[webproducers] Re: preferences file for MS Project
- From: "Greg Glaser" <gglaser@xxxxxxxxx>
- To: <webproducers@xxxxxxxxxxxxx>
- Date: Tue, 6 Nov 2001 17:00:55 -0600
Believe it - MSP is like a spreadsheet that failed freshman algebra. It's
definitely not a registry problem. Anyway...
This is a tough one. I couldn't duplicate the problem exaclty but I was able
to see 6/1 or 7/1 splits on a 7h or 8h day, respectively. I've got a couple
ideas, though:
> Deleting GLOBAL.MPT won't necessarily eliminate the 'bug.' Some of the
settings, like calendar, will be saved along with the program (there's a
similar example in Excel - you can select an option that hides zero values,
but that setting is saved with the file. The *feature* is from the global
template, but the *setting* is in the file).
> You might check the task's start time by selecting the task and going to
Tools|Check Working time. If this dialog box doesn't have "default Calendar"
selected it might be the cause of your problem.
> Double check your resource's Units - they might be more or less than 100%
after the calendar change. Adjusting to 100% could bring it in line.
> Did you save the file? At any time before you changed the default calendar
(manually or by deleting global.mpt) did you save a baseline? You might try
removing the baseline so you can manipulate the start date.
Hope this helps.
g
-----Original Message-----
From: webproducers-bounce@xxxxxxxxxxxxx
[mailto:webproducers-bounce@xxxxxxxxxxxxx]On Behalf Of Maia Gemmill
Sent: Tuesday, November 06, 2001 3:55 PM
To: webproducers
Subject: [webproducers] Re: preferences file for MS Project
On 11/6/01 4:26 PM, "Greg Glaser" <gglaser@xxxxxxxxx> wrote:
>
> The master template is called GLOBAL.MPT. It's easiest to use windows file
> explorer to search for it. You can delete it - MSProj will create it if it
> can't be found in the expected place.
>
> Almost everything else lives in the registry, but you might want to be
more
> specific about your troubles before you head in there...
OK, here's my head-pounding, hair-pulling issue. Hearst Interactive Studios
officially works a 35-hour week (7-hour days). A while ago, I set the
default calendar time to 35 hours per week. For some reason, though, when I
enter tasks into Project, it stretches tasks out onto an additional day. I
haven't created a totally fresh Project file for a while, but I don't
remember seeing this frustrating behavior before...
Here's what happens:
1. Create task, with duration of one day.
2. Enter single resource, assigned 100%
3. Look at Task Usage view: task is assigned for 6 hours on day one, and 1
hour on day two.
I tossed the Global.mpt file, and now we're back to a 40 hour week, but the
funky task usage persists, only now it's 7 hours on day one and 1 hour on
day two.
What am I missing? There has to be some option or preference that I clicked
ages ago and don't remember. I can't believe that Project is *this*
brain-dead without interference from the user. ;)
- - - - - - - - - - - - - - - - - - - - - -
Maia Gemmill * Production Manager
Hearst Interactive
959 eighth avenue
new york ny 10019
t: 212.649.2336 f: 212.957.8524
mgemmill@xxxxxxxxxxxxxxxxxxxxx
__________________________________________________________________________
Check out www.webproducers.org to easily access list commands like
subscribe, unsubscribe, digest mode, vacation, and to read the list archive.
Questions and comments are welcome just e-mail me, morry@xxxxxxxxxxxxxxxx
__________________________________________________________________________
Check out www.webproducers.org to easily access list commands like subscribe,
unsubscribe, digest mode, vacation, and to read the list archive.
Questions and comments are welcome just e-mail me, morry@xxxxxxxxxxxxxxxx
|

|