Thanks for that, I'll have a look at it.

I got a reply from Oracle Support, after escalating the SR, and they
give similar steps, except they didn't mention catpatch.

I did catch that, and am awaiting an answer on how and when catpatch
should be run.  I believe catpatch should be run with the database
started up in migrate mode?  In which case I believe all nodes should be
shutdown, though I may well be wrong.

But thanks again, I'll have a look.

Regards.

On Wed, 2008-05-28 at 08:44 -0700, William Wagman wrote:
> Greetings,
> 
> Metalink note 278641.1 gives instructions for applying a patchset with a
> 10g physical standby in place and, although I haven't tried it in a RAC
> environment, only with standby, but I suspect it could be extrapolated.
> Shut down the primary (in this case the RAC node which is the primary)
> and the standby, install the patch and then with both the primary and
> standby open run catpatch, then follow the instructions for a rolling
> upgrade on other nodes? I've not tried it but it seems like it should
> work.
> 
> Bill Wagman
> Univ. of California at Davis
> IET Campus Data Center
> wjwagman@xxxxxxxxxxx
> (530) 754-6208
> -----Original Message-----
> From: oracle-l-bounce@xxxxxxxxxxxxx
> [mailto:oracle-l-bounce@xxxxxxxxxxxxx] On Behalf Of S. Anthony Sequeira
> Sent: Wednesday, May 28, 2008 5:13 AM
> To: Oracle List
> Subject: Re: Applying CPU to RAC with physical standby
> 
> On Wed, 2008-05-28 at 12:37 +0100, jason arneil wrote:
> > I think you should be OK to apply the catpatch.sql with the database  
> > up, the patch instructions are clear on that. I don't think having  
> > dataguard involved impacts on this, why should it?  
> 
> Yes, but the standby patch application note (187242.1) specifically
> mentions that all nodes must be down while the entire patch is being
> applied.  This is what I'm querying with Oracle Support, and the list.
> I too believe that having a standby should not make a difference, but
> apparently it does.
> 
> > You must however  
> > start the database in upgrade mode to perform the view recompile -
> > but  
> > you know this already!
> > 
> > At this stage I can't see how you can have a node open for business
> > -  
> > except if you want to offer your users some read only activity, then  
> > you could use your standby read only while you were doing the view  
> > recompile.
> 
> We have scheduled downtime in a short window between batch runs on a
> Sunday afternoon.  Oracle Support are dragging their heels on this, if I
> have to take the database down for an extended period of time, it has to
> go back to the business.
> 
> > This though is far removed from the marketing hype of "rolling
> > upgrade".
> 
> Agreed, this begs the question, why use RAC and pay through the nose?
> But that's probably been gone through many times, and is not really
> relevant to the thread.
> 
> Regards.
-- 
S. Anthony Sequeira
++
NEVER RESPOND TO CRITICAL PRESS.  IT IS A GAME YOU CAN ONLY LOSE, AND IT
MAKES US LOOK BAD.
                -- Bruce Perens
++

--