[interfacekit] Registrar: Milestone 3 reached
- From: "Ingo Weinhold" <bonefish@xxxxxxxxxxxxxxx>
- To: "Interface Kit" <interfacekit@xxxxxxxxxxxxx>
- Date: Tue, 19 Nov 2002 21:34:07 CET (+0100)
Hi,
this could have been said a week or so ago, but wasn't due to
communication flow problems. Anyway...
The fearless Storage Kit team, this time supported by Gabe Yoder,
strikes again. Milestone 3 of our four-phased registrar development
schedule has been reached.
Newly implemented are the application roster features application
launching and watching, recent application/document support and message
broadcasting, and the BMessageRunner and BClipboard classes.
Let alone one method, BRoster::ActiveApp(), which requires our own
working app server, the entire part of the BeOS API that depends on
interactions with the registrar is completely implemented. For the next
and last milestone the two missing registrar services, the automatic
background updating of the MIME database and the system shutdown, need
to be added. For the time being they are not crucial, and it does make
more sense to tackle them, when we can run applications under our
operating system, so we postpone the remaining tasks and, in the
meantime, get some other work done.
CU, Ingo