Good Morning Mr. Briggs,
Thank you for this information. I will forward it to my constituents and
fellow commissioners. Please add
deanwoodcitizens@xxxxxxxxxxxxx<mailto:deanwoodcitizens@xxxxxxxxxxxxx> to your
distribution list.
Regards,
Antawan Holmes
Advisory Neighborhood Commission 7C Chair
ANC Commissioner SMD-7C07
site: http://anc7c.org
twitter: @antawanholmes
From: Emanuel D. Briggs <Emanuel.Briggs@xxxxxxxxxxx>
Sent: Tuesday, February 09, 2021 7:08 AM
To: Emanuel D. Briggs <emanuel.briggs@xxxxxxxxxxx>
Cc: Emanuel D. Briggs <emanuel.briggs@xxxxxxxxxxx>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement
Project in the Deanwood Neighborhood
CAUTION: This email originated from outside of the DC Government. Do not click
on links or open attachments unless you recognize the sender and know that the
content is safe. If you believe that this email is suspicious, please forward
to phishing@xxxxxx<mailto:phishing@xxxxxx> for additional analysis by OCTO
Security Operations Center (SOC).
[cid:image001.jpg@01D24A59.3C60D750]
PROJECT UPDATE
Tuesday, February 9, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>
Greetings DC Water Community Stakeholders:
Please see our revised list of ongoing and upcoming construction activities-
Active Work Location: Jay Street NE
Weeks of February 8 and February 15
* We have successfully completed the installation of 250 linear feet of new
8-inch water mains on Jay Street, between 47th Street and 47th Place.
* We have begun testing and disinfection of the newly installed water mains
on Jay Street, and these procedures are still ongoing.
* We have begun the installation of 250 linear feet of new 8-inch water
mains on Jay Street, between 47th Place and 48th Street, and we are now
scheduled to complete this portion of work by Tuesday, February 16.
* For this location, we are tentatively scheduled to install new water
services from Wednesday, February 10 through Friday, February 26. During this
phase of work, we will be connecting the water service lines to homes in these
blocks to the newly installed water mains. Please see below specific details on
what residents can expect to see during installation of new water services.
Week of February 22
* We are now planning to begin the installation of 300 linear feet of new
8-inch water mains on Jay Street, between 48th Street and 48th Place on
Wednesday, February 17; we are now scheduled to complete this portion of work
on Thursday, February 25.
Typically, during installation of new water services, you will see the
following:
* We will begin to paint the areas where we will be working, so you may
begin to see paint markings on the sidewalk, portions of the roadway, and even
on portions of yard spaces.
* Essentially, we will be replacing the portions of water service lines
feeding homes in the block on the city (public space) side. This could include
replacing portions of lead service lines with copper service lines in public
space (in cases where the public portion of the service line is lead), and/or
upgrading the diameter of the service line in public space from ¾ inch up to 1
inch.
* Where property owners may have lead for the portion of their service line
inside their private property, DC Water will replace this portion of lead line
with copper if the property owner has signed a Lead Service Replacement
Agreement with DC Water and a service order for this private side lead line
replacement has been issued.
* We will provide our standard 48-hour advance notification door hanger
before starting the work.
* As property lines vary widely across the District, we understand that for
many of the properties, portions of the front yard spaces are located in public
space (property owned by the District). Despite this fact, we understand
customers’ sensitivity when it comes to disturbances inside yards, so we will
do our very best to work around plantings and pavers in the public space
portion of yards; we do strongly suggest that property owners temporarily
remove these items prior to the work, however, because DC Water is not
responsible for replacement of these items, if damaged.
* Similarly, for portions of yard spaces located inside customers’ private
property, DC Water is not responsible for replacement of any plantings or
pavers that are damaged during private side service line replacements. For this
reason, we ask that customers temporarily remove these items inside their
private property as well.
* We may, on a case-by-case basis, need to perform a test pit in some of
the yards. This would include a small excavation (dig) in some of the yards in
order to access the pipe and/or move the water meter from the private property
over into the public space for future access, if needed. We just want to make
sure you have this information.
Please note that in observation of the “Presidents’ Day” Holiday, we will not
be performing any construction activities on Monday, February 15.
Please also keep in mind that these construction activities are highly
dependent upon favorable weather conditions.
Thanks much, please stay tuned for more updates, and make it a wonderful
week…..ON PURPOSE!!
From: Emanuel D. Briggs
Sent: Tuesday, February 2, 2021 10:35 AM
To: Emanuel D. Briggs
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement
Project in the Deanwood Neighborhood
[cid:image001.jpg@01D24A59.3C60D750]
PROJECT UPDATE
Tuesday, February 2, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>
Greetings DC Water Community Stakeholders:
Please see our list of ongoing and upcoming construction activities-
Active Work Location: Jay Street NE
Weeks of January 25, February 1 and February 8
* We have successfully completed the new water main installations on Jay
Street, between 46th Street and 47th Street.
* We have begun installation of 250 linear feet of new 8-inch water mains
on Jay Street, between 47th Street and 47th Place. We were originally scheduled
to complete this portion of work by Wednesday, February 3, but this week’s
inclement weather has caused a slight delay. Currently, we are tentatively
slated to complete this portion of work by Friday, February 5.
* We have begun testing and disinfection of the newly installed water mains
on Jay Street, and these procedures are ongoing.
* We are still scheduled to begin installation of 250 linear feet of new
8-inch water mains on Jay Street, between 47th Place and 48th Street on
Thursday, February 4, and complete this portion of work by Friday, February 12.
* For this location, we are tentatively scheduled to perform water service
reconnections from Wednesday, February 10 through Friday, February 26. During
this phase of work, we will be connecting the water service lines to homes in
these blocks to the newly installed water mains. In the next update, we will
provide more specific details on what residents can expect to see during water
service reconnections.
Weeks of February 15 and February 22
* We are planning to begin installation of 300 linear feet of new 8-inch
water mains on Jay Street, between 48th Street and 48th Place on Tuesday,
February 16. We are scheduled to complete this portion of work on Wednesday,
February 24.
As noted above, this week’s activities are slightly delayed in light of our
inclement weather event.
Thanks much, please stay tuned for more updates, and enjoy your snowy
Tuesday…..BURR!!!!!
From: Emanuel D. Briggs
Sent: Monday, January 25, 2021 8:58 AM
To: Emanuel D. Briggs
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement
Project in the Deanwood Neighborhood
[cid:image001.jpg@01D24A59.3C60D750]
PROJECT UPDATE
Monday, January 25, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>
Greetings DC Water Community Stakeholders:
Please see our revised list of upcoming construction activities for the next
three weeks-
Active Work Location: Jay Street NE
Week of January 25
* We have nearly completed the new water main installation on Jay Street,
between 46th Street and 47th Street. We are now scheduled to complete this
portion of work by tomorrow- Tuesday, January 26.
* We are now scheduled to begin installation of 250 linear feet of new
8-inch water mains on Jay Street, between 47th Street and 47th Place on this
coming Wednesday, January 27. We should complete this portion of work by the
following Wednesday, February 3.
Weeks of February 1 and February 8
* We are now scheduled to begin testing and disinfection of the newly
installed water mains on Jay Street on Thursday, February 4. We are scheduled
to complete these activities on the following Monday, February 8.
* Concurrently with testing and disinfection of newly installed water
mains, we will also begin installation of new 8-inch water mains on Jay Street,
between 47th Place and 48th Street on Thursday, February 4. We are scheduled to
complete this portion of work on Friday, February 12.
Please keep in mind that the completion dates for these activities are all
highly dependent upon favorable weather conditions.
Thanks much, please stay tuned for more updates, and make it a wonderful
week…ON PURPOSE!
From: Emanuel D. Briggs
Sent: Monday, January 18, 2021 11:16 AM
To: Emanuel D. Briggs
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement
Project in the Deanwood Neighborhood
[cid:image001.jpg@01D24A59.3C60D750]
PROJECT UPDATE
Monday, January 18, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>
Greetings DC Water Community Stakeholders:
Please see our revised list of upcoming construction activities for the next
three weeks-
Active Work Location: Jay Street NE
Week of January 18
* Per last week’s update, we have successfully completed installation of
300 linear feet of new 8-inch water mains on Jay Street, between 45th Place and
46th Street.
* We have completed about 60 percent of the new water main installation on
Jay Street, between 46th Street and 47th Street. We are now scheduled to
complete this portion of work on this coming Friday, January 22.
Week of January 25
* We are now scheduled to begin installation of 250 linear feet of new
8-inch water mains on Jay Street, between 47th Street and 47th Place on next
Monday, January 25. We should complete this portion of work by the following
Monday, February 1.
Week of February 1
* We are now scheduled to begin testing and disinfection of the newly
installed water mains at all above listed work locations on Tuesday, February
2. We are scheduled to complete these activities on the following Monday,
February 8.
* Concurrently with testing and disinfection of newly installed water
mains, we will also begin installation of new 8-inch water mains on Jay Street,
between 47th Place and 48th Street on Tuesday, February 2. We are scheduled to
complete this portion of work on the following Wednesday, February 10.
In observance of the Rev. Dr. Martin Luther King, Jr. Day Holiday, there will
be no construction activities taking place on Monday, January 18.
Also, in observance of the 59th Presidential Inauguration Event, there will be
no construction activities taking place on Wednesday, January 20.
Please keep in mind that the completion dates for these activities are all
highly dependent upon favorable weather conditions.
Thanks much, please stay tuned for more updates, and make it a wonderful
week…ON PURPOSE!
From: Emanuel D. Briggs
Sent: Tuesday, January 12, 2021 7:48 AM
To: Emanuel D. Briggs
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement
Project in the Deanwood Neighborhood
[cid:image001.jpg@01D24A59.3C60D750]
PROJECT UPDATE
Tuesday, January 12, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>
Greetings DC Water Community Stakeholders:
In keeping with our last update sent to you regarding our Small Diameter Water
Main Replacement Project in your area, our Contractor is still working on Jay
Street NE. Please see our list of current and upcoming construction activities
for this location-
Active Work Location: Jay Street NE
Week of January 11
* We have nearly completed installation of 300 linear feet of new 8-inch
water mains on Jay Street, between 45th Place and 46th Street. We are scheduled
to complete this portion of work this week.
* Today, we are scheduled to begin installation of 250 linear feet of new
8-inch water mains on Jay Street, between 46th Street and 47th Street. We are
scheduled to complete this portion of work on Wednesday, January 20.
Week of January 18
* On Thursday, January 21, we are scheduled to begin installation of 250
linear feet of new 8-inch water mains on Jay Street, between 47th Street and
47th Place. We are scheduled to complete this portion of work on Thursday,
January 28.
Week of January 25
* On Friday, January 29, we will begin testing and disinfection of the
newly installed water mains at these locations. We are scheduled to complete
these activities on Thursday, February 4.
In observance of the Rev. Dr. Martin Luther King, Jr. Day Holiday, there will
be no construction activities taking place on Monday, January 18.
Also, in observance of the 59th Presidential Inauguration Event, there will be
no construction activities taking place on Wednesday, January 20.
Please keep in mind that the completion dates for these activities are all
highly dependent upon favorable weather conditions.
Thanks much, please stay tuned for more updates, and have a great and
productive week!!!!!
From: Emanuel D. Briggs
Sent: Thursday, December 10, 2020 10:57 PM
To: Emanuel D. Briggs
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement
Project in the Deanwood Neighborhood
[cid:image001.jpg@01D24A59.3C60D750]
PROJECT UPDATE
Thursday, December 10, 2020
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>
Greetings DC Water Community Stakeholders:
As you may recall from the notification that we’d emailed to you on 10/16
(below), our upcoming Small Diameter Water Main Replacement Project in the
Deanwood Neighborhood was set to start in early November. I have re-attached
our project information sheet to this update to re-familiarize you with the
project. The primary purpose for this new update is to inform you that we did
officially start our construction activities on some of the project area
streets last month.
To date, our Contractor has surveyed and mobilized on the following streets:
Hayes Street NE and Jay Street NE. Mobilization activities include installation
of tree protection fencing, project signs, equipment staging site, and other
related activities. Please see below a list of completed and current
construction activities and applicable dates for the work:
Active Work Location: Jay Street NE
* Monday, November 9 – Monday, November 16
* During that week, we successfully completed installation of 300 linear
feet of new 8-inch water mains on Jay Street NE, from 43rd Place NE to 44th
Street NE
* Tuesday, November 17 – Friday, November 27
* During that week, we successfully completed installation of 500 linear
feet of new 8-inch water mains on Jay Street NE, from 44th Street NE to 45th
Place NE
* Friday, November 27 – Friday, December 4
* During that week, we successfully completed installation of 300 linear
feet of new 8-inch water mains on Jay Street NE, from 45th Place NE to 46th
Street NE
* Friday, December 4 – Thursday, December 10
* Currently, we are installing 250 linear feet of new 8-inch water mains on
Jay Street NE, from 46th Street NE to 47th Street NE
Moving forward, we will be sending you regular weekly updates to keep you
informed of our ongoing activities.
Please have a great weekend, stay tuned for future updates, and let us know if
you have any questions.
From: Emanuel D. Briggs
Sent: Friday, October 16, 2020 8:39 AM
To: Emanuel D. Briggs
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: New DC Water Project In Your Area-Small Diameter Water Main
Replacement Project in the Deanwood Neighborhood
[cid:image001.jpg@01D24A59.3C60D750]
NEW DC WATER PROJECT IN YOUR AREA
Friday, October 16, 2020
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>
Greetings DC Water Community Stakeholders:
This message is intended to inform you of a new DC Water construction project
that will soon begin in your area. As part of its Capital Improvement Program,
DC Water is replacing existing 12-inch and smaller cast iron water mains in
various locations throughout the city. Overall benefits of these projects
include improved water quality and system reliability. Construction activities
for this project will take place in the Deanwood neighborhood. The scope of
work will include installation of approximately 9,700 linear feet of 4-inch up
to 12-inch water mains; replacement of service lines (lead and/or other), as
needed; replacement of fire hydrants and valves; and restoration of all
surfaces disturbed by the project construction upon completion of the work.
The project is scheduled to start early next month, and be completed by August
2021. The normal work hours will be from 7:00am to 5:00pm, Monday through
Friday. However, as construction moves forward there may be portions of work
that need to be completed at night and/or on weekends due to inclement weather
or other unforeseen circumstances-every attempt will be made to keep these
occurrences to a minimum. This and other important information may be found on
the attached project information sheet.
As part of our regular construction outreach program, we will provide the
following:
* This e-mail message and attached project information sheet are being
shared with some local area residents, businesses and community organizations
that will be directly impacted by the project construction; all ANC 7C and 7D
Commissioners; Ward 7 representatives in the Mayor’s Office of Community
Relations and Services; and Ward 7 Councilmember Vincent Gray and members of
his staff.
* This project information will be posted to our website at
www.dcwater.com<http://www.dcwater.com> and updated regularly.
* Our Contractor will be going out beginning next week to hand deliver
printed copies of the attached project information sheet to all customers that
will be directly impacted by the project construction.
* As our project gets underway, we will be providing you regular weekly
email updates to keep you informed about our work activities.
* We are available to provide you with a presentation to discuss the
project’s short-term construction impacts and long-term benefits, as well as
address any concerns you may have. If interested in a presentation, please
contact me and we will be happy to accommodate you.
Thanks much for allowing us to share this important information with you, and
please let us know if you have any questions.
IMPORTANT NOTICE:
The security of electronic mail sent through the Internet is not guaranteed. DC
WATER therefore recommends that you do not send confidential information to us
via electronic mail, including social security numbers, account numbers, and
personal identification numbers unless instructed to do so through a secured
site. Delivery, and timely delivery, of electronic mail is also not guaranteed.
DC WATER also recommends that you do not send time-sensitive or action-oriented
messages to us via electronic mail unless instructed to do so.