[burpg] RPG Schedule

  • From: "D. Armor Harris" <davidh@xxxxxx>
  • To: "burpg@xxxxxxxxxxxxx" <burpg@xxxxxxxxxxxxx>
  • Date: Fri, 6 Dec 2013 15:02:30 -0500

*Work Session: *10am Saturday 12/7 including E-Reg controls bench test

Note that the shops are going to shut down on Wednesday, so everything that
has to be machined has to be done by the end of the day on Wednesday.

*Coordination Meeting:* 7pm Monday, 12/9

Everyone who is involved in the cold flow, and especially the people on the
list below are required to be there at the meeting on Monday.

*Rocket and Test Stand Assembly:* Friday 12/13

*Dry Run in wind tunnel lab:* Friday 12/13 at 4pm

*Cold Flow:* Saturday 12/14 at 9am


   - *E-Regulator Housing*- Mehmet
   - *Firestarter Disconnect Housing #433*- Daniel Poe
   - *Firestarter*- Dean
   - *E-Regulator Controls*- Drew
   - *FCU*- Drew
   - *Cables*- Joe Beaupre
   - *Ground Control Software*- Abessari, Mirek, Brandon, Anish
   - *Firestarter ULD*- Carolina
   - *Nitrous Transporter*- Alessandro
   - *Nitrous GSE Plumbing*- Felix and Ashley
   - *3x Test Stand Transporters*- Sindel
   - *2x GN2 6ksi Ground Valves*- Mehmet
   - *3x N2O 1ksi Ground Valves*- Ben Ha
   - *12x Pyro Bolts, threaded for nuts*- Halstead
   - *U-Haul logistics-* Ben Ha
   - *Soccer Mom for Saturday- *Cory



-- 
David Armor Harris
Boston University Rocket Propulsion Group
davidh@xxxxxx