RE: Database Outages - Best Practices

  • From: "Hollis, Les" <Les.Hollis@xxxxxx>
  • To: <stephenbooth.uk@xxxxxxxxx>, <ryan_gaffuri@xxxxxxxxxxx>
  • Date: Mon, 14 Feb 2005 15:33:10 -0600

As far as prep,

We set out a timeline and an implementation doc as to what we will be
doing ..

timeline includes  times and content of notification pages to be sent,
when we start backup prior to window, verification of backup success,
completion of BCV copy and the fact that the BCV copy database opens
successfully.

Steps we will be performing at what time (these are approximate times).

When we will complete and the page to be sent, verification by Apps
support that the application does indeed function as advertised and
final page of completion of maintenance window....DB ready for use


Implementation doc states the general purpose of maintenance who is
involved, contact names and numbers, what t5ables are affected, any new
init.ora parameters, new users to create, new DB links, etc



-----Original Message-----
From: oracle-l-bounce@xxxxxxxxxxxxx
[mailto:oracle-l-bounce@xxxxxxxxxxxxx] On Behalf Of stephen booth
Sent: Monday, February 14, 2005 3:16 PM
To: ryan_gaffuri@xxxxxxxxxxx
Cc: mfontana@xxxxxxxxx; oracle-l@xxxxxxxxxxxxx
Subject: Re: Database Outages - Best Practices

On Mon, 14 Feb 2005 20:38:11 +0000, ryan_gaffuri@xxxxxxxxxxx
<ryan_gaffuri@xxxxxxxxxxx> wrote:
> most outages are typically related to builds. your adding tables,
dropping tables, data migration, or the application is deploying a new
version.
> standard is outside of regular business hours. negotiate notice in
advance. Negotiated frequency. Negotiated downtime. Negotiated
notification process if there is a delay in bringing the system back up.
>=20
> you want it all written down in advance, with appropriate phone
numbers and you want a client signature.

Ditto on all of the above.

One useful way I've found of getting management to agree outages is to
not call them outages.  Call them 'Power Possession'.  A power
possession is a period when you or any of the other techs and
engineers associated with a system  (database, OS, hardware, network,
power, building management &c) have the option or downing the system,
the datacentre or even the network for maintenence.

Schedule them well inadvance (try for a year), as frequently as
possible, for times time the system isn't busy and for a good long
period of time.  Most times you won't need them and will be able to
tell the business "It's OK, we don't need to take the service down,
this time".  When work needs to be done try to get as much
non-interfering work into that window as possible (obviously don't try
to upgrade the OS and database software at the same time but you
should be OK working on the database whilst a network switch is being=20
upgraded or after a test firing of the backup generators (always make
sure that your backup generators are test fired on the manufacturers
reccommended schedule, this is the voice of bitter experience
speaking), for example).

Stephen
--=20
It's better to ask a silly question than to make a silly assumption.
--