[foxboro] Ver 4.3 and 6.3 co-existance
- From: "Ashley Davey" <Ashley.Davey@xxxxxxxxxxxx>
- To: <foxboro@xxxxxxxxxxxxx>
- Date: Wed, 12 Jun 2002 13:24:39 +0200
Hi list
One of our sites has four AW51B's running Version 4.3. One AW is the CSA host
and also hosts eight of the nine CP40's. A second AW hosts the last CP40. The
other two AW's host x-terminals and are used as operator stations.
There is a requirement to upgrade a CP40 to a CP60.
Would it be possible, as an interim measure, to upgrade the two CP hosts to Ver
6.3 (to host the CP60), and if this is done what are possible pitfalls and what
safety measures would need to be implemented to prevent problems??
Thanks for the help.
Regards
Ashley Davey
Software Engineer
African Products (Pty) Ltd
South Africa
WARNING: This e-mail is being sent from African Products (Pty) Limited, and is
intended for the addressee named above. Any unauthorised use or interception of
this e-mail is illegal. The e-mail message or its attachments may contain
confidential or privileged information and may not be copied, forwarded or
disclosed to any unauthorised person. If you are not the named addressee (or
person responsible for forwarding the e-mail to the addressee) please notify us
immediately via return e-mail and destroy the copy you have received. Save for
bona fide company matters, African Products (Pty) Limited accepts no
responsibility for the opinions or the content in this e-mail or its
attachments.
_______________________________________________________________________
This mailing list is neither sponsored nor endorsed by Invensys Process
Systems (formerly The Foxboro Company). Use the info you obtain here at
your own risks. Read http://www.thecassandraproject.org/disclaimer.html
foxboro mailing list: http://www.freelists.org/list/foxboro
to subscribe: mailto:foxboro-request@xxxxxxxxxxxxx?subject=join
to unsubscribe: mailto:foxboro-request@xxxxxxxxxxxxx?subject=leave
Other related posts:
- » [foxboro] Ver 4.3 and 6.3 co-existance