Oracle 9.2

We want to schedule a job via DBMS_JOB to run at 12:30am and 12:30pm.
I'd prefer to schedule 1 job to do this rather than 1 job to run at
12:30am and 1 job at 12:30pm (I don't want them to run on top of each
other).

When I schedule the job via this command:

execute dbms_job.submit(job=3D>:jobno, what=3D>'program_name;',
next_date=3D>trunc(sysdate+1)+1/48,
interval=3D>'trunc(SYSDATE+12/24,''HH'')');

It works as expected.  But the problem I have is if the job gets broken
or the db is down the next time it executes it will schedule itself 12
hours in the future- if it happens to run at 2:10am then the next run
would be 2:00pm.  Is there a way with 1 job to force it to only run at
12:30am and 12:30pm regardless of the time of current execution?

Thanks

--
http://www.freelists.org/webpage/oracle-l




[ Home | Signup | Help | Login | Archives | Lists ]

All trademarks and copyrights within the FreeLists archives are owned by their respective owners.
Everything else ©2007 Avenir Technologies, LLC.