underway, and we now expect 
to complete this portion of work by Wednesday, July 28.



  *   Between Friday, July 16 and Wednesday, July 28, we will be performing 
some concrete base restoration to portions of the roadway where we have 
successfully completed water main installation, disinfection, tie-in and new 
water service installations.


  *   We are now scheduled to install new 8-inch water mains at Hunt Place and 
46th Street between Tuesday, July 13 – Thursday, July 15.



  *   Testing and disinfection of newly installed water mains at some Hunt 
Place work locations is still underway, and we now expect to complete this 
portion of work by Tuesday, July 20.



Please keep in mind that these construction activities are highly dependent 
upon favorable weather conditions.


Thanks much, and make it a wonderful week…..ON PURPOSE!!

From: Emanuel D. Briggs
Sent: Tuesday, June 29, 2021 8:53 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image001.jpg@01D7E0D6.8E215010]


PROJECT UPDATE
Tuesday, June 29, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>
Greetings DC Water Community Stakeholders:
Please see our revised list of ongoing and upcoming construction activities-
Active Work Location: Hunt Place NE

Weeks of June 28 – July 19


  *   Installation of new water services is still underway, and we now expect 
to complete this portion of work by Wednesday, July 21.



  *   Between Monday, July 12 and Wednesday, July 21, we will be performing 
some concrete base restoration to portions of the roadway where we have 
successfully completed water main installation, disinfection, tie-in and new 
water service installations.


  *   We are scheduled to install new 8-inch water mains at Hunt Place and 46th 
Street between Tuesday, July 6 – Thursday, July 8.



  *   Testing and disinfection of newly installed water mains at some Hunt 
Place work locations is still underway, and we now expect to complete this 
portion of work by Tuesday, July 13.


In observance of the Independence Day Holiday, there will be no construction 
activities scheduled for Monday, July 5.


Please keep in mind that all construction activities are highly dependent upon 
favorable weather conditions.


Thanks much, please stay tuned for more updates, and make it a wonderful 
week…..ON PURPOSE!!

From: Emanuel D. Briggs
Sent: Monday, June 14, 2021 5:23 PM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image001.jpg@01D7E0D6.8E215010]

PROJECT UPDATE
Monday, June 14, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>
Greetings DC Water Community Stakeholders:
Please be advised that our water main tie-in in the alley adjacent to 812 44th 
Street NE, originally scheduled for tomorrow morning, has been cancelled and 
will be rescheduled for another date. We will be sure to update you once we 
have a new date for this portion of work.
Thanks much.

From: Emanuel D. Briggs
Sent: Monday, June 14, 2021 5:05 PM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image001.jpg@01D7E0D6.8E215010]


PROJECT UPDATE
Monday, June 14, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>
Greetings DC Water Community Stakeholders:
Please see our revised list of ongoing and upcoming construction activities-
Active Work Location: Hunt Place NE

Weeks of June 14 – July 12


  *   Tomorrow morning beginning at 9:30am, our Contractor will be working to 
tie-in a newly installed 8-inch water in the alley adjacent to 812 44th Street 
NE. This portion of work will take approximately 8 hours to complete, and there 
will be water service outage to the following addresses during the tie-in work: 
4300 block of Jay Street NE; 900 block of 43rd Place NE; 4302-4308 Nannie Helen 
Burroughs Avenue NE (just the even numbered side of this block); and 4235 
Sheriff Road NE. All affected customers listed here have already received our 
standard 48-hour notification door hanger alerting them about this work and 
pending water service impact.


  *   Installation of new water services is still underway, and we now expect 
to complete this portion of work by Wednesday, June 30.



  *   Between Thursday, July 1 and Wednesday, July 7, we will be performing 
some concrete base restoration to portions of the roadway where we have 
successfully completed water main installation, disinfection, tie-in and new 
water service installations.


  *   We have begun the installation of new 8-inch water mains on Hunt Place, 
between 44th Street and 46th Street. We are now scheduled to complete this 
portion of work by Wednesday, June 30.



  *   Testing and disinfection of newly installed water mains at some Hunt 
Place work locations is still underway, and we now expect to complete this 
portion of work by Wednesday, July 7.



  *   We will be working on Hunt Place between 46th and 48th Streets to install 
350 linear feet of new 8-inch water mains. This portion of work is now 
scheduled to take place from Thursday, July 1 through Monday, July 12..


Please keep in mind that all construction activities are highly dependent upon 
favorable weather conditions.


Thanks much, please stay tuned for more updates, and make it a wonderful 
week…..ON PURPOSE!!


From: Emanuel D. Briggs
Sent: Monday, June 7, 2021 8:37 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image001.jpg@01D7E0D6.8E215010]


PROJECT UPDATE
Monday, June 7, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>
Greetings DC Water Community Stakeholders:
Please see our revised list of ongoing and upcoming construction activities-
Active Work Location: Hunt Place NE

Weeks of June 7 – June 28


  *   Installation of new water services is still underway, and we now expect 
to complete this portion of work by Thursday, June 24.



  *   Between Tuesday, June 15 and Tuesday, June 29, we will be performing some 
concrete base restoration to portions of the roadway where we have successfully 
completed water main installation, disinfection, tie-in and new water service 
installations.


  *   We have begun the installation of new 8-inch water mains on Hunt Place, 
between 44th Street and 46th Street. We are now scheduled to complete this 
portion of work by Thursday, June 10.



  *   Testing and disinfection of newly installed water mains at some Hunt 
Place work locations is still underway, and we now expect to complete this 
portion of work by Wednesday, June 23.



  *   We will be working on Hunt Place between 46th and 48th Streets to install 
350 linear feet of new 8-inch water mains. This portion of work is now 
scheduled to take place from Friday, June 11 through Tuesday, June 29.


  *   We are now scheduled to perform some final restoration activities at some 
Hunt Place work locations from Monday, June 21 – Friday, June 25.



As a reminder, during installation of new water services, we will be connecting 
the new water service lines to some homes to the newly installed water mains. 
Please see below specific details:

Typically, during installation of new water services, you will see the 
following:

  *   We will begin to paint the areas where we will be working, so you may 
begin to see paint markings on the sidewalk, portions of the roadway, and even 
on portions of yard spaces.
  *   Essentially, we will be replacing the portions of water service lines 
feeding homes in the block on the city (public space) side. This could include 
replacing portions of lead service lines with copper service lines in public 
space (in cases where the public portion of the service line is lead), and/or 
upgrading the diameter of the service line in public space from ¾ inch up to 1 
inch.
  *   Where property owners may have lead for the portion of their service line 
inside their private property, DC Water will replace this portion of lead line 
with copper if the property owner has signed a Lead Service Replacement 
Agreement with DC Water and a service order for this private side lead line 
replacement has been issued.
  *   We will provide our standard 48-hour advance notification door hanger 
before starting the work.
  *   As property lines vary widely across the District, we understand that for 
many of the properties, portions of the front yard spaces are located in public 
space (property owned by the District). Despite this fact, we understand 
customers’ sensitivity when it comes to disturbances inside yards, so we will 
do our very best to work around plantings and pavers in the public space 
portion of yards; we do strongly suggest that property owners temporarily 
remove these items prior to the work, however, because DC Water is not 
responsible for replacement of these items, if damaged.
  *   Similarly, for portions of yard spaces located inside customers’ private 
property, DC Water is not responsible for replacement of any plantings or 
pavers that are damaged during private side service line replacements. For this 
reason, we ask that customers temporarily remove these items inside their 
private property as well.
  *   We may, on a case-by-case basis, need to perform a test pit in some of 
the yards. This would include a small excavation (dig) in some of the yards in 
order to access the pipe and/or move the water meter from the private property 
over into the public space for future access, if needed. We just want to make 
sure you have this information.



Please keep in mind that all construction activities are highly dependent upon 
favorable weather conditions.


Thanks much, please stay tuned for more updates, and make it a wonderful 
week…..ON PURPOSE!!


From: Emanuel D. Briggs
Sent: Wednesday, June 2, 2021 7:54 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image001.jpg@01D7E0D6.8E215010]

PROJECT UPDATE
Wednesday, June 2, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>
Greetings DC Water Community Stakeholders:
Please see our revised list of ongoing and upcoming construction activities-
Active Work Location: Hunt Place NE

Weeks of May 31 – June 21


  *   Installation of new water services is still underway, and we anticipate 
completion of this portion of work by Monday, June 21.



  *   Between Thursday, June 10 and Monday, June 14, we will be performing some 
concrete base restoration to portions of the roadway where we have successfully 
completed water main installation, disinfection, tie-in and new water service 
installations.


  *   The installation of new 8-inch water mains on Hunt Place, between 44th 
Street and 46th Street is underway, and we now expect to complete this portion 
of work by Tuesday, June 8.



  *   Testing and disinfection of newly installed water mains at some Hunt 
Place work locations is also underway, and we anticipate completion of this 
portion of work by Monday, June 21.



  *   We will be working on Hunt Place between 46th and 48th Streets to install 
350 linear feet of new 8-inch water mains. This portion of work is scheduled to 
take place from Wednesday, June 9 through Friday, June 25.


  *   We are scheduled to perform some final restoration activities at some 
Hunt Place work locations from Thursday, June 17 – Wednesday, June 23.


Please keep in mind that all construction activities are highly dependent upon 
favorable weather conditions.


Thanks much, please stay tuned for more updates, and make it a wonderful 
week…..ON PURPOSE!!


From: Emanuel D. Briggs
Sent: Tuesday, May 18, 2021 7:37 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image002.jpg@01D7E0D6.8E215010]


PROJECT UPDATE
Tuesday, May 18, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>
Greetings DC Water Community Stakeholders:
Please see our revised list of ongoing and upcoming construction activities-
Active Work Location: Jay Street NE

Week of May 17



  *   We are still scheduled to perform some final restoration activities at 
some Jay Street work location from Monday, May 17 – Friday, May 21.

-----------------------------------------------------------------------------------------------------------------------------------

Active Work Location: Hunt Place NE

Weeks of May 17 – June 7


  *   We have successfully completed installation of new water services at some 
properties along Hunt Place.



  *   We have nearly completed installation of concrete base restoration to 
portions of the roadway, along with some critical water main tie-ins at some 
Hunt Place work locations. We are now scheduled to complete this portion of 
work during this week.


  *   We are still scheduled to work on installation of new 8-inch water mains 
on Hunt Place, between 44th Street and 46th Street beginning Monday, May 24. 
This portion of work is now scheduled to continue through Wednesday, June 9.



  *   We will proceed with testing and disinfection of newly installed water 
mains at other Hunt Place work locations on Thursday, June 3. This will 
continue through Monday, June 7.


  *   We are still scheduled to perform some final restoration activities at 
some Hunt Place work location from Monday, May 17 – Friday, May 21.


Please keep in mind that all construction activities are highly dependent upon 
favorable weather conditions.


Thanks much, please stay tuned for more updates, and make it a wonderful 
week…..ON PURPOSE!!

From: Emanuel D. Briggs
Sent: Monday, May 10, 2021 8:55 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image002.jpg@01D7E0D6.8E215010]

PROJECT UPDATE
Monday, May 10, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>
Greetings DC Water Community Stakeholders:
Please see our revised list of ongoing and upcoming construction activities-
Active Work Location: Jay Street NE

Week of May 17



  *   We are still scheduled to perform some final restoration activities at 
some Jay Street work location from Monday, May 17 – Friday, May 21.

-----------------------------------------------------------------------------------------------------------------------------------

Active Work Location: Hunt Place NE

Weeks of May 10 – May 31


  *   We have successfully completed testing and disinfection of newly 
installed water mains at Hunt Place work locations.



  *   We are still scheduled to complete installation of new water services at 
properties along Hunt Place today.



  *   We are still planning to perform concrete base restoration to portions of 
the roadway, as well as complete some critical water main tie-ins at some Hunt 
Place work locations this week as well.


  *   We are still scheduled to work on installation of new 8-inch water mains 
on Hunt Place, between 44th Street and 46th Street beginning Monday, May 24 
through Wednesday, June 2.


  *   We are still scheduled to perform some final restoration activities at 
some Hunt Place work location from Monday, May 17 – Friday, May 21.


Please keep in mind that all construction activities are highly dependent upon 
favorable weather conditions.


Thanks much, please stay tuned for more updates, and make it a wonderful 
week…..ON PURPOSE!!


From: Emanuel D. Briggs
Sent: Tuesday, May 4, 2021 5:54 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image002.jpg@01D7E0D6.8E215010]

PROJECT UPDATE
Tuesday, May 4, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>
Greetings DC Water Community Stakeholders:
Please see our revised list of ongoing and upcoming construction activities-
Active Work Location: Jay Street NE

Weeks of May 3 – May 17


  *   We have successfully completed the installation of new water services at 
properties along Jay Street.


  *   We are still scheduled to perform concrete base restoration to portions 
of the roadway at some Jay Street work locations throughout this week.



  *   We are currently scheduled to perform some final restoration activities 
at some Jay Street work location from Monday, May 17 – Friday, May 21.

-----------------------------------------------------------------------------------------------------------------------------------

Active Work Location: Hunt Place NE

Weeks of May 3 – May 31


  *   We have begun testing and disinfection of newly installed water mains at 
some Hunt Place work locations, and anticipate completion of this portion of 
work early this week.



  *   We are now scheduled to begin installation of new water services at some 
properties along Hunt Place tomorrow, and this will continue through next 
Monday, May 10.



  *   We are now planning to perform concrete base restoration to portions of 
the roadway at some Hunt Place work locations, and complete all final needed 
water main tie-ins, from next Tuesday, May 11 through the following Friday, May 
14.


  *   We are now scheduled to work on installation of new 8-inch water mains on 
Hunt Place, between 44th Street and 46th Street beginning Monday, May 24 
through Wednesday, June 2.


  *   We are currently scheduled to perform some final restoration activities 
at some Hunt Place work location from Monday, May 17 – Friday, May 21.


Please keep in mind that all construction activities are highly dependent upon 
favorable weather conditions.


Thanks much, please stay tuned for more updates, and make it a wonderful 
week…..ON PURPOSE!!


From: Emanuel D. Briggs
Sent: Wednesday, April 28, 2021 9:02 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image002.jpg@01D7E0D6.8E215010]

PROJECT UPDATE
Wednesday, April 28, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>
Greetings DC Water Community Stakeholders:
In addition to the weekly update we’ve sent to you on Monday, please see below 
for an additional portion of work we have scheduled for this week-
Active Work Location: Jay Street NE

Week of April 26


  *   This morning (Wednesday, April 28) beginning at 9:30am, our Contractor 
will be working at 47th Place and Jay Street to tie newly installed 8-inch 
water mains into the existing drinking water distribution system. This portion 
of work will take approximately 8 hours to complete, and there will be 
interruption of water service to customers within the 900 block of 47th Place 
NE during the tie-in work. All affected customers have already received our 
standard 48 hour notification prior to this portion of work and pending water 
service impacts.

Thanks much, and please let us know if you have any questions.


From: Emanuel D. Briggs
Sent: Monday, April 26, 2021 7:32 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image002.jpg@01D7E0D6.8E215010]

PROJECT UPDATE
Monday, April 26, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>
Greetings DC Water Community Stakeholders:
Please see our revised list of ongoing and upcoming construction activities-
Active Work Location: Jay Street NE

Weeks of April 26 – May 3


  *   Installation of new water services at some properties along Jay Street is 
still underway, and we are now scheduled to complete this phase of work by this 
coming Friday, April 30.


  *   We are scheduled to perform concrete base restoration to portions of the 
roadway at some Jay Street work locations from Monday, May 3 through Friday, 
May 7.

-----------------------------------------------------------------------------------------------------------------------------------

Active Work Location: Hunt Place NE

Weeks of April 26 – May 24


  *   We have begun testing and disinfection of newly installed water mains at 
some Hunt Place work locations, and anticipate completion of this portion of 
work by Tuesday, April 27.



  *   We will begin installation of new water services at some properties along 
Hunt Place this coming Wednesday, April 28 and this will continue through 
Monday, May 3 (please see the highlighted portion below for a reminder of what 
to expect during installation of new water services).



  *   We are planning to perform concrete base restoration to portions of the 
roadway at some Hunt Place work locations, as well as complete all final needed 
water main tie-ins, from Tuesday, May 4 through Friday, May 7.


  *   We are now scheduled to work on installation of new 8-inch water mains on 
Hunt Place, between 44th Street and 46th Street beginning Monday, May 17 
through Tuesday, May 25.


During installation of new water services, we will be connecting the new water 
service lines to some homes to the newly installed water mains. Please see 
below specific details:

Typically, during installation of new water services, you will see the 
following:

  *   We will begin to paint the areas where we will be working, so you may 
begin to see paint markings on the sidewalk, portions of the roadway, and even 
on portions of yard spaces.
  *   Essentially, we will be replacing the portions of water service lines 
feeding homes in the block on the city (public space) side. This could include 
replacing portions of lead service lines with copper service lines in public 
space (in cases where the public portion of the service line is lead), and/or 
upgrading the diameter of the service line in public space from ¾ inch up to 1 
inch.
  *   Where property owners may have lead for the portion of their service line 
inside their private property, DC Water will replace this portion of lead line 
with copper if the property owner has signed a Lead Service Replacement 
Agreement with DC Water and a service order for this private side lead line 
replacement has been issued.
  *   We will provide our standard 48-hour advance notification door hanger 
before starting the work.
  *   As property lines vary widely across the District, we understand that for 
many of the properties, portions of the front yard spaces are located in public 
space (property owned by the District). Despite this fact, we understand 
customers’ sensitivity when it comes to disturbances inside yards, so we will 
do our very best to work around plantings and pavers in the public space 
portion of yards; we do strongly suggest that property owners temporarily 
remove these items prior to the work, however, because DC Water is not 
responsible for replacement of these items, if damaged.
  *   Similarly, for portions of yard spaces located inside customers’ private 
property, DC Water is not responsible for replacement of any plantings or 
pavers that are damaged during private side service line replacements. For this 
reason, we ask that customers temporarily remove these items inside their 
private property as well.
  *   We may, on a case-by-case basis, need to perform a test pit in some of 
the yards. This would include a small excavation (dig) in some of the yards in 
order to access the pipe and/or move the water meter from the private property 
over into the public space for future access, if needed. We just want to make 
sure you have this information.



Please keep in mind that all construction activities are highly dependent upon 
favorable weather conditions.


Thanks much, please stay tuned for more updates, and make it a wonderful 
week…..ON PURPOSE!!


From: Emanuel D. Briggs
Sent: Wednesday, April 21, 2021 8:52 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image002.jpg@01D7E0D6.8E215010]

PROJECT UPDATE
Wednesday, April 21, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>
Greetings DC Water Community Stakeholders:
In addition to the weekly update we’ve sent to you on Monday, please see below 
for an additional portion of work we have scheduled for this week-
Active Work Location: Jay Street NE

Week of April 19


  *   Tomorrow night (Thursday, April 22) beginning at 9:00pm, our Contractor 
will be working at 48th Street and Jay Street to tie newly installed 8-inch 
water mains into the existing drinking water distribution system. This portion 
of work will take approximately 8 hours to complete, and there will be 
interruption of water service to customers within the 900 block of 48th Street 
NE during the tie-in work. All affected customers have received our standard 48 
hour notification prior to this portion of work and pending water service 
impacts.

Thanks much, and please let us know if you have any questions.

From: Emanuel D. Briggs
Sent: Monday, April 19, 2021 1:10 PM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image003.jpg@01D7E0D6.8E215010]

PROJECT UPDATE
Monday, April 19, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>
Greetings DC Water Community Stakeholders:
Please see our revised list of ongoing and upcoming construction activities-
Active Work Location: Jay Street NE

Weeks of April 19 – May 3


  *   Tomorrow beginning at 9:30am, our Contractor will be working at 48th 
Place and Jay Street to tie newly installed 8-inch water mains into the 
existing drinking water distribution system. This portion of work will take 
approximately 8 hours to complete, and there will be interruption of water 
service to customers within the 900 block of 48th Place and 4800 block of Jay 
Street during the tie-in work. All affected customers have received our 
standard 48 hour notification prior to this portion of work and pending water 
service impacts.


  *   Installation of new water services at some properties along Jay Street is 
still underway, and we are now scheduled to complete this phase of work by 
Monday, May 3.


  *   We are now scheduled to perform mill and overlay (final paving 
restoration) operations on Jay Street from 43rd to 47th Streets from Wednesday, 
April 21 – Friday, April 23.

-----------------------------------------------------------------------------------------------------------------------------------

Active Work Location: Hunt Place NE

Weeks of April 19 – May 17


  *   We have successfully completed the installation of 350 linear feet of new 
8-inch water mains on 44th Street, between Jay Street and Hunt Place.


  *   We are now scheduled to work on installation of new 8-inch water mains on 
Hunt Place, between 44th Street and 46th Street beginning Monday, April 26 
through Wednesday, May 19.


Please keep in mind that all construction activities are highly dependent upon 
favorable weather conditions.


Thanks much, please stay tuned for more updates, and make it a wonderful 
week…..ON PURPOSE!!


From: Emanuel D. Briggs
Sent: Friday, April 16, 2021 12:57 PM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image004.jpg@01D7E0D6.8E215010]

PROJECT UPDATE
Friday, April 16, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>
Greetings DC Water Community Stakeholders:
By way of this update, we wanted to inform you that our Contractor was able to 
complete the water main tie-in work at 49th Street and Jay Street yesterday, 
but additional coordination is needed in order to complete the other tie-in at 
48th Place and Jay Street.
We have plans to reschedule the tie-in at 48th Place and Jay Street for some 
time next week. We will also need to complete another water main tie-in at 48th 
Street and Jay Street, and we are planning to get this done next week as well. 
Once we have confirmed dates/times for these tie-in locations, we will provide 
this information to you all, accordingly.
Thanks much.
From: Emanuel D. Briggs
Sent: Thursday, April 15, 2021 6:16 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image004.jpg@01D7E0D6.8E215010]

PROJECT UPDATE
Thursday, April 15, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>
Greetings DC Water Community Stakeholders:
By way of this email, we wanted to inform you that our Contractor will be 
working in the area this morning beginning at 9:30am to tie in newly installed 
8-inch water mains at the following intersections: 48th Place NE and Jay Street 
NE and 49th Street NE and Jay Street NE. This portion of work will take 
approximately 8 hours to complete, and there will be scheduled water service 
outage to customers in the following blocks during the work:

  *   4800 block of Jay Street NE
  *   900 block of 48th Place NE
All affected addresses listed above have received our standard 48-hour prior 
notification about this work and pending water service impacts.
We apologize for any inconvenience, and thank you for your continued patience 
as we complete this critical portion of work.
For any additional questions or concerns, please contact our 24-Hour 
Emergency/Command Center at (202) 612-3400.

From: Emanuel D. Briggs
Sent: Monday, April 12, 2021 7:53 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image005.jpg@01D7E0D6.8E215010]

PROJECT UPDATE
Monday, April 12, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>
Greetings DC Water Community Stakeholders:
Please see our revised list of ongoing and upcoming construction activities-
Active Work Location: Jay Street NE

Weeks of April 12 – April 26


  *   Installation of new water services at some properties along Jay Street is 
underway, and we are still scheduled to complete this phase of work by Monday, 
April 19.



  *   We are still scheduled to perform concrete base restoration to the 
roadway and final tie-ins of newly installed water mains at some Jay Street 
work locations from Tuesday, April 20 through Thursday, April 29.



  *   We are scheduled to perform mill and overlay (final paving restoration) 
operations on Jay Street from 43rd to 47th Streets from Monday, April 19 – 
Thursday, April 22.

-----------------------------------------------------------------------------------------------------------------------------------

Active Work Location: Hunt Place NE

Week of April 12


  *   We are now scheduled to complete installation of 350 linear feet of new 
8-inch water mains on 44th Street, between Jay Street and Hunt Place this week.


In observation of the DC Emancipation Day Holiday, there are no construction 
activities scheduled for Friday, April 16.


Please keep in mind that all construction activities are highly dependent upon 
favorable weather conditions.


Thanks much, please stay tuned for more updates, and make it a wonderful 
week…..ON PURPOSE!!


From: Emanuel D. Briggs
Sent: Friday, April 9, 2021 2:01 PM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood


[cid:image005.jpg@01D7E0D6.8E215010]

PROJECT UPDATE
Friday, April 9, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>
Greetings DC Water Community Stakeholders:
We are aware that some area customers within the vicinity of our ongoing water 
main replacement project have been experiencing low water pressure issues over 
recent weeks. We are reaching out to let you know that our maintenance crews 
worked throughout last night and into this morning to get to the bottom of 
things and find out what was going on. We did identify an open valve that was 
causing an unnecessary breach in the local drinking water distribution system. 
This opening caused the local pressure to be drawn away from some of the area 
streets, toward Sherriff Road. This valve has now been closed, and our 
Contractor is now reading much higher pressure levels, specifically from 44th 
and 49th Streets.

While previously affected residents should now be seeing normal water pressure 
returned to their homes, there may be some residual water pressure issues to 
some area homes, due to air and/or sedimentation trapped in water service lines 
to some homes. If you are still experiencing pressure issues, we recommend that 
you turn on your cold water at the lowest point in your home, and let the cold 
water run for about 10 minutes. If you have removable faucet aerators at the 
end of your faucets, please remove each of these and check the screens for any 
possible sedimentation buildup. These steps should also help to address any 
water quality concerns for area customers (such as discoloration). If you do 
have any water quality issues that persist after following these steps, please 
call our Drinking Water Division at (202) 612-3440.

We apologize for any inconvenience, and we thank you for your patience as we 
worked to resolve this matter.

From: Emanuel D. Briggs
Sent: Monday, April 5, 2021 12:39 PM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image005.jpg@01D7E0D6.8E215010]

PROJECT UPDATE
Monday, April 5, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>
Greetings DC Water Community Stakeholders:
Please see our revised list of ongoing and upcoming construction activities-
Active Work Location: Jay Street NE

Weeks of March 29 – April 26


  *   Tomorrow beginning at 9:30am, our Contractor will be working at 47th and 
Jay Streets NE to tie a newly installed 8-inch water main into the existing 
drinking water distribution system. This portion of work will take 
approximately 8 hours to complete, and there will be interruption of water 
service to customers within the 900 block of 47th Street during the tie-in 
work. All affected customers have received our standard 48 hour notification 
prior to this portion of work and pending water service impacts.


  *   We are still scheduled to install new water services at some Jay Street 
work locations from Thursday, April 1 through Monday, April 19.



  *   We are scheduled to perform concrete base restoration to the roadway at 
some Jay Street work locations from Tuesday, April 20 through Thursday, April 
29.

-----------------------------------------------------------------------------------------------------------------------------------

Active Work Location: Hunt Place NE

Weeks of March 29 – April 26


  *   We are still scheduled to complete installation of 350 linear feet of new 
8-inch water mains on 44th Street, between Jay Street and Hunt Place today.


  *   We are still scheduled to work on installation of new 8-inch water mains 
on Hunt Place, between 44th Street and 46th Street beginning tomorrow through 
Thursday, April 29.


Please keep in mind that all construction activities are highly dependent upon 
favorable weather conditions.


Thanks much, please stay tuned for more updates, and make it a wonderful 
week…..ON PURPOSE!!

From: Emanuel D. Briggs
Sent: Monday, March 29, 2021 8:34 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image006.jpg@01D7E0D6.8E215010]

PROJECT UPDATE
Monday, March 29, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>
Greetings DC Water Community Stakeholders:
Please see our revised list of ongoing and upcoming construction activities-
Active Work Location: Jay Street NE

Weeks of March 29 – April 19


  *   We have successfully completed installation and testing/disinfection of 
all new water mains on Jay Street.


  *   We are still scheduled to install new water services at some Jay Street 
work locations from Thursday, April 1 through Monday, April 19.

  *   As you are aware, we use these weekly community updates to periodically 
remind customers about what they                                                
                                can expect to see during installation of new 
water services. During this portion of work we will be connecting the new water 
service lines to homes in these blocks to the newly installed water mains. 
Please see below specific details:

Typically, during installation of new water services, you will see the 
following:

  *   We will begin to paint the areas where we will be working, so you may 
begin to see paint markings on the sidewalk, portions of the roadway, and even 
on portions of yard spaces.
  *   Essentially, we will be replacing the portions of water service lines 
feeding homes in the block on the city (public space) side. This could include 
replacing portions of lead service lines with copper service lines in public 
space (in cases where the public portion of the service line is lead), and/or 
upgrading the diameter of the service line in public space from ¾ inch up to 1 
inch.
  *   Where property owners may have lead for the portion of their service line 
inside their private property, DC Water will replace this portion of lead line 
with copper if the property owner has signed a Lead Service Replacement 
Agreement with DC Water and a service order for this private side lead line 
replacement has been issued.
  *   We will provide our standard 48-hour advance notification door hanger 
before starting the work.
  *   As property lines vary widely across the District, we understand that for 
many of the properties, portions of the front yard spaces are located in public 
space (property owned by the District). Despite this fact, we understand 
customers’ sensitivity when it comes to disturbances inside yards, so we will 
do our very best to work around plantings and pavers in the public space 
portion of yards; we do strongly suggest that property owners temporarily 
remove these items prior to the work, however, because DC Water is not 
responsible for replacement of these items, if damaged.
  *   Similarly, for portions of yard spaces located inside customers’ private 
property, DC Water is not responsible for replacement of any plantings or 
pavers that are damaged during private side service line replacements. For this 
reason, we ask that customers temporarily remove these items inside their 
private property as well.
  *   We may, on a case-by-case basis, need to perform a test pit in some of 
the yards. This would include a small excavation (dig) in some of the yards in 
order to access the pipe and/or move the water meter from the private property 
over into the public space for future access, if needed. We just want to make 
sure you have this information.


-----------------------------------------------------------------------------------------------------------------------------------

Active Work Location: Hunt Place NE

Weeks of March 29 – April 26


  *   We are now scheduled to work on installation of 350 linear feet of new 
8-inch water mains on 44th Street, between Jay Street and Hunt Place from 
Friday, March 26 – Monday, April 5.


  *   We are now scheduled to work on installation of new 8-inch water mains on 
Hunt Place, between 44th Street and 46th Street from Tuesday, April 6 – 
Thursday, April 29.


Please keep in mind that all construction activities are highly dependent upon 
favorable weather conditions.


Thanks much, please stay tuned for more updates, and make it a wonderful 
week…..ON PURPOSE!!

From: Emanuel D. Briggs
Sent: Tuesday, March 23, 2021 4:22 PM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image006.jpg@01D7E0D6.8E215010]
PROJECT UPDATE
Tuesday, March 23, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>

Greetings DC Water Community Stakeholders:
Our water main tie-in work at 44th and Jay Streets NE has been rescheduled for 
this coming Thursday from 9:30am-5:30pm. Once again, there will be water 
service outage in the 900 block of 44th Street NE during this work.

Thanks much, and please let us know if you have any questions.

From: Emanuel D. Briggs
Sent: Tuesday, March 23, 2021 6:21 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image007.jpg@01D7E0D6.8E215010]

PROJECT UPDATE
Tuesday, March 23, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>

Greetings DC Water Community Stakeholders:
Please disregard my previous email. Our water main tie-in at 44th and Jay 
Streets NE, originally scheduled for this morning, is being postponed. We will 
inform you once this portion of work has been rescheduled.

Thanks much.

From: Emanuel D. Briggs
Sent: Tuesday, March 23, 2021 6:03 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image008.jpg@01D7E0D6.8E215010]


PROJECT UPDATE
Tuesday, March 23, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>

Greetings DC Water Community Stakeholders:
In addition to the weekly update that we’ve provided to you yesterday morning, 
we also needed to inform you that our Contractor will be working at 44th and 
Jay Streets NE this morning to tie newly installed 8-inch water mains into the 
existing drinking water distribution system. This portion of work will take 
place from 9:30am – 5:30pm, and there will be water outage in the 900 block of 
44th Street NE during the tie-in.

All affected customers in this block have received our standard 48-hour 
notification door hanger prior to this morning’s tie-in work and scheduled 
water outage.

We apologize for any inconvenience, and thank you in advance for your 
cooperation while we complete this critical portion of work.

From: Emanuel D. Briggs
Sent: Monday, March 22, 2021 5:48 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image009.jpg@01D7E0D6.8E215010]

PROJECT UPDATE
Monday, March 22, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>

Greetings DC Water Community Stakeholders:
Please see our revised list of ongoing and upcoming construction activities-
Active Work Location: Jay Street NE

Week of March 22


  *   We have successfully completed the installation of 300 linear feet of new 
8-inch water mains on Jay Street, between 48th Place and 49th Street.


  *   Testing and disinfection of newly installed water mains at some Jay 
Street work locations is nearly completed, and should be done sometime this 
week.

Week of March 29


  *   We are still scheduled to install new water services at some Jay Street 
work locations from Thursday, April 1 through Monday, April 19.

-----------------------------------------------------------------------------------------------------------------------------------

Active Work Location: Hunt Place NE

Week of March 22


  *   We are now scheduled to work on installation of 350 linear feet of new 
8-inch water mains on 44th Street, between Jay Street and Hunt Place from 
Tuesday, March 23 – Wednesday, March 31.

Week of March 29


  *   We are now scheduled to work on installation of new 8-inch water mains on 
Hunt Place, between 44th Street and 46th Street from Thursday, April 1 – 
Monday, April 26.


Please keep in mind that all construction activities are highly dependent upon 
favorable weather conditions.


Thanks much, please stay tuned for more updates, and make it a wonderful 
week…..ON PURPOSE!!

From: Emanuel D. Briggs
Sent: Monday, March 15, 2021 9:24 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image010.jpg@01D7E0D6.8E215010]


PROJECT UPDATE
Monday, March 15, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>

Greetings DC Water Community Stakeholders:
Please see our revised list of ongoing and upcoming construction activities-
Active Work Location: Jay Street NE

Week of March 15


  *   We have successfully completed the installation of 300 linear feet of new 
8-inch water mains on Jay Street, between 48th Street and 48th Place.


  *   We have nearly completed the installation of 300 linear feet of new 
8-inch water mains on Jay Street, between 48th Place and 49th Street, and are 
now scheduled to complete this portion of work during this week.


  *   Testing and disinfection of newly installed water mains at Jay Street 
work locations is still on schedule to take place throughout this week.

Week of March 29


  *   We are now scheduling to install new water services at some Jay Street 
work locations from Thursday, April 1 through Monday, April 19.

-----------------------------------------------------------------------------------------------------------------------------------

Active Work Location: Hunt Place NE

Week of March 15


  *   We are still scheduled to work on installation of 350 linear feet of new 
8-inch water mains on 44th Street, between Jay Street and Hunt Place from 
Monday, March 15 – Tuesday, March 23.

Week of March 22


  *   We are still scheduled to work on installation of new 8-inch water mains 
on Hunt Place, between 44th Street and 46th Street from Wednesday, March 24 – 
Friday, April 16.


Please keep in mind that all construction activities are highly dependent upon 
favorable weather conditions.


Thanks much, please stay tuned for more updates, and make it a wonderful 
week…..ON PURPOSE!!


From: Emanuel D. Briggs
Sent: Monday, March 8, 2021 6:05 PM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image011.jpg@01D7E0D6.8E215010]


PROJECT UPDATE
Monday, March 8, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>

Greetings DC Water Community Stakeholders:
Please see our revised list of ongoing and upcoming construction activities-

Active Work Location: Jay Street NE

Week of March 8


  *   We have nearly completed the installation of 300 linear feet of new 
8-inch water mains on Jay Street, between 48th Street and 48th Place, and are 
now scheduled to complete this portion of work today.


  *   We are now scheduled to begin installation of 300 linear feet of new 
8-inch water mains on Jay Street, between 48th Place and 49th Street on 
Tuesday, March 9; we are now scheduled to complete this portion of work by 
Friday, March 12.

Week of March 15


  *   Testing and disinfection of newly installed water mains at Jay Street 
work locations is now scheduled to take place from Monday, March 15 through 
Friday, March 19.

Week of March 29


  *   We are now scheduling to install new water services at some Jay Street 
work locations from Monday, March 29 through Wednesday, April 14.

-----------------------------------------------------------------------------------------------------------------------------------

Active Work Location: Hunt Place NE

Week of March 15


  *   We are now scheduled to begin installation of 350 linear feet of new 
8-inch water mains on 44th Street, between Jay Street and Hunt Place on Monday, 
March 15; we are now scheduled to complete this portion of work by Tuesday, 
March 23.

Week of March 22


  *   We are scheduled to begin installation of new 8-inch water mains on Hunt 
Place between 44th Street and 46th Street on Wednesday, March 24; we are 
scheduled to complete this portion of work by Friday, April 16.

--------------------------------------------------------------------------------------------------------------------------------------

As a final piece of information for this week’s update, we want to inform you 
of a separate notification that many of you have already begun receiving from 
DC Water. As some of you may be aware, prior to any scheduled water shut-offs 
we will have for water main tie-ins as part of this project, we will need to 
conduct what we call “test-shuts”. During test-shuts, we will essentially need 
to visit the area and check valves along the existing mains in order to 
identify operational valves that will be needed to turn off water inside the 
mains when we need to conduct this phase of work. In testing the valves, we 
will essentially be turning them on and off for brief intervals, so some 
residents will experience brief interruptions in their water service during 
these test-shuts. We will be conducting a series test-shuts in your area on the 
following dates:


  *   Tuesday, March 9 – Test-shuts will be conducted in the 44th Street and 
Nannie Helen Burroughs Avenue area
  *   Wednesday, March 10 – Test shuts will be conducted in the 48th and Hayes 
Streets area
  *   Thursday, March 11 – Test shuts will be conducted in the 47th Place and 
Jay Street area

All test-shuts are scheduled to start at 9:30am and last for approximately 2-4 
hours.

Now, for the notification information – besides this update from me, all 
customers whom will be affected by these test-shuts are also receiving 
notifications via our ‘Everbridge’ automated notification system. Affected 
customers will be receiving this separate notification to both their email and 
telephone accounts that we have on file for them. Should any of you receive 
these notifications, we just want you to be aware of them, and not be alarmed. 
This is all being done as step toward improving our outreach and notification 
efforts to inform our valued customers of scheduled water shut-offs.
----------------------------------------------------------------------------------------------------------------------------------------

Please keep in mind that all construction activities are highly dependent upon 
favorable weather conditions.


Thanks much, please stay tuned for more updates, and make it a wonderful 
week…..ON PURPOSE!!


From: Emanuel D. Briggs
Sent: Monday, March 1, 2021 8:23 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image012.jpg@01D7E0D6.8E215010]


PROJECT UPDATE
Monday, March 1, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>

Greetings DC Water Community Stakeholders:
Please see our revised list of ongoing and upcoming construction activities-

Active Work Location: Jay Street NE

Week of March 1


  *   We have more than halfway completed the installation of 300 linear feet 
of new 8-inch water mains on Jay Street, between 48th Street and 48th Place, 
and are now scheduled to complete this portion of work by Wednesday, March 3.

Week of March 8


  *   We are now scheduled to begin installation of 300 linear feet of new 
8-inch water mains on Jay Street, between 48th Place and 49th Street on 
Thursday, March 4; we are now scheduled to complete this portion of work by 
Tuesday, March 9.

Week of March 15


  *   Testing and disinfection of newly installed water mains at Jay Street 
work locations is now scheduled to take place from Wednesday, March 10 through 
Tuesday, March 16.


  *   We are still scheduled to install new water services at some Jay Street 
work locations from Monday, March 1 through Tuesday, March 16.

  *   As mentioned in a previous update, during this portion of work we will be 
connecting the new water service lines to homes in these blocks to the newly 
installed water mains. As a reminder, please see below specific details on what 
residents can expect to see during installation of new water services.

Typically, during installation of new water services, you will see the 
following:

  *   We will begin to paint the areas where we will be working, so you may 
begin to see paint markings on the sidewalk, portions of the roadway, and even 
on portions of yard spaces.
  *   Essentially, we will be replacing the portions of water service lines 
feeding homes in the block on the city (public space) side. This could include 
replacing portions of lead service lines with copper service lines in public 
space (in cases where the public portion of the service line is lead), and/or 
upgrading the diameter of the service line in public space from ¾ inch up to 1 
inch.
  *   Where property owners may have lead for the portion of their service line 
inside their private property, DC Water will replace this portion of lead line 
with copper if the property owner has signed a Lead Service Replacement 
Agreement with DC Water and a service order for this private side lead line 
replacement has been issued.
  *   We will provide our standard 48-hour advance notification door hanger 
before starting the work.
  *   As property lines vary widely across the District, we understand that for 
many of the properties, portions of the front yard spaces are located in public 
space (property owned by the District). Despite this fact, we understand 
customers’ sensitivity when it comes to disturbances inside yards, so we will 
do our very best to work around plantings and pavers in the public space 
portion of yards; we do strongly suggest that property owners temporarily 
remove these items prior to the work, however, because DC Water is not 
responsible for replacement of these items, if damaged.
  *   Similarly, for portions of yard spaces located inside customers’ private 
property, DC Water is not responsible for replacement of any plantings or 
pavers that are damaged during private side service line replacements. For this 
reason, we ask that customers temporarily remove these items inside their 
private property as well.
  *   We may, on a case-by-case basis, need to perform a test pit in some of 
the yards. This would include a small excavation (dig) in some of the yards in 
order to access the pipe and/or move the water meter from the private property 
over into the public space for future access, if needed. We just want to make 
sure you have this information.



Active Work Location: Hunt Place NE

Week of March 8


  *   We are now scheduled to begin installation of 350 linear feet of new 
8-inch water mains on 44th Street, between Jay Street and Hunt Place on 
Wednesday, March 10; we are now scheduled to complete this portion of work by 
Thursday, March 18.



Please keep in mind that these construction activities are highly dependent 
upon favorable weather conditions.


Thanks much, please stay tuned for more updates, and make it a wonderful 
week…..ON PURPOSE!!


From: Emanuel D. Briggs
Sent: Monday, February 22, 2021 1:28 PM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image013.jpg@01D7E0D6.8E215010]


PROJECT UPDATE
Monday, February 22, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>

Greetings DC Water Community Stakeholders:
In addition to the weekly update you’ve just received this morning, we also 
wanted to inform you that our Contractor will be working at Jay Street NE and 
43rd Place NE this coming Wednesday (February 24) beginning at 9:30am to tie 
newly installed 8-inch water mains into the existing drinking water 
distribution system.
This portion of work will take approximately 8 hours to complete, and will 
result in scheduled water service outage to the following addresses during the 
tie-in:

  *   4300 block of Jay Street NE
  *   4302-4308 Nannie Helen Burroughs Avenue NE
  *   900 block of 43rd Place NE
  *   4235 Sheriff Road NE
All affected customers listed above have received our standard 48-hour 
notification prior to the work and water outage.

We apologize for any inconvenience, and thank you for your patience and 
cooperation as we complete this critical portion of work.

Please let us know if you have any questions.

From: Emanuel D. Briggs
Sent: Monday, February 22, 2021 11:10 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood


[cid:image013.jpg@01D7E0D6.8E215010]


PROJECT UPDATE
Monday, February 22, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>

Greetings DC Water Community Stakeholders:
Please see our revised list of ongoing and upcoming construction activities-

Active Work Location: Jay Street NE

Week of February 15


  *   As of last week, we have successfully completed the installation of 250 
linear feet of new 8-inch water mains on Jay Street, between 47th Place and 
48th Street.

Week of February 22


  *   We have begun the installation of 300 linear feet of new 8-inch water 
mains on Jay Street, between 48th Street and 48th Place, and are still 
scheduled to complete this portion of work by Friday, February 26.

Week of March 1


  *   We are still scheduled to begin installation of 300 linear feet of new 
8-inch water mains on Jay Street, between 48th Place and 49th Street on Monday, 
March 1; we are also still scheduled to complete this portion of work by 
Thursday, March 4.


  *   We will be performing testing and disinfection of newly installed water 
mains at all above listed Jay Street locations from Friday, March 5 through 
Thursday, March 11.


  *   We will be installing new water services at all above listed Jay Street 
locations from Monday, March 1 through Tuesday, March 16.



Active Work Location: Hunt Place NE

Week of March 1


  *   We are scheduled to begin installation of new 8-inch water mains on 44th 
Street, between Jay Street and Hunt Place on Friday, March 5; we are scheduled 
to complete this portion of work by Monday, March 15.


Please keep in mind that these construction activities are highly dependent 
upon favorable weather conditions.


Thanks much, please stay tuned for more updates, and make it a wonderful 
week…..ON PURPOSE!!


From: Emanuel D. Briggs
Sent: Tuesday, February 16, 2021 10:17 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image013.jpg@01D7E0D6.8E215010]


PROJECT UPDATE
Tuesday, February 16, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>

Greetings DC Water Community Stakeholders:
Please see our revised list of ongoing and upcoming construction activities-
Active Work Location: Jay Street NE

Week of February 15


  *   Testing and disinfection of newly installed water mains on Jay Street are 
still ongoing.



  *   We have begun the installation of 250 linear feet of new 8-inch water 
mains on Jay Street, between 47th Place and 48th Street, and we are now 
scheduled to complete this portion of work by tomorrow, February 17.

  *   For this location, we are now scheduled to install new water services 
from Wednesday, February 24 through Thursday, March 11.

Week of February 22


  *   We are now planning to begin the installation of 300 linear feet of new 
8-inch water mains on Jay Street, between 48th Street and 48th Place on 
Thursday, February 18; we are now scheduled to complete this portion of work on 
Friday, February 26.

Week of March 1


  *   We are scheduled to begin installation of 300 linear feet of new 8-inch 
water mains on Jay Street, between 48th Place and 49th Street on Monday, March 
1; we are scheduled to complete this portion of work on Thursday, March 4.



Please keep in mind that these construction activities are highly dependent 
upon favorable weather conditions.


Thanks much, please stay tuned for more updates, and make it a wonderful 
week…..ON PURPOSE!!


From: Emanuel D. Briggs
Sent: Tuesday, February 9, 2021 7:08 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image013.jpg@01D7E0D6.8E215010]


PROJECT UPDATE
Tuesday, February 9, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>

Greetings DC Water Community Stakeholders:
Please see our revised list of ongoing and upcoming construction activities-
Active Work Location: Jay Street NE

Weeks of February 8 and February 15


  *   We have successfully completed the installation of 250 linear feet of new 
8-inch water mains on Jay Street, between 47th Street and 47th Place.


  *   We have begun testing and disinfection of the newly installed water mains 
on Jay Street, and these procedures are still ongoing.



  *   We have begun the installation of 250 linear feet of new 8-inch water 
mains on Jay Street, between 47th Place and 48th Street, and we are now 
scheduled to complete this portion of work by Tuesday, February 16.

  *   For this location, we are tentatively scheduled to install new water 
services from Wednesday, February 10 through Friday, February 26. During this 
phase of work, we will be connecting the water service lines to homes in these 
blocks to the newly installed water mains. Please see below specific details on 
what residents can expect to see during installation of new water services.

Week of February 22


  *   We are now planning to begin the installation of 300 linear feet of new 
8-inch water mains on Jay Street, between 48th Street and 48th Place on 
Wednesday, February 17; we are now scheduled to complete this portion of work 
on Thursday, February 25.

Typically, during installation of new water services, you will see the 
following:

  *   We will begin to paint the areas where we will be working, so you may 
begin to see paint markings on the sidewalk, portions of the roadway, and even 
on portions of yard spaces.
  *   Essentially, we will be replacing the portions of water service lines 
feeding homes in the block on the city (public space) side. This could include 
replacing portions of lead service lines with copper service lines in public 
space (in cases where the public portion of the service line is lead), and/or 
upgrading the diameter of the service line in public space from ¾ inch up to 1 
inch.
  *   Where property owners may have lead for the portion of their service line 
inside their private property, DC Water will replace this portion of lead line 
with copper if the property owner has signed a Lead Service Replacement 
Agreement with DC Water and a service order for this private side lead line 
replacement has been issued.
  *   We will provide our standard 48-hour advance notification door hanger 
before starting the work.
  *   As property lines vary widely across the District, we understand that for 
many of the properties, portions of the front yard spaces are located in public 
space (property owned by the District). Despite this fact, we understand 
customers’ sensitivity when it comes to disturbances inside yards, so we will 
do our very best to work around plantings and pavers in the public space 
portion of yards; we do strongly suggest that property owners temporarily 
remove these items prior to the work, however, because DC Water is not 
responsible for replacement of these items, if damaged.
  *   Similarly, for portions of yard spaces located inside customers’ private 
property, DC Water is not responsible for replacement of any plantings or 
pavers that are damaged during private side service line replacements. For this 
reason, we ask that customers temporarily remove these items inside their 
private property as well.
  *   We may, on a case-by-case basis, need to perform a test pit in some of 
the yards. This would include a small excavation (dig) in some of the yards in 
order to access the pipe and/or move the water meter from the private property 
over into the public space for future access, if needed. We just want to make 
sure you have this information.



Please note that in observation of the “Presidents’ Day” Holiday, we will not 
be performing any construction activities on Monday, February 15.

Please also keep in mind that these construction activities are highly 
dependent upon favorable weather conditions.


Thanks much, please stay tuned for more updates, and make it a wonderful 
week…..ON PURPOSE!!


From: Emanuel D. Briggs
Sent: Tuesday, February 2, 2021 10:35 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image014.jpg@01D7E0D6.8E215010]


PROJECT UPDATE
Tuesday, February 2, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>

Greetings DC Water Community Stakeholders:
Please see our list of ongoing and upcoming construction activities-
Active Work Location: Jay Street NE

Weeks of January 25, February 1 and February 8


  *   We have successfully completed the new water main installations on Jay 
Street, between 46th Street and 47th Street.



  *   We have begun installation of 250 linear feet of new 8-inch water mains 
on Jay Street, between 47th Street and 47th Place. We were originally scheduled 
to complete this portion of work by Wednesday, February 3, but this week’s 
inclement weather has caused a slight delay. Currently, we are tentatively 
slated to complete this portion of work by Friday, February 5.


  *   We have begun testing and disinfection of the newly installed water mains 
on Jay Street, and these procedures are ongoing.



  *   We are still scheduled to begin installation of 250 linear feet of new 
8-inch water mains on Jay Street, between 47th Place and 48th Street on 
Thursday, February 4, and complete this portion of work by Friday, February 12.

  *   For this location, we are tentatively scheduled to perform water service 
reconnections from Wednesday, February 10 through Friday, February 26. During 
this phase of work, we will be connecting the water service lines to homes in 
these blocks to the newly installed water mains. In the next update, we will 
provide more specific details on what residents can expect to see during water 
service reconnections.

Weeks of February 15 and February 22


  *   We are planning to begin installation of 300 linear feet of new 8-inch 
water mains on Jay Street, between 48th Street and 48th Place on Tuesday, 
February 16. We are scheduled to complete this portion of work on Wednesday, 
February 24.


As noted above, this week’s activities are slightly delayed in light of our 
inclement weather event.


Thanks much, please stay tuned for more updates, and enjoy your snowy 
Tuesday…..BURR!!!!!


From: Emanuel D. Briggs
Sent: Monday, January 25, 2021 8:58 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood


[cid:image015.jpg@01D7E0D6.8E215010]


PROJECT UPDATE
Monday, January 25, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>

Greetings DC Water Community Stakeholders:
Please see our revised list of upcoming construction activities for the next 
three weeks-
Active Work Location: Jay Street NE

Week of January 25


  *   We have nearly completed the new water main installation on Jay Street, 
between 46th Street and 47th Street. We are now scheduled to complete this 
portion of work by tomorrow- Tuesday, January 26.



  *   We are now scheduled to begin installation of 250 linear feet of new 
8-inch water mains on Jay Street, between 47th Street and 47th Place on this 
coming Wednesday, January 27. We should complete this portion of work by the 
following Wednesday, February 3.


Weeks of February 1 and February 8


  *   We are now scheduled to begin testing and disinfection of the newly 
installed water mains on Jay Street on Thursday, February 4. We are scheduled 
to complete these activities on the following Monday, February 8.



  *   Concurrently with testing and disinfection of newly installed water 
mains, we will also begin installation of new 8-inch water mains on Jay Street, 
between 47th Place and 48th Street on Thursday, February 4. We are scheduled to 
complete this portion of work on Friday, February 12.


Please keep in mind that the completion dates for these activities are all 
highly dependent upon favorable weather conditions.


Thanks much, please stay tuned for more updates, and make it a wonderful 
week…ON PURPOSE!


From: Emanuel D. Briggs
Sent: Monday, January 18, 2021 11:16 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image016.jpg@01D7E0D6.8E215010]


PROJECT UPDATE
Monday, January 18, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>

Greetings DC Water Community Stakeholders:
Please see our revised list of upcoming construction activities for the next 
three weeks-
Active Work Location: Jay Street NE

Week of January 18


  *   Per last week’s update, we have successfully completed installation of 
300 linear feet of new 8-inch water mains on Jay Street, between 45th Place and 
46th Street.



  *   We have completed about 60 percent of the new water main installation on 
Jay Street, between 46th Street and 47th Street. We are now scheduled to 
complete this portion of work on this coming Friday, January 22.

Week of January 25



  *   We are now scheduled to begin installation of 250 linear feet of new 
8-inch water mains on Jay Street, between 47th Street and 47th Place on next 
Monday, January 25. We should complete this portion of work by the following 
Monday, February 1.

Week of February 1


  *   We are now scheduled to begin testing and disinfection of the newly 
installed water mains at all above listed work locations on Tuesday, February 
2. We are scheduled to complete these activities on the following Monday, 
February 8.



  *   Concurrently with testing and disinfection of newly installed water 
mains, we will also begin installation of new 8-inch water mains on Jay Street, 
between 47th Place and 48th Street on Tuesday, February 2. We are scheduled to 
complete this portion of work on the following Wednesday, February 10.


In observance of the Rev. Dr. Martin Luther King, Jr. Day Holiday, there will 
be no construction activities taking place on Monday, January 18.

Also, in observance of the 59th Presidential Inauguration Event, there will be 
no construction activities taking place on Wednesday, January 20.


Please keep in mind that the completion dates for these activities are all 
highly dependent upon favorable weather conditions.


Thanks much, please stay tuned for more updates, and make it a wonderful 
week…ON PURPOSE!


From: Emanuel D. Briggs
Sent: Tuesday, January 12, 2021 7:48 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood


[cid:image017.jpg@01D7E0D6.8E215010]


PROJECT UPDATE
Tuesday, January 12, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>

Greetings DC Water Community Stakeholders:
In keeping with our last update sent to you regarding our Small Diameter Water 
Main Replacement Project in your area, our Contractor is still working on Jay 
Street NE. Please see our list of current and upcoming construction activities 
for this location-
Active Work Location: Jay Street NE

Week of January 11


  *   We have nearly completed installation of 300 linear feet of new 8-inch 
water mains on Jay Street, between 45th Place and 46th Street. We are scheduled 
to complete this portion of work this week.



  *   Today, we are scheduled to begin installation of 250 linear feet of new 
8-inch water mains on Jay Street, between 46th Street and 47th Street. We are 
scheduled to complete this portion of work on Wednesday, January 20.


Week of January 18



  *   On Thursday, January 21, we are scheduled to begin installation of 250 
linear feet of new 8-inch water mains on Jay Street, between 47th Street and 
47th Place. We are scheduled to complete this portion of work on Thursday, 
January 28.

Week of January 25


  *   On Friday, January 29, we will begin testing and disinfection of the 
newly installed water mains at these locations. We are scheduled to complete 
these activities on Thursday, February 4.

In observance of the Rev. Dr. Martin Luther King, Jr. Day Holiday, there will 
be no construction activities taking place on Monday, January 18.

Also, in observance of the 59th Presidential Inauguration Event, there will be 
no construction activities taking place on Wednesday, January 20.


Please keep in mind that the completion dates for these activities are all 
highly dependent upon favorable weather conditions.


Thanks much, please stay tuned for more updates, and have a great and 
productive week!!!!!

From: Emanuel D. Briggs
Sent: Thursday, December 10, 2020 10:57 PM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image018.jpg@01D7E0D6.8E215010]
PROJECT UPDATE
Thursday, December 10, 2020
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>

Greetings DC Water Community Stakeholders:
As you may recall from the notification that we’d emailed to you on 10/16 
(below), our upcoming Small Diameter Water Main Replacement Project in the 
Deanwood Neighborhood was set to start in early November. I have re-attached 
our project information sheet to this update to re-familiarize you with the 
project. The primary purpose for this new update is to inform you that we did 
officially start our construction activities on some of the project area 
streets last month.

To date, our Contractor has surveyed and mobilized on the following streets: 
Hayes Street NE and Jay Street NE. Mobilization activities include installation 
of tree protection fencing, project signs, equipment staging site, and other 
related activities. Please see below a list of completed and current 
construction activities and applicable dates for the work:

Active Work Location: Jay Street NE

  *   Monday, November 9 – Monday, November 16

  *   During that week, we successfully completed installation of 300 linear 
feet of new 8-inch water mains on Jay Street NE, from 43rd Place NE to 44th 
Street NE



  *   Tuesday, November 17 – Friday, November 27

  *   During that week, we successfully completed installation of 500 linear 
feet of new 8-inch water mains on Jay Street NE, from 44th Street NE to 45th 
Place NE



  *   Friday, November 27 – Friday, December 4

  *   During that week, we successfully completed installation of 300 linear 
feet of new 8-inch water mains on Jay Street NE, from 45th Place NE to 46th 
Street NE



  *   Friday, December 4 – Thursday, December 10

  *   Currently, we are installing 250 linear feet of new 8-inch water mains on 
Jay Street NE, from 46th Street NE to 47th Street NE
Moving forward, we will be sending you regular weekly updates to keep you 
informed of our ongoing activities.

Please have a great weekend, stay tuned for future updates, and let us know if 
you have any questions.

From: Emanuel D. Briggs
Sent: Friday, October 16, 2020 8:39 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: New DC Water Project In Your Area-Small Diameter Water Main 
Replacement Project in the Deanwood Neighborhood


[cid:image019.jpg@01D7E0D6.8E215010]
NEW DC WATER PROJECT IN YOUR AREA
Friday, October 16, 2020
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>

Greetings DC Water Community Stakeholders:
This message is intended to inform you of a new DC Water construction project 
that will soon begin in your area. As part of its Capital Improvement Program, 
DC Water is replacing existing 12-inch and smaller cast iron water mains in 
various locations throughout the city.  Overall benefits of these projects 
include improved water quality and system reliability. Construction activities 
for this project will take place in the Deanwood neighborhood. The scope of 
work will include installation of approximately 9,700 linear feet of 4-inch up 
to 12-inch water mains; replacement of service lines (lead and/or other), as 
needed; replacement of fire hydrants and valves; and restoration of all 
surfaces disturbed by the project construction upon completion of the work.



The project is scheduled to start early next month, and be completed by August 
2021. The normal work hours will be from 7:00am to 5:00pm, Monday through 
Friday. However, as construction moves forward there may be portions of work 
that need to be completed at night and/or on weekends due to inclement weather 
or other unforeseen circumstances-every attempt will be made to keep these 
occurrences to a minimum. This and other important information may be found on 
the attached project information sheet.



As part of our regular construction outreach program, we will provide the 
following:

  *   This e-mail message and attached project information sheet are being 
shared with some local area residents, businesses and community organizations 
that will be directly impacted by the project construction; all ANC 7C and 7D 
Commissioners; Ward 7 representatives in the Mayor’s Office of Community 
Relations and Services; and Ward 7 Councilmember Vincent Gray and members of 
his staff.
  *   This project information will be posted to our website at 
www.dcwater.com<http://www.dcwater.com> and updated regularly.
  *   Our Contractor will be going out beginning next week to hand deliver 
printed copies of the attached project information sheet to all customers that 
will be directly impacted by the project construction.
  *   As our project gets underway, we will be providing you regular weekly 
email updates to keep you informed about our work activities.
  *   We are available to provide you with a presentation to discuss the 
project’s short-term construction impacts and long-term benefits, as well as 
address any concerns you may have. If interested in a presentation, please 
contact me and we will be happy to accommodate you.

Thanks much for allowing us to share this important information with you, and 
please let us know if you have any questions.

IMPORTANT NOTICE: 
The security of electronic mail sent through the Internet is not guaranteed. DC 
WATER therefore recommends that you do not send confidential information to us 
via electronic mail, including social security numbers, account numbers, and 
personal identification numbers unless instructed 
to do so through a secured site. Delivery, and timely delivery, of electronic 
mail is also not guaranteed. DC WATER also recommends that you do not send 
time-sensitive or action-oriented messages to us via electronic mail unless 
instructed to do so.

JPEG image

JPEG image

JPEG image

JPEG image

JPEG image

JPEG image

JPEG image

JPEG image

JPEG image

JPEG image

JPEG image

JPEG image

JPEG image

JPEG image

JPEG image

JPEG image

JPEG image

JPEG image

JPEG image