[deanwoodcitizens] FW: Project Update For Your Area-Small Diameter Water Main Replacement Project in the Deanwood Neighborhood

  • From: "Holmes, Antawan (ANC 7C07)" <7C07@xxxxxxxxxx>
  • To: "Emanuel D. Briggs" <emanuel.briggs@xxxxxxxxxxx>
  • Date: Tue, 9 Feb 2021 16:53:54 +0000

Good Morning Mr. Briggs,

Thank you for this information.  I will forward it to my constituents and 
fellow commissioners.  Please add 
deanwoodcitizens@xxxxxxxxxxxxx<mailto:deanwoodcitizens@xxxxxxxxxxxxx> to your 
distribution list.

Regards,
Antawan Holmes
Advisory Neighborhood Commission 7C Chair
ANC Commissioner SMD-7C07
site: http://anc7c.org
twitter: @antawanholmes

From: Emanuel D. Briggs <Emanuel.Briggs@xxxxxxxxxxx>
Sent: Tuesday, February 09, 2021 7:08 AM
To: Emanuel D. Briggs <emanuel.briggs@xxxxxxxxxxx>
Cc: Emanuel D. Briggs <emanuel.briggs@xxxxxxxxxxx>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

CAUTION: This email originated from outside of the DC Government. Do not click 
on links or open attachments unless you recognize the sender and know that the 
content is safe. If you believe that this email is suspicious, please forward 
to phishing@xxxxxx<mailto:phishing@xxxxxx> for additional analysis by OCTO 
Security Operations Center (SOC).

[cid:image001.jpg@01D24A59.3C60D750]


PROJECT UPDATE
Tuesday, February 9, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>

Greetings DC Water Community Stakeholders:
Please see our revised list of ongoing and upcoming construction activities-

Active Work Location: Jay Street NE


Weeks of February 8 and February 15


  *   We have successfully completed the installation of 250 linear feet of new 
8-inch water mains on Jay Street, between 47th Street and 47th Place.


  *   We have begun testing and disinfection of the newly installed water mains 
on Jay Street, and these procedures are still ongoing.



  *   We have begun the installation of 250 linear feet of new 8-inch water 
mains on Jay Street, between 47th Place and 48th Street, and we are now 
scheduled to complete this portion of work by Tuesday, February 16.

  *   For this location, we are tentatively scheduled to install new water 
services from Wednesday, February 10 through Friday, February 26. During this 
phase of work, we will be connecting the water service lines to homes in these 
blocks to the newly installed water mains. Please see below specific details on 
what residents can expect to see during installation of new water services.

Week of February 22


  *   We are now planning to begin the installation of 300 linear feet of new 
8-inch water mains on Jay Street, between 48th Street and 48th Place on 
Wednesday, February 17; we are now scheduled to complete this portion of work 
on Thursday, February 25.


Typically, during installation of new water services, you will see the 
following:

  *   We will begin to paint the areas where we will be working, so you may 
begin to see paint markings on the sidewalk, portions of the roadway, and even 
on portions of yard spaces.
  *   Essentially, we will be replacing the portions of water service lines 
feeding homes in the block on the city (public space) side. This could include 
replacing portions of lead service lines with copper service lines in public 
space (in cases where the public portion of the service line is lead), and/or 
upgrading the diameter of the service line in public space from ¾ inch up to 1 
inch.
  *   Where property owners may have lead for the portion of their service line 
inside their private property, DC Water will replace this portion of lead line 
with copper if the property owner has signed a Lead Service Replacement 
Agreement with DC Water and a service order for this private side lead line 
replacement has been issued.
  *   We will provide our standard 48-hour advance notification door hanger 
before starting the work.
  *   As property lines vary widely across the District, we understand that for 
many of the properties, portions of the front yard spaces are located in public 
space (property owned by the District). Despite this fact, we understand 
customers’ sensitivity when it comes to disturbances inside yards, so we will 
do our very best to work around plantings and pavers in the public space 
portion of yards; we do strongly suggest that property owners temporarily 
remove these items prior to the work, however, because DC Water is not 
responsible for replacement of these items, if damaged.
  *   Similarly, for portions of yard spaces located inside customers’ private 
property, DC Water is not responsible for replacement of any plantings or 
pavers that are damaged during private side service line replacements. For this 
reason, we ask that customers temporarily remove these items inside their 
private property as well.
  *   We may, on a case-by-case basis, need to perform a test pit in some of 
the yards. This would include a small excavation (dig) in some of the yards in 
order to access the pipe and/or move the water meter from the private property 
over into the public space for future access, if needed. We just want to make 
sure you have this information.



Please note that in observation of the “Presidents’ Day” Holiday, we will not 
be performing any construction activities on Monday, February 15.

Please also keep in mind that these construction activities are highly 
dependent upon favorable weather conditions.


Thanks much, please stay tuned for more updates, and make it a wonderful 
week…..ON PURPOSE!!


From: Emanuel D. Briggs
Sent: Tuesday, February 2, 2021 10:35 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image001.jpg@01D24A59.3C60D750]


PROJECT UPDATE
Tuesday, February 2, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>

Greetings DC Water Community Stakeholders:
Please see our list of ongoing and upcoming construction activities-

Active Work Location: Jay Street NE


Weeks of January 25, February 1 and February 8


  *   We have successfully completed the new water main installations on Jay 
Street, between 46th Street and 47th Street.



  *   We have begun installation of 250 linear feet of new 8-inch water mains 
on Jay Street, between 47th Street and 47th Place. We were originally scheduled 
to complete this portion of work by Wednesday, February 3, but this week’s 
inclement weather has caused a slight delay. Currently, we are tentatively 
slated to complete this portion of work by Friday, February 5.


  *   We have begun testing and disinfection of the newly installed water mains 
on Jay Street, and these procedures are ongoing.



  *   We are still scheduled to begin installation of 250 linear feet of new 
8-inch water mains on Jay Street, between 47th Place and 48th Street on 
Thursday, February 4, and complete this portion of work by Friday, February 12.

  *   For this location, we are tentatively scheduled to perform water service 
reconnections from Wednesday, February 10 through Friday, February 26. During 
this phase of work, we will be connecting the water service lines to homes in 
these blocks to the newly installed water mains. In the next update, we will 
provide more specific details on what residents can expect to see during water 
service reconnections.

Weeks of February 15 and February 22


  *   We are planning to begin installation of 300 linear feet of new 8-inch 
water mains on Jay Street, between 48th Street and 48th Place on Tuesday, 
February 16. We are scheduled to complete this portion of work on Wednesday, 
February 24.


As noted above, this week’s activities are slightly delayed in light of our 
inclement weather event.


Thanks much, please stay tuned for more updates, and enjoy your snowy 
Tuesday…..BURR!!!!!


From: Emanuel D. Briggs
Sent: Monday, January 25, 2021 8:58 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood


[cid:image001.jpg@01D24A59.3C60D750]


PROJECT UPDATE
Monday, January 25, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>

Greetings DC Water Community Stakeholders:
Please see our revised list of upcoming construction activities for the next 
three weeks-

Active Work Location: Jay Street NE


Week of January 25


  *   We have nearly completed the new water main installation on Jay Street, 
between 46th Street and 47th Street. We are now scheduled to complete this 
portion of work by tomorrow- Tuesday, January 26.



  *   We are now scheduled to begin installation of 250 linear feet of new 
8-inch water mains on Jay Street, between 47th Street and 47th Place on this 
coming Wednesday, January 27. We should complete this portion of work by the 
following Wednesday, February 3.


Weeks of February 1 and February 8


  *   We are now scheduled to begin testing and disinfection of the newly 
installed water mains on Jay Street on Thursday, February 4. We are scheduled 
to complete these activities on the following Monday, February 8.



  *   Concurrently with testing and disinfection of newly installed water 
mains, we will also begin installation of new 8-inch water mains on Jay Street, 
between 47th Place and 48th Street on Thursday, February 4. We are scheduled to 
complete this portion of work on Friday, February 12.


Please keep in mind that the completion dates for these activities are all 
highly dependent upon favorable weather conditions.


Thanks much, please stay tuned for more updates, and make it a wonderful 
week…ON PURPOSE!


From: Emanuel D. Briggs
Sent: Monday, January 18, 2021 11:16 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image001.jpg@01D24A59.3C60D750]


PROJECT UPDATE
Monday, January 18, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>

Greetings DC Water Community Stakeholders:
Please see our revised list of upcoming construction activities for the next 
three weeks-

Active Work Location: Jay Street NE


Week of January 18


  *   Per last week’s update, we have successfully completed installation of 
300 linear feet of new 8-inch water mains on Jay Street, between 45th Place and 
46th Street.



  *   We have completed about 60 percent of the new water main installation on 
Jay Street, between 46th Street and 47th Street. We are now scheduled to 
complete this portion of work on this coming Friday, January 22.

Week of January 25



  *   We are now scheduled to begin installation of 250 linear feet of new 
8-inch water mains on Jay Street, between 47th Street and 47th Place on next 
Monday, January 25. We should complete this portion of work by the following 
Monday, February 1.

Week of February 1


  *   We are now scheduled to begin testing and disinfection of the newly 
installed water mains at all above listed work locations on Tuesday, February 
2. We are scheduled to complete these activities on the following Monday, 
February 8.



  *   Concurrently with testing and disinfection of newly installed water 
mains, we will also begin installation of new 8-inch water mains on Jay Street, 
between 47th Place and 48th Street on Tuesday, February 2. We are scheduled to 
complete this portion of work on the following Wednesday, February 10.


In observance of the Rev. Dr. Martin Luther King, Jr. Day Holiday, there will 
be no construction activities taking place on Monday, January 18.

Also, in observance of the 59th Presidential Inauguration Event, there will be 
no construction activities taking place on Wednesday, January 20.


Please keep in mind that the completion dates for these activities are all 
highly dependent upon favorable weather conditions.


Thanks much, please stay tuned for more updates, and make it a wonderful 
week…ON PURPOSE!


From: Emanuel D. Briggs
Sent: Tuesday, January 12, 2021 7:48 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood


[cid:image001.jpg@01D24A59.3C60D750]


PROJECT UPDATE
Tuesday, January 12, 2021
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>

Greetings DC Water Community Stakeholders:
In keeping with our last update sent to you regarding our Small Diameter Water 
Main Replacement Project in your area, our Contractor is still working on Jay 
Street NE. Please see our list of current and upcoming construction activities 
for this location-

Active Work Location: Jay Street NE



Week of January 11


  *   We have nearly completed installation of 300 linear feet of new 8-inch 
water mains on Jay Street, between 45th Place and 46th Street. We are scheduled 
to complete this portion of work this week.



  *   Today, we are scheduled to begin installation of 250 linear feet of new 
8-inch water mains on Jay Street, between 46th Street and 47th Street. We are 
scheduled to complete this portion of work on Wednesday, January 20.


Week of January 18



  *   On Thursday, January 21, we are scheduled to begin installation of 250 
linear feet of new 8-inch water mains on Jay Street, between 47th Street and 
47th Place. We are scheduled to complete this portion of work on Thursday, 
January 28.

Week of January 25


  *   On Friday, January 29, we will begin testing and disinfection of the 
newly installed water mains at these locations. We are scheduled to complete 
these activities on Thursday, February 4.

In observance of the Rev. Dr. Martin Luther King, Jr. Day Holiday, there will 
be no construction activities taking place on Monday, January 18.

Also, in observance of the 59th Presidential Inauguration Event, there will be 
no construction activities taking place on Wednesday, January 20.


Please keep in mind that the completion dates for these activities are all 
highly dependent upon favorable weather conditions.


Thanks much, please stay tuned for more updates, and have a great and 
productive week!!!!!

From: Emanuel D. Briggs
Sent: Thursday, December 10, 2020 10:57 PM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: Project Update For Your Area-Small Diameter Water Main Replacement 
Project in the Deanwood Neighborhood

[cid:image001.jpg@01D24A59.3C60D750]
PROJECT UPDATE
Thursday, December 10, 2020
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>

Greetings DC Water Community Stakeholders:
As you may recall from the notification that we’d emailed to you on 10/16 
(below), our upcoming Small Diameter Water Main Replacement Project in the 
Deanwood Neighborhood was set to start in early November. I have re-attached 
our project information sheet to this update to re-familiarize you with the 
project. The primary purpose for this new update is to inform you that we did 
officially start our construction activities on some of the project area 
streets last month.

To date, our Contractor has surveyed and mobilized on the following streets: 
Hayes Street NE and Jay Street NE. Mobilization activities include installation 
of tree protection fencing, project signs, equipment staging site, and other 
related activities. Please see below a list of completed and current 
construction activities and applicable dates for the work:



Active Work Location: Jay Street NE

  *   Monday, November 9 – Monday, November 16

  *   During that week, we successfully completed installation of 300 linear 
feet of new 8-inch water mains on Jay Street NE, from 43rd Place NE to 44th 
Street NE



  *   Tuesday, November 17 – Friday, November 27

  *   During that week, we successfully completed installation of 500 linear 
feet of new 8-inch water mains on Jay Street NE, from 44th Street NE to 45th 
Place NE



  *   Friday, November 27 – Friday, December 4

  *   During that week, we successfully completed installation of 300 linear 
feet of new 8-inch water mains on Jay Street NE, from 45th Place NE to 46th 
Street NE



  *   Friday, December 4 – Thursday, December 10

  *   Currently, we are installing 250 linear feet of new 8-inch water mains on 
Jay Street NE, from 46th Street NE to 47th Street NE
Moving forward, we will be sending you regular weekly updates to keep you 
informed of our ongoing activities.

Please have a great weekend, stay tuned for future updates, and let us know if 
you have any questions.

From: Emanuel D. Briggs
Sent: Friday, October 16, 2020 8:39 AM
To: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Cc: Emanuel D. Briggs 
<Emanuel.Briggs@xxxxxxxxxxx<mailto:Emanuel.Briggs@xxxxxxxxxxx>>
Subject: RE: New DC Water Project In Your Area-Small Diameter Water Main 
Replacement Project in the Deanwood Neighborhood


[cid:image001.jpg@01D24A59.3C60D750]
NEW DC WATER PROJECT IN YOUR AREA
Friday, October 16, 2020
Manager, Community Outreach: Emanuel D. Briggs
(202)787-2003 or emanuel.briggs@xxxxxxxxxxx<mailto:emanuel.briggs@xxxxxxxxxxx>

Greetings DC Water Community Stakeholders:
This message is intended to inform you of a new DC Water construction project 
that will soon begin in your area. As part of its Capital Improvement Program, 
DC Water is replacing existing 12-inch and smaller cast iron water mains in 
various locations throughout the city.  Overall benefits of these projects 
include improved water quality and system reliability. Construction activities 
for this project will take place in the Deanwood neighborhood. The scope of 
work will include installation of approximately 9,700 linear feet of 4-inch up 
to 12-inch water mains; replacement of service lines (lead and/or other), as 
needed; replacement of fire hydrants and valves; and restoration of all 
surfaces disturbed by the project construction upon completion of the work.



The project is scheduled to start early next month, and be completed by August 
2021. The normal work hours will be from 7:00am to 5:00pm, Monday through 
Friday. However, as construction moves forward there may be portions of work 
that need to be completed at night and/or on weekends due to inclement weather 
or other unforeseen circumstances-every attempt will be made to keep these 
occurrences to a minimum. This and other important information may be found on 
the attached project information sheet.



As part of our regular construction outreach program, we will provide the 
following:

  *   This e-mail message and attached project information sheet are being 
shared with some local area residents, businesses and community organizations 
that will be directly impacted by the project construction; all ANC 7C and 7D 
Commissioners; Ward 7 representatives in the Mayor’s Office of Community 
Relations and Services; and Ward 7 Councilmember Vincent Gray and members of 
his staff.
  *   This project information will be posted to our website at 
www.dcwater.com<http://www.dcwater.com> and updated regularly.
  *   Our Contractor will be going out beginning next week to hand deliver 
printed copies of the attached project information sheet to all customers that 
will be directly impacted by the project construction.
  *   As our project gets underway, we will be providing you regular weekly 
email updates to keep you informed about our work activities.
  *   We are available to provide you with a presentation to discuss the 
project’s short-term construction impacts and long-term benefits, as well as 
address any concerns you may have. If interested in a presentation, please 
contact me and we will be happy to accommodate you.

Thanks much for allowing us to share this important information with you, and 
please let us know if you have any questions.


IMPORTANT NOTICE:
The security of electronic mail sent through the Internet is not guaranteed. DC 
WATER therefore recommends that you do not send confidential information to us 
via electronic mail, including social security numbers, account numbers, and 
personal identification numbers unless instructed to do so through a secured 
site. Delivery, and timely delivery, of electronic mail is also not guaranteed. 
DC WATER also recommends that you do not send time-sensitive or action-oriented 
messages to us via electronic mail unless instructed to do so.

JPEG image

JPEG image

JPEG image

JPEG image

JPEG image

JPEG image

JPEG image

Other related posts: