Re: [foxboro] MESH Upgrade question

I meant to add, what we've been doing for spares for CP40A and INT30A
is to buy a pair of B modules and pick an easy to migrate pair of A
modules (easy meaning fits in to our shut schedule).  Then just swap B
for A modules while that plant area is down and put the A modules back
in to our spares.

That's kept us from having to buy any more EOL modules.

Regards,

Kevin FitzGerrell
 
 