Hi all,
As per IBIS spec 4.0, the power and ground clamps need to be
subtracted from the pull up and pull down waveforms.
I am using the s2ibis2 version 1.1 and this takes into account only
subtraction of one clamp (power clamp from the pull up curve and ground
clamp from the pull down curve).
Is there a latest version of the s2ibis2 software that subtracts both
clamps from the pull up and pull down curves? If not is there any
software or any method to subtract these other than doing manually to
comply with the spec.
Any help as soon as possible will be greatly appreciated.
Thank you.
regards
Jayasree
-- Binary/unsupported file stripped by Ecartis --
-- Type: text/x-vcard
-- File: njy.vcf
------------------------------------------------------------------
To unsubscribe from si-list:
si-list-request@xxxxxxxxxxxxx with 'unsubscribe' in the Subject field
or to administer your membership from a web page, go to:
http://www.freelists.org/webpage/si-list
For help:
si-list-request@xxxxxxxxxxxxx with 'help' in the Subject field
List FAQ wiki page is located at:
http://si-list.org/wiki/wiki.pl?Si-List_FAQ
List technical documents are available at:
http://www.si-list.org
List archives are viewable at:
http://www.freelists.org/archives/si-list
or at our remote archives:
http://groups.yahoo.com/group/si-list/messages
Old (prior to June 6, 2001) list archives are viewable at:
http://www.qsl.net/wb6tpu